NATIONAL GRID SA

Project Name: AL ARIDA 132/33 KV S/S


Contract No. : 4400006058 THREE WEEKS WORK SCHEDULE
Three Weeks Look ahead # 13
Date : 7.01.2017
Last week This week Next week
31/12 01/1 02/1 03/1 04/1 05/1 06/1 07/1 08/1 09/1 10/1 11/1 12/1 13/1 14/1 15/1 16/1 17/1 18/1 19/1 20/1
NO. WORK DESCRIPTION SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI
% Co.

A 132 KV GIS Building


Formwork and steel re-bars for corbels & intermediate
1 beams 100%

2 Casting concrete for corbels & intermediate beams 100%

Formwork and steel re-bars for top portion of G.F


3 columns & fire walls 40%

Casting concrete for top portion of G.F columns & fire


4 walls 0%

Formwork, steel re-bars and casting concrete for roof


5 beams 0%

Formwork, steel re-bars and casting concrete for main


6 staircase 55%

7 Block works & plastering for G.F walls 20%

8 Installation of runway beams for OHC 0%

Application of painting system for walls interior surfeces


9 & ceiling soffit at cable basement 35%

B 33 KV SWGR Building

1 Formwork and steel re-bars for roof beams 100%

2 Casting concrete for roof beams 100%

3 Block works & plastering for G.F walls 20%

Application of painting system for walls interior surfeces


4 & ceiling soffit at cable basement 35%

C Control Building

1 Formwork and steel re-bars for roof beams 100%

2 Casting concrete for roof beams 100%

Formwork, steel re-bars and casting concrete for last


3 remaining portion of tie beams 90%

4 Backfilling up to F.L of slab on grade 65%

5 Casting lean concrete for slab on grade 0%

Application of W/P membrane & casting protection


6 screed above lean concrete for slab on grade 0%

7 Steel re-bars and casting concrete for slab on grade 0%

8 Block works & plastering for G.F walls 20%

M.V & H.V Cable Trenches and CSE Found at 132/33


D KV Power Transfomer Area
Formwork & steel re-bars for strip footing of HV cable
1 trench & CSE found at 100 MVA Trans "T601" area 100%

Casting concrete for strip footing of HV cable trench &


2 CSE found at 100 MVA Trans "T601" area 100%

Formwork & steel re-bars for walls of MV & HV cable


3 trench and CSE pedestals 20%

Casting concrete for walls of MV & HV cable trench and


4 CSE pedestals 0%

E Oil Tank

1 Formwork and steel re-bars for raft foundation 100%

2 Casting concrete for raft foundation 100%

3 Formwork and steel re-bars for walls 100%

4 Casting concrete for walls 100%

5 Formwork and steel re-bars for roof slab 0%

6 Casting concrete for roof slab 0%

Page : 1 of 1