00 30-Sep-17
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements
Prior to entering service, all new fire extinguishers to be installed have
been delivered to Local Fire Control Unit for inspection (using GI-1781 GI-1781.001,
A1
checklists), commissioning, tagging, & SA numbering. Para 5.12.1
Hand-type portable extinguishers in process plant areas are installed SAES-B-019 Para
B1
at 30 m intervals. 4.3.1
Where extinguishers protect individual equipment, they are located at SAES-B-019 Para
B2
least 7.5 m from equipment. 4.3.2
Placement of portable extinguishers in buildings shall comply with Section SAES-B-019 Para
B3
906, SAES-M-100. 4.3.3
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Extinguishers weighing more than 18 kg are mounted so that tops are SAES-B-019 Para
B10
not more than 1.0 meters above floors or deck levels 4.5
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
C) Wheels turn freely & tires are inflated properly in good condition.
E) Tamper seal and safety pin are intact.
F) Nitrogen pressure gauge reads full (at least 1600 psi). GI-1781.001,
D1 G) Extinguisher has no obvious damage or corrosion. Supplement 10 &
H) Rubber hose is coiled properly and in good condition. 11
i) Nozzle moves freely, is in holder, unplugged & in good condition.
J) Dry chemical level and type is correct with no caking.
K) Cap gasket is in good condition
L) Bursting disc is intact.
M) Hydrotest date from manufacturel is shown on
label.
N) Inspection tag exists showing last inspection date.
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
REMARKS:
REFERENCE DOCUMENTS:
1- Schedule Q (Project Specific)
2- Saudi Aramco GI-1781.001 -- Inspection, Test, and Maintenance of Fire Protection Equipment, 3 January 2009
3- SAES-B-019 -- Portable, Mobile and Special Fixed Firefighting Equipment, (22 July 2012)
4- NFPA 10 -- Standard for Portable Fire Extinguishers, 2013 Edition
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date: