ASSIGNMENT:
PROJECT PLANNING AND REPORTING
Preliminary and General Substructure Superstructure Finishes Electrical Works Sanitary Works
Piling Frame
Contractor’s site management Sawn formwork, steel reinforcement, Floor Finishes
The provision of underground
and personnel Supply and transport R.C vibrated concrete to ground column Internal Cold-water system
Floor tiles including toilet electrical pipe sleeve
Contractor’s Site Office square pile Sawn formwork, steel reinforcement, Internal Sanitary System
Parquet flooring Supply and install UPVC pipes
Worker’s Quarters and Services Excavation from existing ground vibrated concrete to first floor beam
Sawn formwork, steel reinforcement, on concrete slab and brick wall
Mobilization and demobilization level, partly backfill and
vibrated concrete to first floor column Supply and install the electrical
of excavator and lorry for remainder cart away for pile
excavation works Sawn formwork, steel reinforcement, wiring
cap, ground beam and slab
vibrated concrete to first floor slab Supply and install the electrical
Mobilization and demobilization Handle, pitch and drive R.C Sawn formwork, steel reinforcement, fittings and switch board
of piling rig square pile Wall Finishes
vibrated concrete to roof beam
Mobilization and demobilization Jointing pile by butt welding
of mobile cane for roof works External wall plastering
Hack-off/cut-off pile heads and
Internal wall plastering
connect to pile cap
Roof Wall tiles
Timber Roof Truss Wall painting
Roof covering Wall flashing
Gutter and rainwater goods Chamfered and rebated timber
skirting
Formwork Staircase
Structural Work on Staircase
Sawn formwork, steel Finishes works on staircase
reinforcement, vibrated Ceiling Finishes
concrete to pile cap and stump Ceiling frame and finishing
Sawn formwork, steel Ceiling Painting
reinforcement, vibrate concrete Wall
to ground beam Well burnt clay brick on 115mm
Sawn formwork, steel thick external brick wall
reinforcement, vibrated Well burnt clay brick on 115mm
concrete to ground slab thick internal brick wall
Window
Window Concrete Lintel
Window frame and finishing
Door
Door Concrete Lintel
Door Frame
Door Leaf
Door Painting
Iron mongery
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of 60 days Fri 1/12/23 Tue 13/2/24
excavator and lorry for excavation
7 Mobilization and demobilization of 40 days Fri 1/12/23 Thu 18/1/24
piling rig
8 Mobilization and demobilization of 55 days Sat 15/6/24 Wed
mobila crane for roof works 21/8/24
9 Substructure 70 days Wed 1/11/23 Tue 23/1/24
10 Piling 70 days Wed 1/11/23 Tue 23/1/24
11 Supply and transport R.C square pile 20 days Wed 1/11/23 Thu
23/11/23
12 Excavation from existing ground 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
16 Formwork 25 days Sat 23/12/23 Tue 23/1/24
Page 1
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
17 Sawn formwork, steel 20 days Sat 23/12/23 Wed
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
Page 2
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
29 Roof Covering 20 days Fri 19/7/24 Mon 12/8/24
30 Gutter and rainwater goods 10 days Tue 13/8/24 Fri 23/8/24
31 Staircase 45 days Wed 12/6/24 Tue 6/8/24
32 Structural Work on Staircase 25 days Wed 12/6/24 Fri 12/7/24
33 Finishes Works on Staircase 20 days Sat 13/7/24 Tue 6/8/24
34 Wall 80 days Sat 6/4/24 Thu 18/7/24
35 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
Page 3
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
53 External Wall Plastering 30 days Fri 19/7/24 Fri 23/8/24
54 Wall tiles 20 days Tue 23/7/24 Wed 14/8/24
55 Wall Painting 30 days Thu 25/7/24 Wed 28/8/24
56 Wall flashing 20 days Fri 26/7/24 Sat 17/8/24
57 Chamfered and rebated timber 30 days Thu 1/8/24 Thu 5/9/24
skirting
58 Ceiling Finishes 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing 15 days Fri 19/7/24 Tue 6/8/24
60 Ceiling Painting 20 days Wed 7/8/24 Thu 29/8/24
61 Electrical Works 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 20 days Fri 19/7/24 Mon
and switch board 12/8/24
66 Sanitary Works 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system 45 days Wed 12/6/24 Tue 6/8/24
68 Internal Sanitary System 45 days Sat 6/7/24 Thu 29/8/24
Page 4
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of 60 days Fri 1/12/23 Tue 13/2/24
excavator and lorry for excavation
7 Mobilization and demobilization of 40 days Fri 1/12/23 Thu 18/1/24
piling rig
8 Mobilization and demobilization of 55 days Sat 15/6/24 Wed
mobila crane for roof works 21/8/24
9 Substructure 70 days Wed 1/11/23 Tue 23/1/24
10 Piling 70 days Wed 1/11/23 Tue 23/1/24
11 Supply and transport R.C square pile 20 days Wed 1/11/23 Thu
23/11/23
12 Excavation from existing ground 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
16 Formwork 25 days Sat 23/12/23 Tue 23/1/24
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 1
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
17 Sawn formwork, steel 20 days Sat 23/12/23 Wed
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 2
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
29 Roof Covering 20 days Fri 19/7/24 Mon 12/8/24
30 Gutter and rainwater goods 10 days Tue 13/8/24 Fri 23/8/24
31 Staircase 45 days Wed 12/6/24 Tue 6/8/24
32 Structural Work on Staircase 25 days Wed 12/6/24 Fri 12/7/24
33 Finishes Works on Staircase 20 days Sat 13/7/24 Tue 6/8/24
34 Wall 80 days Sat 6/4/24 Thu 18/7/24
35 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 3
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
53 External Wall Plastering 30 days Fri 19/7/24 Fri 23/8/24
54 Wall tiles 20 days Tue 23/7/24 Wed 14/8/24
55 Wall Painting 30 days Thu 25/7/24 Wed 28/8/24
56 Wall flashing 20 days Fri 26/7/24 Sat 17/8/24
57 Chamfered and rebated timber 30 days Thu 1/8/24 Thu 5/9/24
skirting
58 Ceiling Finishes 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing 15 days Fri 19/7/24 Tue 6/8/24
60 Ceiling Painting 20 days Wed 7/8/24 Thu 29/8/24
61 Electrical Works 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 20 days Fri 19/7/24 Mon
and switch board 12/8/24
66 Sanitary Works 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system 45 days Wed 12/6/24 Tue 6/8/24
68 Internal Sanitary System 45 days Sat 6/7/24 Thu 29/8/24
Project: Master Workprogramm Milestone Manual Task External Tasks Manual Progress
Date: Tue 19/12/23 Summary Duration-only External Milestone
Page 4
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of 60 days Fri 1/12/23 Tue 13/2/24
excavator and lorry for excavation
works
7 Mobilization and demobilization of 40 days Fri 1/12/23 Thu 18/1/24
piling rig
13 Handle, pitch and drive R.C square 25 days Fri 24/11/23 Fri 22/12/23
pile
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Master Workprogramm
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 19/12/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 1
ID Task Task Name Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
29 Roof Covering 20 days Fri 19/7/24 Mon 12/8/24
30 Gutter and rainwater goods 10 days Tue 13/8/24 Fri 23/8/24
31 Staircase 45 days Wed 12/6/24 Tue 6/8/24
32 Structural Work on Staircase 25 days Wed 12/6/24 Fri 12/7/24
33 Finishes Works on Staircase 20 days Sat 13/7/24 Tue 6/8/24
34 Wall 80 days Sat 6/4/24 Thu 18/7/24
35 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
63 Supply and install UPVC pipes on 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Master Workprogramm
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 19/12/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 2
ID Task Task Name December Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 11% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 11% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 8% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square 100% 20 days Wed 1/11/23 Thu 100%
pile 23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and
remainder cart away for pile cap,
ground beam and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name December Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical 0% 20 days Thu 18/1/24 Fri 9/2/24
wiring
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name January Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 19% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 20% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 14% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 14% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 14% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name January Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
62 The provision of underground electrical 12% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 70% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name February Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 26% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 26% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 25% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 25% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 25% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square 100% 20 days Wed 1/11/23 Thu 100%
pile 23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and
remainder cart away for pile cap,
ground beam and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name February Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical 100% 20 days Thu 18/1/24 Fri 9/2/24
wiring
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name March 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 34% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 44% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 40% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 40% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 40% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name March 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
62 The provision of underground electrical 36% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name April 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 43% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 56% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 55% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 55% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 55% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name April 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
62 The provision of underground electrical 48% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name May 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 51% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 69% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 70% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 70% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 70% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name May 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
62 The provision of underground electrical 60% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name June 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 61% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 72% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 71% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 71% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 71% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name June 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 65% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 65% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
49 Floor tiles including toilet 90% 20 days Wed 12/6/24 Fri 5/7/24
62 The provision of underground electrical 78% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name July 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 73% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 74% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 72% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 72% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 72% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name July 2024 Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 90% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
40 Window frame and finishing 90% 15 days Fri 19/7/24 Tue 6/8/24
49 Floor tiles including toilet 100% 20 days Wed 12/6/24 Fri 5/7/24
59 Ceiling frame and finishing 80% 15 days Fri 19/7/24 Tue 6/8/24
62 The provision of underground electrical 80% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 25% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 60% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name August Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 84% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 77% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 73% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 73% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 73% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
30 Gutter and rainwater goods 100% 10 days Tue 13/8/24 Fri 23/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name August Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 100% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
40 Window frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
49 Floor tiles including toilet 100% 20 days Wed 12/6/24 Fri 5/7/24
57 Chamfered and rebated timber 70% 30 days Thu 1/8/24 Thu 5/9/24
skirting
59 Ceiling frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
62 The provision of underground electrical 81% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 30% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 100% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name September Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 93% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 87% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 85% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 85% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 85% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
30 Gutter and rainwater goods 100% 10 days Tue 13/8/24 Fri 23/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name September Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 100% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
40 Window frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
49 Floor tiles including toilet 100% 20 days Wed 12/6/24 Fri 5/7/24
57 Chamfered and rebated timber 100% 30 days Thu 1/8/24 Thu 5/9/24
skirting
59 Ceiling frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
62 The provision of underground electrical 100% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 75% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 100% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name October Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE 100% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works 100% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management 100% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office 100% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies 100% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
30 Gutter and rainwater goods 100% 10 days Tue 13/8/24 Fri 23/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name October Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase 100% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm 100% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
40 Window frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
49 Floor tiles including toilet 100% 20 days Wed 12/6/24 Fri 5/7/24
57 Chamfered and rebated timber 100% 30 days Thu 1/8/24 Thu 5/9/24
skirting
59 Ceiling frame and finishing 100% 15 days Fri 19/7/24 Tue 6/8/24
62 The provision of underground electrical 100% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on 100% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring 100% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings 100% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost November Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM47,158.00 4% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM5,175.00 4% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM2,925.00 5% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM1,250.00 5% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM1,000.00 5% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM0.00 0% 60 days Fri 1/12/23 Tue 13/2/24
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM0.00 0% 40 days Fri 1/12/23 Thu 18/1/24
piling rig
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM2,185.00 20% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM6,204.00 24% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding RM8,250.00 RM1,980.00 24% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and RM6,725.00 RM1,614.00 24% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
18 Sawn formwork, steel RM24,150.00 RM0.00 0% 20 days Sat 30/12/23 Tue 23/1/24
reinforcement, vibrate concrete to
ground beam
22 Sawn formwork, steel RM15,750.00 RM0.00 0% 20 days Thu 18/1/24 Fri 9/2/24
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM0.00 0% 20 days Tue 13/2/24 Wed 6/3/24
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM0.00 0% 20 days Thu 7/3/24 Sat 30/3/24
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM0.00 0% 30 days Mon 1/4/24 Wed 8/5/24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM0.00 0% 25 days Thu 9/5/24 Tue 11/6/24
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24
32 Structural Work on Staircase RM8,400.00 RM0.00 0% 25 days Wed 12/6/24 Fri 12/7/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost November Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
49 Floor tiles including toilet RM42,000.00 RM0.00 0% 20 days Wed 12/6/24 Fri 5/7/24
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
61 Electrical Works RM30,875.00 RM0.00 0% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM0.00 0% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM0.00 0% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
67 Internal Cold-water system RM7,500.00 RM0.00 0% 45 days Wed 12/6/24 Tue 6/8/24
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost December Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM113,857.50 11% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM26,392.50 11% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM4,680.00 8% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM2,000.00 8% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM1,600.00 8% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM7,875.00 30% 60 days Fri 1/12/23 Tue 13/2/24
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM10,237.50 65% 40 days Fri 1/12/23 Thu 18/1/24
piling rig
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM3,300.00 40% 20 days Sat 23/12/23 Wed
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM2,415.00 10% 20 days Sat 30/12/23 Tue 23/1/24
reinforcement, vibrate concrete
to ground beam
22 Sawn formwork, steel RM15,750.00 RM0.00 0% 20 days Thu 18/1/24 Fri 9/2/24
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM0.00 0% 20 days Tue 13/2/24 Wed 6/3/24
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM0.00 0% 20 days Thu 7/3/24 Sat 30/3/24
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM0.00 0% 30 days Mon 1/4/24 Wed 8/5/24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM0.00 0% 25 days Thu 9/5/24 Tue 11/6/24
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24
32 Structural Work on Staircase RM8,400.00 RM0.00 0% 25 days Wed 12/6/24 Fri 12/7/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost December Duration Start Finish Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2023 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24
35 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24
thick external brick wall
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
49 Floor tiles including toilet RM42,000.00 RM0.00 0% 20 days Wed 12/6/24 Fri 5/7/24
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24
61 Electrical Works RM30,875.00 RM0.00 0% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM0.00 0% 200 days Thu 18/1/24 Wed
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM0.00 0% 20 days Thu 18/1/24 Fri 9/2/24
65 Supply and install the electrical fittings RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon
and switch board 12/8/24
67 Internal Cold-water system RM7,500.00 RM0.00 0% 45 days Wed 12/6/24 Tue 6/8/24
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost January Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM219,808.00 19% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM48,615.00 20% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM8,190.00 14% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM3,500.00 14% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM2,800.00 14% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM18,375.00 70% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM0.00 0% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM11,025.00 12% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM11,025.00 70% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM0.00 0% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM0.00 0% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM0.00 0% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM0.00 0% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM0.00 0% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost January Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM0.00 0% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
49 Floor tiles including toilet RM42,000.00 RM0.00 0% 20 days Wed 12/6/24 Fri 5/7/24 26
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM0.00 0% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM0.00 0% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM0.00 0% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 28
61 Electrical Works RM30,875.00 RM4,018.00 12% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM378.00 12% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM3,640.00 70% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
67 Internal Cold-water system RM7,500.00 RM0.00 0% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost February Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM270,931.00 26% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM67,875.00 31% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM14,625.00 25% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM6,250.00 25% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM5,000.00 25% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM0.00 0% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM40,950.00 31% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM25,200.00 80% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM0.00 0% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM0.00 0% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM0.00 0% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM0.00 0% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost February Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM0.00 0% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
49 Floor tiles including toilet RM42,000.00 RM0.00 0% 20 days Wed 12/6/24 Fri 5/7/24 26
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM0.00 0% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM0.00 0% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM0.00 0% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 28
61 Electrical Works RM30,875.00 RM5,956.00 21% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM756.00 24% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
67 Internal Cold-water system RM7,500.00 RM0.00 0% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost March 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM304,684.00 34% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM83,400.00 44% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM23,400.00 40% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM10,000.00 40% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM8,000.00 40% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM0.00 0% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
9 Substructure RM748,525.00 RM221,284.00 26% 290 days Wed 1/11/23 Fri 25/10/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM58,800.00 52% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete
to ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete
to first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete
to first floor column
25 Sawn formwork, steel RM39,500.00 RM0.00 0% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete
to first floor slab
26 Sawn formwork, steel RM15,750.00 RM0.00 0% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete
to roof beam
28 Timber Roof Truss RM88,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM0.00 0% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost March 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM0.00 0% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
49 Floor tiles including toilet RM42,000.00 RM0.00 0% 20 days Wed 12/6/24 Fri 5/7/24 26
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM0.00 0% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM0.00 0% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM0.00 0% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 28
61 Electrical Works RM30,875.00 RM6,334.00 29% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground RM3,150.00 RM1,134.00 36% 200 days Thu 18/1/24 Wed 19
electrical pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
wiring
65 Supply and install the electrical RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon 36
fittings and switch board 12/8/24
67 Internal Cold-water system RM7,500.00 RM0.00 0% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost April 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM356,937.00 43% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM98,925.00 56% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM32,175.00 55% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM13,750.00 55% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM11,000.00 55% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM0.00 0% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
20 Superstructure RM592,375.00 RM101,862.00 20% 225 days Thu 18/1/24 Fri 25/10/24
21 Frame RM114,050.00 RM94,350.00 76% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM35,550.00 90% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM0.00 0% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM0.00 0% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost April 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM800.00 40% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
49 Floor tiles including toilet RM42,000.00 RM0.00 0% 20 days Wed 12/6/24 Fri 5/7/24 26
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM0.00 0% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM0.00 0% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM0.00 0% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 28
61 Electrical Works RM30,875.00 RM6,712.00 36% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground RM3,150.00 RM1,512.00 48% 200 days Thu 18/1/24 Wed 19
electrical pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
wiring
65 Supply and install the electrical RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon 36
fittings and switch board 12/8/24
67 Internal Cold-water system RM7,500.00 RM0.00 0% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost May 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM390,677.50 51% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM114,450.00 69% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM40,950.00 70% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM17,500.00 70% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM14,000.00 70% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM0.00 0% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM111,687.50 97% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM39,500.00 100% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM13,387.50 85% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM0.00 0% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost May 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM0.00 0% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM1,300.00 65% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
49 Floor tiles including toilet RM42,000.00 RM0.00 0% 20 days Wed 12/6/24 Fri 5/7/24 26
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM0.00 0% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM0.00 0% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM0.00 0% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 28
61 Electrical Works RM30,875.00 RM7,090.00 44% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM1,890.00 60% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
67 Internal Cold-water system RM7,500.00 RM0.00 0% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost June 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM533,962.00 61% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM119,875.00 72% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM41,535.00 71% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM17,750.00 71% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM14,200.00 71% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM4,390.00 40% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM114,050.00 100% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM39,500.00 100% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM62,125.00 70% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM5,880.00 70% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost June 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM0.00 0% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM10,237.50 65% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM10,237.50 65% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM2,000.00 100% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 36
49 Floor tiles including toilet RM42,000.00 RM37,800.00 90% 20 days Wed 12/6/24 Fri 5/7/24 26
52 Internal Wall Plastering RM13,650.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM0.00 0% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM0.00 0% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM0.00 0% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM0.00 0% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
59 Ceiling frame and finishing RM38,850.00 RM0.00 0% 15 days Fri 19/7/24 Tue 6/8/24 28
61 Electrical Works RM30,875.00 RM7,657.00 55% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM2,457.00 78% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM0.00 0% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM0.00 0% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
66 Sanitary Works RM14,375.00 RM6,375.00 43% 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system RM7,500.00 RM6,375.00 85% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM0.00 0% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost July 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM735,403.75 73% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM122,007.50 74% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM42,120.00 72% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM18,000.00 72% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM14,400.00 72% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM5,487.50 50% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM114,050.00 100% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM39,500.00 100% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM88,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM0.00 0% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM8,400.00 100% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost July 2024 Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM23,625.00 90% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM2,000.00 100% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM2,317.50 90% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM35,910.00 90% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM2,205.00 70% 15 days Fri 19/7/24 Tue 6/8/24 36
43 Door frame RM3,150.00 RM2,205.00 70% 15 days Fri 19/7/24 Tue 6/8/24 36
49 Floor tiles including toilet RM42,000.00 RM42,000.00 100% 20 days Wed 12/6/24 Fri 5/7/24 26
51 Wall Finishes RM59,850.00 RM17,587.50 25% 40 days Fri 19/7/24 Thu 5/9/24
52 Internal Wall Plastering RM13,650.00 RM4,095.00 30% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM2,362.50 30% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM4,410.00 40% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM3,150.00 20% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM3,570.00 40% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM0.00 0% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
58 Ceiling Finishes RM49,350.00 RM31,080.00 34% 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing RM38,850.00 RM31,080.00 80% 15 days Fri 19/7/24 Tue 6/8/24 28
61 Electrical Works RM30,875.00 RM19,966.25 66% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM2,520.00 80% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM906.25 25% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM11,340.00 60% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
66 Sanitary Works RM14,375.00 RM8,875.00 60% 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system RM7,500.00 RM7,500.00 100% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM1,375.00 20% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost August Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM863,989.00 84% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM128,530.00 77% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM42,705.00 73% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM18,250.00 73% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM14,600.00 73% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM10,975.00 100% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM114,050.00 100% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM39,500.00 100% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM88,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM6,300.00 100% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM8,400.00 100% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost August Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM26,250.00 100% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM2,000.00 100% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM2,575.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM39,900.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM3,150.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
43 Door frame RM3,150.00 RM3,150.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
44 Door leaf RM18,750.00 RM18,750.00 100% 15 days Wed 7/8/24 Fri 23/8/24 43
49 Floor tiles including toilet RM42,000.00 RM42,000.00 100% 20 days Wed 12/6/24 Fri 5/7/24 26
51 Wall Finishes RM59,850.00 RM59,062.50 94% 40 days Fri 19/7/24 Thu 5/9/24
52 Internal Wall Plastering RM13,650.00 RM13,650.00 100% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM7,875.00 100% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM11,025.00 100% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM15,750.00 100% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM8,925.00 100% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM1,837.50 70% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
58 Ceiling Finishes RM49,350.00 RM49,350.00 100% 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing RM38,850.00 RM38,850.00 100% 15 days Fri 19/7/24 Tue 6/8/24 28
60 Ceiling Painting RM10,500.00 RM10,500.00 100% 20 days Wed 7/8/24 Thu 29/8/24 59
61 Electrical Works RM30,875.00 RM27,739.00 71% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM2,551.50 81% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM1,087.50 30% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM18,900.00 100% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
66 Sanitary Works RM14,375.00 RM14,375.00 100% 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system RM7,500.00 RM7,500.00 100% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM6,875.00 100% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost September Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM888,568.75 93% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM140,950.00 87% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM49,725.00 85% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM21,250.00 85% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM17,000.00 85% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM10,975.00 100% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM114,050.00 100% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM39,500.00 100% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM88,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM6,300.00 100% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM8,400.00 100% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost September Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM26,250.00 100% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM2,000.00 100% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM2,575.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM39,900.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM3,150.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
43 Door frame RM3,150.00 RM3,150.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
44 Door leaf RM18,750.00 RM18,750.00 100% 15 days Wed 7/8/24 Fri 23/8/24 43
49 Floor tiles including toilet RM42,000.00 RM42,000.00 100% 20 days Wed 12/6/24 Fri 5/7/24 26
51 Wall Finishes RM59,850.00 RM59,850.00 100% 40 days Fri 19/7/24 Thu 5/9/24
52 Internal Wall Plastering RM13,650.00 RM13,650.00 100% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM7,875.00 100% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM11,025.00 100% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM15,750.00 100% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM8,925.00 100% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM2,625.00 100% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
58 Ceiling Finishes RM49,350.00 RM49,350.00 100% 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing RM38,850.00 RM38,850.00 100% 15 days Fri 19/7/24 Tue 6/8/24 28
60 Ceiling Painting RM10,500.00 RM10,500.00 100% 20 days Wed 7/8/24 Thu 29/8/24 59
61 Electrical Works RM30,875.00 RM29,968.75 94% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM3,150.00 100% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM2,718.75 75% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM18,900.00 100% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
66 Sanitary Works RM14,375.00 RM14,375.00 100% 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system RM7,500.00 RM7,500.00 100% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM6,875.00 100% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
ID Task Task Name Cost Actual Cost October Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PROPOSED THREE UNITS OF DOUBLE RM905,000.00 RM905,000.00 100% 290 days Wed 1/11/23 Fri 25/10/24
STOREY DETACHED HOUSE
2 Preliminary and General Works RM156,475.00 RM156,475.00 100% 290 days Wed 1/11/23 Fri 25/10/24
3 Contractor's Site Management RM58,500.00 RM58,500.00 100% 290 days Wed 1/11/23 Fri 25/10/24
4 Contractor's Site Office RM25,000.00 RM25,000.00 100% 290 days Wed 1/11/23 Fri 25/10/24
5 Worker's Quarters and Servies RM20,000.00 RM20,000.00 100% 290 days Wed 1/11/23 Fri 25/10/24
6 Mobilization and demobilization of RM26,250.00 RM26,250.00 100% 60 days Fri 1/12/23 Tue 13/2/24 12SF
excavator and lorry for excavation
works
7 Mobilization and demobilization of RM15,750.00 RM15,750.00 100% 40 days Fri 1/12/23 Thu 18/1/24 13SF
piling rig
8 Mobilization and demobilization of RM10,975.00 RM10,975.00 100% 55 days Sat 15/6/24 Wed 26SF
mobila crane for roof works 21/8/24
11 Supply and transport R.C square pile RM30,000.00 RM30,000.00 100% 20 days Wed 1/11/23 Thu 100%
23/11/23
12 Excavation from existing ground RM10,925.00 RM10,925.00 100% 30 days Fri 24/11/23 Fri 29/12/23 11
level, partly backfill and remainder
cart away for pile cap, ground beam
and slab
13 Handle, pitch and drive R.C square RM25,850.00 RM25,850.00 100% 25 days Fri 24/11/23 Fri 22/12/23 12SS
pile
14 Jointing pile by butt welding RM8,250.00 RM8,250.00 100% 25 days Fri 24/11/23 Fri 22/12/23 13SS
15 Hack-off/cut-off pile heads and RM6,725.00 RM6,725.00 100% 25 days Fri 24/11/23 Fri 22/12/23 14SS
connect to pile cap
17 Sawn formwork, steel RM8,250.00 RM8,250.00 100% 20 days Sat 23/12/23 Wed 15
reinforcement, vibrated concrete 17/1/24
to pile cap and stump
18 Sawn formwork, steel RM24,150.00 RM24,150.00 100% 20 days Sat 30/12/23 Tue 23/1/24 17SS+5 days
reinforcement, vibrate concrete
to ground beam
19 Sawn formwork, steel RM42,000.00 RM42,000.00 100% 10 days Sat 6/1/24 Wed 18SS+5 days
reinforcement, vibrated concrete 17/1/24
to ground slab
21 Frame RM114,050.00 RM114,050.00 100% 115 days Thu 18/1/24 Tue 11/6/24
22 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 20 days Thu 18/1/24 Fri 9/2/24 19
reinforcement, vibrated concrete to
ground column
23 Sawn formwork, steel RM31,500.00 RM31,500.00 100% 20 days Tue 13/2/24 Wed 6/3/24 22
reinforcement, vibrated concrete to
first floor beam
24 Sawn formwork, steel RM11,550.00 RM11,550.00 100% 20 days Thu 7/3/24 Sat 30/3/24 23
reinforcement, vibrated concrete to
first floor column
25 Sawn formwork, steel RM39,500.00 RM39,500.00 100% 30 days Mon 1/4/24 Wed 8/5/24 24
reinforcement, vibrated concrete to
first floor slab
26 Sawn formwork, steel RM15,750.00 RM15,750.00 100% 25 days Thu 9/5/24 Tue 11/6/24 25
reinforcement, vibrated concrete to
roof beam
28 Timber Roof Truss RM88,750.00 RM88,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
30 Gutter and rainwater goods RM6,300.00 RM6,300.00 100% 10 days Tue 13/8/24 Fri 23/8/24 29
32 Structural Work on Staircase RM8,400.00 RM8,400.00 100% 25 days Wed 12/6/24 Fri 12/7/24 28SS
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
ID Task Task Name Cost Actual Cost October Duration Start Finish Predecessors Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode 2024 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
33 Finishes Works on Staircase RM26,250.00 RM26,250.00 100% 20 days Sat 13/7/24 Tue 6/8/24 32
35 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick internal brick wall
36 Well burnt clay brick on 115mm RM15,750.00 RM15,750.00 100% 30 days Wed 12/6/24 Thu 18/7/24 26
thick external brick wall
37 Bonding Tie RM2,000.00 RM2,000.00 100% 50 days Sat 6/4/24 Tue 11/6/24 26FS-50 days
39 Window concrete lintel RM2,575.00 RM2,575.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
40 Window frame and finishing RM39,900.00 RM39,900.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
42 Door concrete lintel RM3,150.00 RM3,150.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
43 Door frame RM3,150.00 RM3,150.00 100% 15 days Fri 19/7/24 Tue 6/8/24 36
44 Door leaf RM18,750.00 RM18,750.00 100% 15 days Wed 7/8/24 Fri 23/8/24 43
49 Floor tiles including toilet RM42,000.00 RM42,000.00 100% 20 days Wed 12/6/24 Fri 5/7/24 26
51 Wall Finishes RM59,850.00 RM59,850.00 100% 40 days Fri 19/7/24 Thu 5/9/24
52 Internal Wall Plastering RM13,650.00 RM13,650.00 100% 30 days Fri 19/7/24 Fri 23/8/24 35
53 External Wall Plastering RM7,875.00 RM7,875.00 100% 30 days Fri 19/7/24 Fri 23/8/24 36
54 Wall tiles RM11,025.00 RM11,025.00 100% 20 days Tue 23/7/24 Wed 52SS+2 days
14/8/24
55 Wall Painting RM15,750.00 RM15,750.00 100% 30 days Thu 25/7/24 Wed 52SS+4 days
28/8/24
56 Wall flashing RM8,925.00 RM8,925.00 100% 20 days Fri 26/7/24 Sat 17/8/24 52SS+5 days
57 Chamfered and rebated timber RM2,625.00 RM2,625.00 100% 30 days Thu 1/8/24 Thu 5/9/24 56SS+5 days
skirting
58 Ceiling Finishes RM49,350.00 RM49,350.00 100% 35 days Fri 19/7/24 Thu 29/8/24
59 Ceiling frame and finishing RM38,850.00 RM38,850.00 100% 15 days Fri 19/7/24 Tue 6/8/24 28
60 Ceiling Painting RM10,500.00 RM10,500.00 100% 20 days Wed 7/8/24 Thu 29/8/24 59
61 Electrical Works RM30,875.00 RM30,875.00 100% 225 days Thu 18/1/24 Fri 25/10/24
62 The provision of underground electrical RM3,150.00 RM3,150.00 100% 200 days Thu 18/1/24 Wed 19
pipe sleeve 25/9/24
63 Supply and install UPVC pipes on RM3,625.00 RM3,625.00 100% 80 days Fri 19/7/24 Fri 25/10/24 36
concrete slab and brick wall
64 Supply and install the electrical wiring RM5,200.00 RM5,200.00 100% 20 days Thu 18/1/24 Fri 9/2/24 62SS
65 Supply and install the electrical fittings RM18,900.00 RM18,900.00 100% 20 days Fri 19/7/24 Mon 36
and switch board 12/8/24
66 Sanitary Works RM14,375.00 RM14,375.00 100% 65 days Wed 12/6/24 Thu 29/8/24
67 Internal Cold-water system RM7,500.00 RM7,500.00 100% 45 days Wed 12/6/24 Tue 6/8/24 26
68 Internal Sanitary System RM6,875.00 RM6,875.00 100% 45 days Sat 6/7/24 Thu 29/8/24 49
Project: Master Workprogramm Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 19/12/23 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24
1/11/2023 30/11/2023 31/12/2023 31/1/2023 28/2/2023 31/3/2023 30/4/2023 31/5/2023 30/6/2023 31/7/2023 31/8/2023 30/9/2023 31/10/2023
ITEM DESCRIPTION
2 Preliminary and General Works - 4% 11% 19% 26% 34% 43% 51% 61% 73% 84% 93% 100%
9 Substructure - 25% 77% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
20 Superstructure - - - 5% 9% 14% 20% 26% 44% 67% 89% 98% 100%
47 Finishes - - - - - - - - 10% 44% 96% 100% 100%
61 Electrical Works - - - 12% 21% 29% 36% 44% 55% 66% 71% 94% 100%
66 Sanitary Works - - - - - - - - 43% 60% 100% 100% 100%
Duration(Months) 1/11/2023 30/11/2023 31/12/2023 31/1/2023 28/2/2023 31/3/2023 30/4/2023 31/5/2023 30/6/2023 31/7/2023 31/8/2023 30/9/2023 31/10/2023
Planned Work(%) - 4% 11% 19% 27% 35% 43% 51% 61% 73% 84% 93% 100%
120%
100%
Planned Work(%)
80%
60%
40%
20%
0%
1/11/2023 1/12/2023 1/1/2024 1/2/2024 1/3/2024 1/4/2024 1/5/2024 1/6/2024 1/7/2024 1/8/2024 1/9/2024 1/10/2024
Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24
30/11/2023 31/12/2023 31/1/2023 28/2/2023 31/3/2023 30/4/2023 31/5/2023 30/6/2023 31/7/2023 31/8/2023 30/9/2023 31/10/2023
CONTRACT SUM
ITEM DESCRIPTION (RM) WEIGHTAGE
2 Preliminary and General Works 156,475.00 17.29% 5,175.00 26,293.50 48,615.00 68,875.00 83,400.00 98,925.00 114,450.00 119,875.00 122,007.50 128,530.00 140,950.00 156,475.00
9 Substructure 156,150.00 17.25% 41,983.00 87,465.00 156,150.00 156,150.00 156,150.00 156,150.00 156,150.00 156,150.00 156,150.00 156,150.00 156,150.00 156,150.00
20 Superstructure 388,050.00 42.88% - - 11,025.00 40,950.00 58,800.00 101,862.00 112,987.50 204,530.00 329,862.50 378,907.50 388,050.00 388,050.00
47 Finishes 159,075.00 17.58% - - - - - - - 39,375.00 98,542.50 158,287.50 159,075.00 159,075.00
61 Electrical Works 30,875.00 3.41% - - 4,018.00 5,956.00 6,334.00 6,712.00 7,090.00 7,657.00 19,966.25 27,739.00 29,968.75 30,875.00
66 Sanitary Works 14,375.00 1.59% - - - - - - - 6,375.00 8,875.00 14,375.00 14,375.00 14,375.00
Cumulative cost (RM) 905,000.00 100% 47,158.00 113,758.50 219,808.00 271,931.00 304,684.00 363,649.00 390,677.50 533,962.00 735,403.75 863,989.00 888,568.75 905,000.00
Cumulative (%) 5% 13% 24% 30% 34% 40% 43% 59% 81% 95% 98% 100%
Duration(Months) 1/11/2023 30/11/2023 31/12/2023 31/1/2023 28/2/2023 31/3/2023 30/4/2023 31/5/2023 30/6/2023 31/7/2023 31/8/2023 30/9/2023 31/10/2023
Planned Work(%) - 5% 13% 24% 30% 34% 40% 43% 59% 81% 95% 98% 100%
120%
100%
80%
Planned Cost(%)
60%
40%
20%
0%
1/11/2023 1/12/2023 1/1/2024 1/2/2024 1/3/2024 1/4/2024 1/5/2024 1/6/2024 1/7/2024 1/8/2024 1/9/2024 1/10/2024
Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24
ITEM DESCRIPTION 1/11/2023 30/11/2023 31/12/2023 31/1/2023 28/2/2023 31/3/2023 30/4/2023 31/5/2023 30/6/2023 31/7/2023 31/8/2023 30/9/2023 31/10/2023
1 Planned Work (%) - 4% 11% 19% 27% 35% 43% 51% 61% 73% 84% 93% 100%
2 Actual Work (%) - 3% 9% 16% 25% 35% 45% 51% 56% 71% 86% 95% 100%
3 Differences (%) - -1% -2% -3% -2% 0% 2% 0% -5% -2% 2% 2% 0%
Physical Status (Monthly) - Delay Delay Delay Delay On Path Ahead On Path Delay Delay Ahead Ahead On Path
120%
100%
Planned Work(%) & Actual Work (%)
80%
60%
40%
20%
0%
1/10/2023 1/11/2023 1/12/2023 1/1/2024 1/2/2024 1/3/2024 1/4/2024 1/5/2024 1/6/2024 1/7/2024 1/8/2024 1/9/2024 1/10/2024