You are on page 1of 2

SAUDI ARAMCO ID/PID - REV 1 - 18-May-05 (Standards Cutoff - August 2004)

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Asphalt Paving SATIP-Q-006-02 18-May-05 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Aggregate Subbase and Base Course SAIC-Q-


1.1
Materials Test Reports
SAIC-Q-1035
1035
RH1 R1
SAIC-Q-
1.2 Asphalt Mix Design Review SAIC-Q-1036
1036
RH1 RH1
RECEIVING
2.0
INSPECTION
S. ARAMCO - Witness delivery of subbase and
Subbase and Aggregate Base Course SAIC-Q-
2.1
Material Receiving Inspection
SAIC-Q-1037
1037
W1 W2 aggregate base materials for the first 2 delivery days,
and once every 5 delivery days thereafter.

3.0 INSTALLATION

Grades, Elevation and Surface SAIC-Q-


3.1
Preparation Inspection
SAIC-Q-1039
1039
W1 S

Foamed Asphalt Stabilization Inspection Refer to SATIP-Q-006-03 for Foamed Asphalt


3.2
(If Required) Stabilization
Placement and Compaction of Subbase
SAIC-Q-
3.3 and Aggregate Base Course Material SAIC-Q-1040
1040
W1 S
Inspection
SAIC-A- S. ARAMCO - Witness first 3 occurences, and once
3.4 Compaction Testing SAIC-A-1005
1005
W1 W2 every 5 occurences thereafter.
Prime Coating and Tack Coating SAIC-Q-
3.5
Inspection
SAIC-Q-1041
1041
H1 H1
Asphaltic Concrete Receiving,
SAIC-Q-
3.6 Placement/Compaction of Binder and SAIC-Q-1061
1061
W1 W1
Wearing Courses Inspection
Contractor QC - Witness coring of asphalt samples as
SAIC-Q- follows: first 10% and last 10% of the number of cores
3.7 Asphalt Core Density Testing SAIC-Q-1043
1043
W2 S for each layer of pavement. S. ARAMCO - surveillance
for the first 5% and the last 5% of cores.
SAIC-Q-
3.8 Asphalt Paving Final Inspection SAIC-Q-1044
1044
W1 W1
4.0 PRE-COMMISSIONING

Page 1 of 2
SAUDI ARAMCO ID/PID - REV 1 - 18-May-05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Asphalt Paving SATIP-Q-006-02 18-May-05 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

4.1 N/A

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
1 the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 sample Review of Documents S Surveillance

Page 2 of 2