TAISEI – DMCI JOINT VENTURE

North – South Commuter Railway Project (CP01)


Elevated Structures 6 Stations and Depot

Oct. 5, 2021

UNLOADING BAY
DEPOT - CIVIL
TAISEI – DMCI JOINT VENTURE
North – South Commuter Railway Project (CP01)
Elevated Structures 6 Stations and Depot

Item
Activity Unit Quantity Start Date Finish Date Remarks
No.

Unloading Bay 10-Sep-21 10-Nov-21


A Subbase 10-Sep-21 06-Nov-21
A-2, B-2, C-2 m3 50.86 10-Sep-21 16-Sep-21 Completed
A-1. A-3, A-4 m
3
97.37 25-Sep-21 01-Oct-21 Completed
B-1, B-3, B-4 m
3
88.02 07-Oct-21 13-Oct-21 Completed
C-1, C-3, C-4 m
3
51.65 19-Oct-21 25-Oct-21
D-4 m
3
21.80 03-Nov-21 06-Nov-21

B PCC Pavement 22-Sep-21 10-Nov-21


A-2 m
2
109.77 22-Sep-21 26-Sep-21 Completed
B-2 & C2 m
2
144.50 27-Sep-21 01-Oct-21 Completed
A-1 m
2
163.27 02-Oct-21 05-Oct-21
A-3 m
2
163.35 06-Oct-21 09-Oct-21
A-4 m
2
160.23 10-Oct-21 13-Oct-21
B-1 m
2
104.72 14-Oct-21 17-Oct-21
B-3 m 2
163.23 18-Oct-21 21-Oct-21
B-4 m
2
172.16 22-Oct-21 25-Oct-21
C-1 & C3 m
2
68.09 26-Oct-21 29-Oct-21
C-4 m
2
190.17 03-Nov-21 06-Nov-21
D-4 m
2
109.00 07-Nov-21 10-Nov-21

C Unloading Bay Pit 10-Sep-21 24-Oct-21


Excavation m
3
166.63 10-Sep-21 11-Sep-21 Completed
Blinding Concrete m
3
9.99 12-Sep-21 13-Sep-21 Completed
Rebar Installation kg 14,273.16 14-Sep-21 26-Sep-21 Completed
Structural Concrete m
3
70.42 27-Sep-21 28-Oct-21
Foundation including Kicker m
3
39.39 27-Sep-21 29-Sep-21 Completed
Wall m
3
15.01 30-Sep-21 12-Oct-21 Completed
Topping Slab m3 14.40 13-Oct-21 15-Oct-21
Support Post m
3
1.62 16-Oct-21 28-Oct-21
Backfilling lot 1.00 18-Oct-21 24-Oct-21

D Curing of Support Post lot 1.00 29-Oct-21 05-Nov-21

3 Rail Support W10x49


Delivery on Site 29-Oct-21 29-Oct-21
Preparatory Works Bolt Hole Drilling, Cutting and Beveling 03-Nov-21 08-Nov-21
Paint
1st Coat - Zinc Primer 09-Nov-21 09-Nov-21
2nd Coat - Epoxy Coating 16-Nov-21 16-Nov-21
DFT Testing 17-Nov-21 17-Nov-21
Installation and Grouting
Installation of W10x49 at Support Post 10-Nov-21 11-Nov-21
Alligment and Tack Welding at Joint Connection 10-Nov-21 11-Nov-21
Grouting of Support Post 11-Nov-21 11-Nov-21
Full Penetration Welding Works 12-Nov-21 14-Nov-21
NDT Testing
Visual and Ultrasonic Testing 13-Nov-21 15-Nov-21
Build-Up Weld 13-Nov-21 15-Nov-21
TAISEI – DMCI JOINT VENTURE
North – South Commuter Railway Project (CP01)
Elevated Structures 6 Stations and Depot

CP04 ACCESS
TAISEI – DMCI JOINT VENTURE
North – South Commuter Railway Project (CP01)
Elevated Structures 6 Stations and Depot

Unloading Bay:

Oct 22 2021 Oct 26 2021


Oct 11,2021
Oct 19 2021
Oct 15,2021
Oct 9,2021 Oct 17 2021

Completed Target to Concrete


TAISEI – DMCI JOINT VENTURE
North – South Commuter Railway Project (CP01)
Elevated Structures 6 Stations and Depot

Unloading-Bay Pit Preparation for Backfilling


TAISEI – DMCI JOINT VENTURE
North – South Commuter Railway Project (CP01)
Elevated Structures 6 Stations and Depot

Unloading-Bay
TAISEI – DMCI JOINT VENTURE
North – South Commuter Railway Project (CP01)
Elevated Structures 6 Stations and Depot