Reconstruction of Runway (07L/25R) at

RAILCOP Jinnah International Airport (JIAP) Karachi


ID Task Name Start Finish Duration 2023 2024 2025
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
0 Construction Schedule Mar 1 '23 Aug 21 '24 540 days
1 1 Notice to Proceed Mar 1 '23 Mar 1 '23 0 days 3/1
2 2 Completion of Project Aug 21 '24 Aug 21 '24 0 days 8/21
3 3 Mobilization Mar 1 '23 Apr 19 '23 50 days Mobilization
4 3.1 Mobilization of Tools, Plants etc. to the site Mar 1 '23 Mar 1 '23 0 days 3/1
5 3.2 Construction of Storage Yards Mar 1 '23 Mar 30 '23 30 days Construction of Storage Yards
6 3.3 Construction of Labor Camps Mar 1 '23 Mar 25 '23 25 days Construction of Labor Camps
7 3.4 Construction of Site Offices etc. Mar 1 '23 Mar 30 '23 30 days Construction of Site Offices etc.
8 3.5 Surveying & Settingout Works Mar 31 '23 Apr 19 '23 20 days Surveying & Settingout Works
9 4 Earth Works Apr 20 '23 Sep 6 '23 140 days Earth Works
10 4.1 Dismantling, Scarification & Removal of Existing Pavement (Runway & Apr 20 '23 Jul 18 '23 90 days Dismantling, Scarification & Removal of Existing Pavement (Runway & Sholders)
11 4.2 Unclassified Excavation including grading compaction May 10 '23 Aug 7 '23 90 days Unclassified Excavation including grading compaction
12 4.3 Clearing and Grubbing Apr 20 '23 Jun 18 '23 60 days Clearing and Grubbing
13 4.4 Compaction of Natural Ground Apr 30 '23 Jun 28 '23 60 days Compaction of Natural Ground
14 4.5 FOE with Excavated Classified Jun 9 '23 Sep 6 '23 90 days FOE with Excavated Classified
15 5 Sub Base & Base Courses Jul 9 '23 Apr 3 '24 270 days Sub Base & Base Courses
16 5.1 Sub base Course Jul 9 '23 Jan 24 '24 200 days Sub base Course
17 5.2 Crushed Aggregate base Course Aug 28 '23 Apr 3 '24 220 days Crushed Aggregate base Course
18 6 Pavement Surface Courses Jun 19 '23 Jul 23 '24 401 days Pavement Surface Courses
19 6.1 Econocrete Base (Lean Concrete) Sep 27 '23 Mar 24 '24 180 days Econocrete Base (Lean Concrete)
20 6.2 Pavement Quality Concrete(700 psi Flexural strength) Oct 17 '23 May 13 '24 210 days Pavement Quality Concrete(700 psi Flexural streng
21 6.3 Saw cutting the Transverse / Contraction joint Nov 16 '23 May 18 '24 185 days Saw cutting the Transverse / Contraction joint
22 6.4 Cutting a slot 12+/- 3mm wide Construction / longitudina Nov 16 '23 May 18 '24 185 days Cutting a slot 12+/- 3mm wide Construction / lon
23 6.5 Bituminous impregnated fibre board Nov 16 '23 May 18 '24 185 days Bituminous impregnated fibre board
24 6.6 Cutting a slot 19+/-3mm wide construction joint between the asphalt sh Nov 16 '23 May 18 '24 185 days Cutting a slot 19+/-3mm wide construction joint
25 6.7 Emulsified Asphalt Prime coat Mar 15 '24 Jun 2 '24 80 days Emulsified Asphalt Prime coat
26 6.8 Emulsified Asphalt Tack coat May 4 '24 Jul 22 '24 80 days Emulsified Asphalt Tack coat
27 6.9 Asphalt Mix Pavement wearing course May 5 '24 Jul 23 '24 80 days Asphalt Mix Pavement wearing course
28 6.10 Asphalt Base/Levelling Mar 16 '24 Jun 3 '24 80 days Asphalt Base/Levelling
29 6.11 Cold Milling (0-50mm) Link Taxiway Jun 19 '23 Aug 17 '23 60 days Cold Milling (0-50mm) Link Taxiway
30 6.12 Needle punch & Thermally Bonded non-woven Geotextile Oct 7 '23 May 3 '24 210 days

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress

Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
Reconstruction of Runway (07L/25R) at
RAILCOP Jinnah International Airport (JIAP) Karachi
ID Task Name Start Finish Duration 2023 2024 2025
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
31 7 Ancillary Works Mar 26 '24 Aug 20 '24 148 days Ancillary Works
32 7.1 Runway Marking Water Base May 14 '24 Jun 12 '24 30 days Runway Marking Water Base
33 7.2 Taxi way Marking Water Base Jul 4 '24 Aug 2 '24 30 days Taxi way Marking Water Base
34 7.3 Dismantling, Scarification and Removal of Existing Pavement Structure Mar 26 '24 Apr 14 '24 20 days Dismantling, Scarification and Removal of Existing Pa
35 7.4 Clearing and Grubbing Mar 26 '24 Apr 14 '24 20 days Clearing and Grubbing
36 7.5 Compaction of Natural Ground Surface Apr 2 '24 Apr 26 '24 25 days Compaction of Natural Ground Surface
37 7.6 Granular Sub-base Course Apr 12 '24 May 21 '24 40 days Granular Sub-base Course
38 7.7 Crushed Aggregate base Apr 22 '24 May 31 '24 40 days Crushed Aggregate base
39 7.8 Emulsified Asphalt Prime Coat May 12 '24 Jun 20 '24 40 days Emulsified Asphalt Prime Coat
40 7.9 Emulsified Asphalt Tack Coat Jun 21 '24 Jul 30 '24 40 days Emulsified Asphalt Tack Coat
41 7.10 Asphalt Mix Pavement wearing course Jun 22 '24 Jul 31 '24 40 days
42 7.11 Asphalt Base/Levelling May 13 '24 Jun 21 '24 40 days
43 7.12 Pavement Marking in Non- Reflective TP Paint for lines of 20cm ThicAug 1 '24 Aug 15 '24 15 days
44 7.13 Precast Curb in Concrete Class-A Aug 1 '24 Aug 20 '24 20 days
45 7.14 Reflectorized Aluminum Pavement Stud Aug 1 '24 Aug 15 '24 15 days
46 7.15 Galvanized Wire Mesh Fence 2500mm High Apr 15 '24 Jul 3 '24 80 days
47 8 Storm Water Drainage Jul 9 '23 Jan 11 '24 187 days Storm Water Drainage
48 8.1 Clearing and Grubbing Jul 9 '23 Aug 7 '23 30 days Clearing and Grubbing
49 8.2 Unclassified Excavation including grading compaction Jul 16 '23 Aug 24 '23 40 days Unclassified Excavation including grading compaction
50 8.3 Granular Sub Base Aug 5 '23 Oct 3 '23 60 days Granular Sub Base
51 8.4 Compaction of Natural Ground Jul 16 '23 Aug 24 '23 40 days Compaction of Natural Ground
52 8.5 Lean Concrete Aug 25 '23 Oct 23 '23 60 days Lean Concrete
53 8.6 Grouted Rip Rap Class A Sep 14 '23 Dec 2 '23 80 days Grouted Rip Rap Class A
54 8.7 Dismantling of Existing Drainage Structure Jul 9 '23 Aug 17 '23 40 days Dismantling of Existing Drainage Structure
55 8.8 Stone Masonry dressed uncoursed Sep 14 '23 Dec 2 '23 80 days Stone Masonry dressed uncoursed
56 8.9 Roll Pointing Dec 3 '23 Jan 1 '24 30 days Roll Pointing
57 8.10 Filling / Sealing of cracks in concrete Dec 3 '23 Jan 1 '24 30 days
58 8.11 Reinstatement of road surface Dec 3 '23 Jan 1 '24 30 days
59 8.12 Unclassified Excavation including grading, compaction Sep 14 '23 Oct 23 '23 40 days
60 8.13 Lean Concrete Sep 24 '23 Nov 22 '23 60 days
61 8.14 Miscellaneous structural concrete 4000 psi Oct 14 '23 Jan 1 '24 80 days

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress

Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
Reconstruction of Runway (07L/25R) at
RAILCOP Jinnah International Airport (JIAP) Karachi
ID Task Name Start Finish Duration 2023 2024 2025
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
62 8.15 Reinforcement as per AASHTO M-31 Grade 60 Oct 4 '23 Dec 12 '23 70 days
63 8.16 PVC Water stopper 8"/10" Size Nov 3 '23 Dec 2 '23 30 days
64 8.17 Premoulded Joint Filler 12mm Dec 13 '23 Jan 11 '24 30 days
65 8.18 One coat of water proofing primer Oct 14 '23 Nov 2 '23 20 days
66 9 Relocation of Utilities Sep 24 '23 Mar 8 '24 167 days Relocation of Utilities
67 9.1 Relocation of Localizer Antenna Foundation Sep 24 '23 Dec 29 '23 97 days Relocation of Localizer Antenna Foundation
68 9.1.1 Structural Excavation in Common Sep 24 '23 Oct 23 '23 30 days Structural Excavation in Common
69 9.1.2 Lean Concrete Oct 24 '23 Dec 2 '23 40 days Lean Concrete
70 9.1.3 Miscellaneous structural concrete 4000 psi Nov 10 '23 Dec 29 '23 50 days Miscellaneous structural concrete 4000 psi
71 9.1.4 Reinforcement as per AASHTO M-31 Grade 60 Nov 3 '23 Dec 22 '23 50 days Reinforcement as per AASHTO M-31 Grade 60
72 9.1.5 Crushed Aggregate Base Course Oct 4 '23 Nov 12 '23 40 days Crushed Aggregate Base Course
73 9.1.6 Dismantling of Structures and Obstructions Sep 24 '23 Oct 23 '23 30 days Dismantling of Structures and Obstructions
74 9.2 Relocation of ASF Check Posts at Both Ends of Runway Oct 24 '23 Mar 8 '24 137 days Relocation of ASF Check Posts at Both Ends of Runway
75 9.2.1 Structural Excavation in Common Nov 3 '23 Dec 2 '23 30 days Structural Excavation in Common
76 9.2.2 Common Backfill Jan 2 '24 Jan 11 '24 10 days Common Backfill
77 9.2.3 Lean Concrete Nov 13 '23 Dec 22 '23 40 days Lean Concrete
78 9.2.4 Miscellaneous structural concrete 4000 psi Nov 30 '23 Jan 28 '24 60 days Miscellaneous structural concrete 4000 psi
79 9.2.5 Reinforcement as per AASHTO M-31 Grade 60 Nov 23 '23 Jan 21 '24 60 days Reinforcement as per AASHTO M-31 Grade 60
80 9.2.6 Stone Soiling Nov 23 '23 Dec 12 '23 20 days Stone Soiling
81 9.2.7 Block Masonry Nov 23 '23 Jan 11 '24 50 days Block Masonry
82 9.2.8 Plaster Jan 29 '24 Feb 17 '24 20 days Plaster
83 9.2.9 Distemper Feb 18 '24 Mar 8 '24 20 days Distemper
84 9.2.10 Dismantling of Structures and Obstructions Oct 24 '23 Nov 2 '23 10 days Dismantling of Structures and Obstructions
85 9.3 Other Utilities Dec 3 '23 Mar 1 '24 90 days Other Utilities
86 9.3.1 Relocation of PAF Aircraft Barriers Dec 3 '23 Mar 1 '24 90 days Relocation of PAF Aircraft Barriers
87 9.3.2 Relocation of Manhole Dec 3 '23 Mar 1 '24 90 days Relocation of Manhole
88 9.3.3 Relocation of Optical Fiber Dec 3 '23 Mar 1 '24 90 days Relocation of Optical Fiber
89 9.3.4 Thrust Boring Dec 3 '23 Mar 1 '24 90 days Thrust Boring
90 10 Site Clearance Aug 20 '24 Aug 20 '24 1 day Site Clearance
91 11 Project Handing Over Aug 21 '24 Aug 21 '24 1 day Project Handing Over

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress

Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone