Professional Documents
Culture Documents
00 30-Jun-16
Foam Generating Equipment - Installation Insp & Testing SAIC-B-2014 15-Nov-17 MECH
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
NCRs (damages upon receipt) are resolved or detail final disposition & Sch Q, Att III,
A2
resolution. Punch list items (on receipt) are identified for follow-up Para. 3.24
Protect oil loading piers, platforms, sea islands, oil tankers, & other craft in
harbor, offshore producing operations & associated cargo piers (Use
SAES-B-019,
A7 SAES-B-060 & SAES-B-009 as detailed checklists). Firefighting tug
Para. 5.6
boats and other selected launches are equipped with foam
monitors/tanks to supplement installed system facilities.
B Foam Requirements
Foam concentrate is supplied in 208 liter (55 U.S. gallon) mild steel with
polyethylene lined drums as follows:
A) Each container shall have three labels written in English.
21-SAMSS-011,
B2 B) Two labels are centrally positioned, directly
Section 6
opposite each other.
C) The third label is located centrally on the top of the container.
D) The labels are clearly legible & permanently attached to container
Foam Generating Equipment - Installation Insp & Testing SAIC-B-2014 15-Nov-17 MECH
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Foam systems are examined visually to determine that they have been
properly installed as follows:
A) They conform with installation plans
B) Continuity of piping exists
NFPA 11,
to assure system operability C)
C1
Removal of temporary blinds has been accomplished
Section 11.1
D) Valves, controls & gauges (for operation) are accessible.
E) Vapor seals (where applicable) have
been properly installed. F) Devices have
proper identification and operating instructions.
NFPA 11,
Flush all foam system piping after installation using normal water supply
C2
(foam-forming materials are shut off)
Section 11.2
Flushing to remove foreign materials in both underground (UG) and NFPA 11,
C3 aboveground (AG) water supply mains during installation is completed
before connection is made to system piping Section 11.2
NFPA 11,
Minimum rate of flow for flushing is not less than the water demand
C4
rate of the system, as determined by system design.
Section 11.2
NFPA 11,
During flushing, flow is continued for enough time to ensure thorough
C5
cleaning of lines.
Section 11.2
NFPA 11,
Where flushing cannot be accomplished, pipe interiors are carefully
C6
visually examined for cleanliness during installation.
Section 11.2
Equipment is tested by qualified personnel that perform a complete check NFPA 11,
C7 of control circuits & systems to ensure proper operation & supervision in
the event of failure. Section 11.5
NFPA 11,
Tests are adequate to determine that the system has been properly
C8
installed and that it functions as intended. Section 10.3
Section 11.3
Hydrotest all equipment piping for 2-hour hydrostatic pressure gauge NFPA 11,
C9 test at 200 psi or 50 psi in excess of the maximum pressure anticipated,
whichever is greater. Hydrotest has been accepted. Section 11.4
NFPA 11,
Normally dry horizontal piping has proper drainage pitch (slope) per
C10
approved drawings to permit self drainage.
Section 11.4
Functional Test ensures proper operation (devices & equipment):
Total flood system automatic closing devices (doors, NFPA 11,
C11 windows) conveyor openings, automatic equipment interlocks, automatic
opening of heat smoke vents or ventilators function properly. Section 11.5
Foam Generating Equipment - Installation Insp & Testing SAIC-B-2014 15-Nov-17 MECH
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
NFPA 11,
Operating instructions (from supplier) are followed. Device identification
C12
is checked and found to be correct.
Section 11.5
Flow tests ensure the hazard is fully protected with data required:
A) Static water pressure
B) Residual water pressure at control valve & remote reference point in
the system NFPA 11,
C13 C) Actual discharge rate
D) Consumption rate of foam-producing material Section 11.6
E) Concentration of the foam solution
F) Foam quality (expansion & 1/4 drain time) or foam discharge is
conducted or the foam discharge is visually inspected
NFPA 11,
After completion of acceptance tests using foam, systems are flushed &
C14
restored to operational condition.
Section 11.7
Foam Generating Equipment - Installation Insp & Testing SAIC-B-2014 15-Nov-17 MECH
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
REFERENCE DOCUMENTS:
1- Schedule Q, Project Specific (Mar 2013)
2- Saudi Aramco GI-1781.001 -- Inspection, Test, and Maintenance of Fire Protection Equipment, 3 January 2009
3- SAES-B-019 -- Portable, Mobile and Special Fixed Firefighting Equipment, (10 December 2013)
4- 21-SAMSS-011 -- Fluroprotein Foam Concentrate for MTBE Hydrocarbon Fires, 28 November 2011
5- NFPA 11 -- Standards for Low, Medium & High Expansion Foam & Mobile Foam Apparatus, 2016 Edition
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection:
T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
Foam Generating Equipment - Installation Insp & Testing SAIC-B-2014 15-Nov-17 MECH
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
QC Supervisor Proponent and Others
Quality Record Approved:
T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date: