SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13 Note: For Maintain Potential

-13 Note: For Maintain Potential Projects usage only.


SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

SATIP-O-101-01
Security Fencing & Gates, (Type SSD/1 Standard Security Fence) 30-Apr-13 CIVIL
MP
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

SAIC-Q-
1.1 Concrete Mix Design Approval SAIC-Q-1006
1006 RH RH

RECEIVING
2.0
INSPECTION

Fence and Gates Components Receiving SAIC-O-


2.1
Inspection- SSD/1 Fence
SAIC-O-1001
1001 I W

Review of 28-day compressive strength of concrete


Pre-Cast Posts Receiving Inspection for SAIC-O-
2.2
SSD/1 Fence
SAIC-O-1002
1002 I W cylinder samples for Pre-Cast Posts from Saudi Aramco-
approved independent laboratory.

3.0 INSTALLATION

SSD/1 Location, Depth of Trench/ SAIC-O-


3.1
Boreholes & Elevations Inspection
SAIC-O-1003
1003 I S

SAIC-O-
3.2 Pre-pour Inspection for SSD/1 Fence SAIC-O-1004
1004 H S

Concrete Sampling, Testing & Placement SAIC-Q-


3.3
Inspection
SAIC-Q-1060
1060 I S

Cast-In-Place Concrete Finishing and SAIC-Q-


3.4
Curing Inspection
SAIC-Q-1015
1015 I S

SAIC-O-
3.5 Final Inspection for SSD/1 Fence SAIC-O-1005
1005 I W

4.0 PRE-COMMISSIONING

4.1 Not Applicable

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13 Note: For Maintain Potential Projects usage only.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

SATIP-O-101-01
Security Fencing & Gates, (Type SSD/1 Standard Security Fence) 30-Apr-13 CIVIL
MP
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
1 the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection/Test