ID Task Task Name Duration Start Finish Predecessors 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter

Duration Start Finish Predecessors 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
0 Transnet - Block Valve Lid Replacement 230 days 2023/08/01 2024/07/15
1 Prelims & General Tasks 31 days 2023/08/01 2023/09/12
2 LoA and SLA sign-off 0 days 2023/08/01 2023/08/01 08/01
3 Resource Mobilisation 21 days 2023/08/01 2023/08/29 2
4 Health and Safety File [single file] 21 days 2023/08/01 2023/08/29 2
5 Approval of Health and Safety File 10 days 2023/08/30 2023/09/12 4
6 Site Visits 55 days 2023/08/30 2023/11/14
7 Notification to visit sites 3 days 2023/08/30 2023/09/01 3
8 Conduct site visit to 127 Block Valves (Phase 1A). 22 days 2023/09/04 2023/10/03 7
9 Conduct site visit to 64 Block Valves (Phase 1B). 11 days 2023/10/04 2023/10/18 8
10 Conduct site visit to 63 Block Valves (Phase 2). 11 days 2023/10/19 2023/11/02 9
11 Conduct site visit to 48 Block Valves (Phase 3). 8 days 2023/11/03 2023/11/14 10
12 Phase 1A 195 days 2023/09/19 2024/07/15
13 Design of a reinforced concrete slab - middle of existing concrete lids & 20 days 2023/09/19 2023/10/16 5FS+4 days
sample testing
14 Design of an external locking mechanism to Block Valve Chamber Lid 10 days 2023/09/19 2023/10/02 5FS+4 days
(removable key) & sample testing
15 Approval of design and Sample 5 days 2023/10/17 2023/10/23 14FS+2 days,13
16 Fabrication of 77 reinforced concrete slabs 70 days 2023/10/31 2024/03/04 15FS+5 days
17 Fabrication of 19 reinforced concrete slabs 35 days 2024/02/23 2024/04/11 15FS+5 days,16FS-7 days
18 Fabrication of 19 reinforced concrete slabs 35 days 2024/04/12 2024/05/30 15FS+5 days,17
19 Fabrication of 11 reinforced concrete slabs 21 days 2024/05/31 2024/06/28 15FS+5 days,18
20 Supply, and install reinforced concrete slab and external locking 95 days 2024/03/05 2024/07/15
mechanism to Block Valve Chamber
21 77 reinforced concrete slab (Between Durban & Jameson Park) 77 days 2024/03/05 2024/06/19
15FS+15 days,16
22 19 reinforced concrete slab (Between Jameson Park & Langlaagte) 19 days 2024/04/12 2024/05/08
15FS+15 days,17
23 19 reinforced concrete slab (Between Kendal & Waltloo) 19 days 2024/05/31 2024/06/26
15FS+15 days,18
24 11 reinforced concrete slab (Between Jameson Park & Kendal; 11 days 2024/07/01 2024/07/15
17FS+7
Secunda & Kendal; Kendal & Witbank) days,19
25 Phase completion 0 days 2024/07/15 2024/07/15 24 07/15
26 Phase 1B 105 days 2023/09/06 2024/02/27
27 Design external locking mechanism - Block Valve Chambers (removable 10 days 2023/09/06 2023/09/19 7FS+2 days
key) & sample testing
28 Approval of design and Sample 5 days 2023/10/04 2023/10/10 27,39
29 Fabrication of 22 external locking mechanism 11 days 2023/10/11 2023/10/25 28
30 Fabrication of 22 external locking mechanism 11 days 2023/10/26 2023/11/09 29
31 Fabrication of 19 external locking mechanism 10 days 2023/11/10 2023/11/23 30
32 Supply and install external locking mechanism (removable key) to 69 days 2023/10/26 2024/02/27
Block Valve Chambers
33 22 external locking mechanism (removable key) to Block Valve 22 days 2023/10/26 2023/11/24 28FS+3
Chambers (Between Sasolburg & Klerksdorp; Langlaagte & Tarlton; days,29
34 Talton & Rustenburg)
22 external locking mechanism (removable key) to Block Valve 22 days 2023/11/30 2024/01/26 33FS+3
Chambers (Between Coalbrook & Jameson Park; Jameson Park & days,30
Kendal, Secunda & Kendal; Secunda & Jameson Park)

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Transnet - Block Valve Lid Split External Tasks Inactive Summary Manual Summary Critical
Date: 2023/05/21 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
35 19 external locking mechanism (removable key) to Block Valve 19 days 2024/02/01 2024/02/27 34FS+3
Chambers (Between Jameson Park & Alrode; Coalbrook & Meyerton; days,31
Meyerton & Alrode; Alrode & Airport)
36 Phase completion 0 days 2024/02/27 2024/02/27 35 02/27
37 Phase 2 194 days 2023/09/20 2024/07/15
38 Design reinforced concrete lid - replace existing Steel lids & sample testing
20 days 2023/10/17 2023/11/13 13
39 Design external locking mechanism - Block Valve Chambers (removable 10 days 2023/09/20 2023/10/03 27
key) & sample testing
40 Approval of design and Sample - concrete lids 5 days 2023/11/14 2023/11/20 38
41 Fabrication of 13 reinforced concrete lids 26 days 2023/11/23 2024/01/25 40FS+2 days
42 Fabrication of 16 reinforced concrete lids 32 days 2024/01/26 2024/03/11 40FS+2 days,41
43 Fabrication of 19 reinforced concrete lids 38 days 2024/03/12 2024/05/02 40FS+2 days,42
44 Fabrication of 14 reinforced concrete lids 28 days 2024/05/03 2024/06/11 40FS+2 days,43
45 Approval of design and Sample - locking mechanism 5 days 2023/10/04 2023/10/10 39
46 Fabrication of 13 external locking mechanism 13 days 2023/10/11 2023/10/27 45
47 Fabrication of 16 external locking mechanism 16 days 2023/10/30 2023/11/20 46
48 Fabrication of 19 external locking mechanism 19 days 2023/11/21 2023/12/15 47
49 Fabrication of 14 external locking mechanism 14 days 2024/01/15 2024/02/01 48
50 Supply and install reinforced concrete lid and external locking 112 days 2024/02/09 2024/07/15
mechanism to Block Valves
51 13 Block Valve Chambers (Between Durban & Hillcrest; Hillcrest & Howick)
13 days 2024/02/09 2024/02/27 46FS+10 days,41FS+10 days
52 16 Block Valve Chambers (Between Howick & Ladysmith) 16 days 2024/03/26 2024/04/16 47FS+10 days,42FS+10 days
53 19 Block Valve Chambers (Between Ladysmith & Newcastle; 19 days 2024/05/17 2024/06/12 48FS+10
Newcastle & Quagga) days,43FS+10
54 14 Block Valve Chambers (Between Quagga & Coalbrook) 14 days 2024/06/26 2024/07/15 49FS+10 days,44FS+10 days
55 Removal and transportation of the old Steel Block Valve Lids to the 112 days 2024/02/09 2024/07/15
nearest depot for disposal
56 13 old Steel Block Valve Lids (Between Durban & Hillcrest; Hillcrest & 13 days 2024/02/09 2024/02/27 51SS
Howick)
57 16 old Steel Block Valve Lids (Betwen Howick & Ladysmith) 16 days 2024/03/26 2024/04/16 52SS
58 19 old Steel Block Valve Lids (Between Ladysmith & Newcastle; 19 days 2024/05/17 2024/06/12 53SS
Newcastle & Quagga)
59 14 old Steel Block Valve Lids (Betwen Quagga & Coalbrook) 14 days 2024/06/26 2024/07/15 54SS
60 Modification of existing gearbox to allow the valve to be operated 63 days 2023/11/13 2024/03/06
externally
61 13 existing gearboxes (Between Durban & Hillcrest and Hillcrest & Howick)
13 days 2023/11/13 2023/11/29 46FS+10 days
62 16 existing gearboxes (Betwen Howick & Ladysmith) 16 days 2023/12/05 2024/01/23 47FS+10 days
63 19 existing gearboxes (Between Ladysmith & Newcastle; Newcastle & 19 Quagga)
days 2024/01/29 2024/02/22 48FS+10 days
64 14 existing gearboxes (Betwen Quagga & Coalbrook) 14 days 2024/02/16 2024/03/06 49FS+10 days
65 Core drill 110mm diam. hole in Concrete lid 66 days 2023/11/23 2024/03/21
66 Core drill 13 Concrete lids 46 days 2023/11/23 2024/02/22 40FS+2 days
67 Core drill 16 Concrete lids 56 days 2023/11/23 2024/03/07 40FS+2 days
68 Core drill 19 Concrete lids 66 days 2023/11/23 2024/03/21 40FS+2 days
69 Core drill 14 Concrete lids 49 days 2023/11/23 2024/02/27 40FS+2 days
70 Supply and Install Plastic caps to cover the 110mm diam core drilled hole
70 days 2023/11/23 2024/03/27
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Transnet - Block Valve Lid Split External Tasks Inactive Summary Manual Summary Critical
Date: 2023/05/21 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 2
ID Task Task Name Duration Start Finish Predecessors 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
71 Supply and Install 13 Plastic caps 46 days 2023/11/23 2024/02/22 40FS+2 days
72 Supply and Install 16 Plastic caps 56 days 2023/11/23 2024/03/07 40FS+2 days
73 Supply and Install 19 Plastic caps 66 days 2023/11/23 2024/03/21 40FS+2 days
74 Supply and Install 14 Plastic caps 49 days 2023/11/23 2024/02/27 40FS+2 days
75 Supply 15 Universal T-piece key to fit the extended shafts 15 days 2024/03/07 2024/03/27 64
76 Phase completion 0 days 2024/07/15 2024/07/15 59,75 07/15
77 Phase 3 150 days 2023/11/21 2024/07/15
78 Approval of design and Sample - concrete lids 5 days 2023/11/21 2023/11/27 40
79 Fabrication of reinforced concrete lid as per accepted Phase 2 design 98 days 2023/11/28 2024/05/09
80 14 reinforced concrete lids 28 days 2023/11/28 2024/02/01 78
81 27 reinforced concrete lids 56 days 2024/02/02 2024/04/19 80
82 7 reinforced concrete lids 14 days 2024/04/22 2024/05/09 81
83 Removal and transportation of the old Steel Block Valve Lids to the 83 days 2024/02/02 2024/05/28
nearest depot for disposal
84 14 old Steel Block Valve Lids (Between Durban & Empangeni) 14 days 2024/02/02 2024/02/21 80
85 27 old Steel Block Valve Lids (Between Empangeni & Ingogo) 27 days 2024/04/22 2024/05/28 81
86 7 old Steel Block Valve Lids (Between Ingogo & Secunda) 7 days 2024/05/10 2024/05/20 82
87 Fabrication of external locking mechanism as per accepted Phase 2 design
83 days 2024/02/22 2024/06/17
88 14 external locking mechanisms 14 days 2024/02/22 2024/03/12 84
89 27 external locking mechanisms 14 days 2024/05/29 2024/06/17 85
90 7 external locking mechanisms 14 days 2024/05/21 2024/06/07 86
91 Supply, and installation of a reinforced concrete lid and external 110 days 2024/02/02 2024/07/04
locking mechanism to Block Valve Chambers as per Phase 2 design
92 14 Block Valve Chambers (Between Durban & Empangeni) 14 days 2024/02/02 2024/02/21 80
93 27 Block Valve Chambers (Between Empangeni & Ingogo) 27 days 2024/05/29 2024/07/04 85
94 7 Block Valve Chambers (Between Ingogo & Secunda) 7 days 2024/05/21 2024/05/29 86
95 Modification of existing gearbox to allow the valve to be operated 110 days 2024/02/02 2024/07/04
externally
96 14 existing gearboxes (Between Durban & Empangeni) 14 days 2024/02/02 2024/02/21 92FF
97 27 existing gearboxes (Between Empangeni & Ingogo) 27 days 2024/05/29 2024/07/04 93FF
98 7 existing gearboxes (Between Ingogo & Secunda) 7 days 2024/05/21 2024/05/29 94FF
99 Core drill 110mm diam. hole in Concrete lid 103 days 2024/02/22 2024/07/15
100 Core drill 14 Concrete lids 14 days 2024/02/22 2024/03/12 92
101 Core drill 27 Concrete lids 27 days 2024/06/07 2024/07/15 93FF+7 days
102 Core drill 7 Concrete lids 7 days 2024/05/30 2024/06/07 94
103 Supply and Install Plastic caps to cover the 110mm diam core drilled hole
103 days 2024/02/22 2024/07/15
104 Supply and Install 14 Plastic caps 14 days 2024/02/22 2024/03/12 100FF
105 Supply and Install 27 Plastic caps 27 days 2024/06/07 2024/07/15 101FF
106 Supply and Install 7 Plastic caps 7 days 2024/05/30 2024/06/07 102FF
107 Supply 9 Universal T-piece key to fit the extended shafts 9 days 2024/06/10 2024/06/20 106
108 Phase completion 0 days 2024/07/15 2024/07/15 105,107 07/15

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Transnet - Block Valve Lid Split External Tasks Inactive Summary Manual Summary Critical
Date: 2023/05/21 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress