Reconstruction of Runway (07L/25R) at
RAILCOP Jinnah International Airport (JIAP) Karachi
ID Task Name Start Finish Duration 2023 2024 2025
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
31 7 Ancillary Works Mar 26 '24 Aug 20 '24 148 days Ancillary Works
32 7.1 Runway Marking Water Base May 14 '24 Jun 12 '24 30 days Runway Marking Water Base
33 7.2 Taxi way Marking Water Base Jul 4 '24 Aug 2 '24 30 days Taxi way Marking Water Base
34 7.3 Dismantling, Scarification and Removal of Existing Pavement Structure Mar 26 '24 Apr 14 '24 20 days Dismantling, Scarification and Removal of Existing Pa
35 7.4 Clearing and Grubbing Mar 26 '24 Apr 14 '24 20 days Clearing and Grubbing
36 7.5 Compaction of Natural Ground Surface Apr 2 '24 Apr 26 '24 25 days Compaction of Natural Ground Surface
37 7.6 Granular Sub-base Course Apr 12 '24 May 21 '24 40 days Granular Sub-base Course
38 7.7 Crushed Aggregate base Apr 22 '24 May 31 '24 40 days Crushed Aggregate base
39 7.8 Emulsified Asphalt Prime Coat May 12 '24 Jun 20 '24 40 days Emulsified Asphalt Prime Coat
40 7.9 Emulsified Asphalt Tack Coat Jun 21 '24 Jul 30 '24 40 days Emulsified Asphalt Tack Coat
41 7.10 Asphalt Mix Pavement wearing course Jun 22 '24 Jul 31 '24 40 days
42 7.11 Asphalt Base/Levelling May 13 '24 Jun 21 '24 40 days
43 7.12 Pavement Marking in Non- Reflective TP Paint for lines of 20cm ThicAug 1 '24 Aug 15 '24 15 days
44 7.13 Precast Curb in Concrete Class-A Aug 1 '24 Aug 20 '24 20 days
45 7.14 Reflectorized Aluminum Pavement Stud Aug 1 '24 Aug 15 '24 15 days
46 7.15 Galvanized Wire Mesh Fence 2500mm High Apr 15 '24 Jul 3 '24 80 days
47 8 Storm Water Drainage Jul 9 '23 Jan 11 '24 187 days Storm Water Drainage
48 8.1 Clearing and Grubbing Jul 9 '23 Aug 7 '23 30 days Clearing and Grubbing
49 8.2 Unclassified Excavation including grading compaction Jul 16 '23 Aug 24 '23 40 days Unclassified Excavation including grading compaction
50 8.3 Granular Sub Base Aug 5 '23 Oct 3 '23 60 days Granular Sub Base
51 8.4 Compaction of Natural Ground Jul 16 '23 Aug 24 '23 40 days Compaction of Natural Ground
52 8.5 Lean Concrete Aug 25 '23 Oct 23 '23 60 days Lean Concrete
53 8.6 Grouted Rip Rap Class A Sep 14 '23 Dec 2 '23 80 days Grouted Rip Rap Class A
54 8.7 Dismantling of Existing Drainage Structure Jul 9 '23 Aug 17 '23 40 days Dismantling of Existing Drainage Structure
55 8.8 Stone Masonry dressed uncoursed Sep 14 '23 Dec 2 '23 80 days Stone Masonry dressed uncoursed
56 8.9 Roll Pointing Dec 3 '23 Jan 1 '24 30 days Roll Pointing
57 8.10 Filling / Sealing of cracks in concrete Dec 3 '23 Jan 1 '24 30 days
58 8.11 Reinstatement of road surface Dec 3 '23 Jan 1 '24 30 days
59 8.12 Unclassified Excavation including grading, compaction Sep 14 '23 Oct 23 '23 40 days
60 8.13 Lean Concrete Sep 24 '23 Nov 22 '23 60 days
61 8.14 Miscellaneous structural concrete 4000 psi Oct 14 '23 Jan 1 '24 80 days
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 2
Reconstruction of Runway (07L/25R) at
RAILCOP Jinnah International Airport (JIAP) Karachi
ID Task Name Start Finish Duration 2023 2024 2025
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
62 8.15 Reinforcement as per AASHTO M-31 Grade 60 Oct 4 '23 Dec 12 '23 70 days
63 8.16 PVC Water stopper 8"/10" Size Nov 3 '23 Dec 2 '23 30 days
64 8.17 Premoulded Joint Filler 12mm Dec 13 '23 Jan 11 '24 30 days
65 8.18 One coat of water proofing primer Oct 14 '23 Nov 2 '23 20 days
66 9 Relocation of Utilities Sep 24 '23 Mar 8 '24 167 days Relocation of Utilities
67 9.1 Relocation of Localizer Antenna Foundation Sep 24 '23 Dec 29 '23 97 days Relocation of Localizer Antenna Foundation
68 9.1.1 Structural Excavation in Common Sep 24 '23 Oct 23 '23 30 days Structural Excavation in Common
69 9.1.2 Lean Concrete Oct 24 '23 Dec 2 '23 40 days Lean Concrete
70 9.1.3 Miscellaneous structural concrete 4000 psi Nov 10 '23 Dec 29 '23 50 days Miscellaneous structural concrete 4000 psi
71 9.1.4 Reinforcement as per AASHTO M-31 Grade 60 Nov 3 '23 Dec 22 '23 50 days Reinforcement as per AASHTO M-31 Grade 60
72 9.1.5 Crushed Aggregate Base Course Oct 4 '23 Nov 12 '23 40 days Crushed Aggregate Base Course
73 9.1.6 Dismantling of Structures and Obstructions Sep 24 '23 Oct 23 '23 30 days Dismantling of Structures and Obstructions
74 9.2 Relocation of ASF Check Posts at Both Ends of Runway Oct 24 '23 Mar 8 '24 137 days Relocation of ASF Check Posts at Both Ends of Runway
75 9.2.1 Structural Excavation in Common Nov 3 '23 Dec 2 '23 30 days Structural Excavation in Common
76 9.2.2 Common Backfill Jan 2 '24 Jan 11 '24 10 days Common Backfill
77 9.2.3 Lean Concrete Nov 13 '23 Dec 22 '23 40 days Lean Concrete
78 9.2.4 Miscellaneous structural concrete 4000 psi Nov 30 '23 Jan 28 '24 60 days Miscellaneous structural concrete 4000 psi
79 9.2.5 Reinforcement as per AASHTO M-31 Grade 60 Nov 23 '23 Jan 21 '24 60 days Reinforcement as per AASHTO M-31 Grade 60
80 9.2.6 Stone Soiling Nov 23 '23 Dec 12 '23 20 days Stone Soiling
81 9.2.7 Block Masonry Nov 23 '23 Jan 11 '24 50 days Block Masonry
82 9.2.8 Plaster Jan 29 '24 Feb 17 '24 20 days Plaster
83 9.2.9 Distemper Feb 18 '24 Mar 8 '24 20 days Distemper
84 9.2.10 Dismantling of Structures and Obstructions Oct 24 '23 Nov 2 '23 10 days Dismantling of Structures and Obstructions
85 9.3 Other Utilities Dec 3 '23 Mar 1 '24 90 days Other Utilities
86 9.3.1 Relocation of PAF Aircraft Barriers Dec 3 '23 Mar 1 '24 90 days Relocation of PAF Aircraft Barriers
87 9.3.2 Relocation of Manhole Dec 3 '23 Mar 1 '24 90 days Relocation of Manhole
88 9.3.3 Relocation of Optical Fiber Dec 3 '23 Mar 1 '24 90 days Relocation of Optical Fiber
89 9.3.4 Thrust Boring Dec 3 '23 Mar 1 '24 90 days Thrust Boring
90 10 Site Clearance Aug 20 '24 Aug 20 '24 1 day Site Clearance
91 11 Project Handing Over Aug 21 '24 Aug 21 '24 1 day Project Handing Over