You are on page 1of 29

SEISMIC RETROFITTING OF

MANI MANDIR COMPLEX


AT MORBI,
GUJARAT, INDIA
Presented by
Ashlin T V

1
INTRODUCTION
 100m×100m in plan

 Historic monument
 125 km from the epicenter of the 2001
Bhuj earthquake
 Morbi in the western state of Gujarat

 Western banks of the Macchu River

 Built in the 1930s by the ruler of Morbi

 Very ornate masonry building

2
Contd.
 Built in yellow sandstone in the tradition of the Indo-Saracenic style of architecture.

 The Secretariat building has a large central courtyard housing the Mani Mandir
temple

 Total area of the Willingdon Secretariat is;

- 4900m2 on ground floor

- 4150m2 on first floor

- 255m2 a part of second floor

Fig. 1: Mani Mandir Complex

3
Principles that Governed The Seismic Retrofit Program

 Avoid intervention to maximum extent possible

 Introduce retrofitting measures in consonance with the heritage character and


principles of conservation

 New elements must be non-intrusive and compatible with existing materials

 New elements must not be a cause of further damage (such as corrosion).

 Retrofit measures must be easy to implement

4
DAMAGE DOCUMENTATION
Micro-Detailed Structural
Macro Survey Detailed Survey
Survey

Identifying the areas of Floor-wise and Wing- Room-wise


severe, moderate and wise Documenting all
minor damage To identify the types of damages including the
Areas that required damage extent of corrosion, the
emergency location of structural
interventions members and their
sizes, and the length
and width of cracks.

5
EXISTING STRUCTURE

 Two – storey complex

 Load bearing walls of soft,

- yellow sandstone above plinth

- black basalt stone below plinth

 Stone is dressed and exposed on external side

- coated with paint or lime wash internally

 Ashlar-type masonry
Fig. 2: Plan of Mani Mandir Complex
6
 No physical bonds between stone blocks

 Stay in place by bearing friction

 Some stones locked by wooden keys – Chhatris ( ornamental canopies)

- Shikhars ( decorative towers)

 The stone blocks of pillars are socketed into each other by a small tongue and groove
detail

 Floors are built of stone slabs

750mm width and 200mm thick.

 Slabs wedged between flanges of steel joist

Fig. 3: Stone Slab Wedged between Steel Joists

7
 Joist rest on stone cornice

 Floor finish – 150mm thick


 Arches along external façade walls
and internally across passages

Fig. 4: Separation of Joist Flanges and Failure of


Stone Slab

8
Damage Prior of 2001 Damage in 1956
Earthquake Earthquake
 Corrosion of steel joists  Displacement of keystones of

 Damage to cornice pieces at the portals, arches

steel joist locations  Movement of stones of walls

 Weathering and flaking of


sandstone

 Roof leakage

 Peeling of internal paint

9
Damage in 2001 Earthquake

 Severe damage and collapse of a large number of elements

 Extensive damage at the roof level

 Moderate damage at the first storey

 Little damage on the ground storey

 Staircase cap slabs, parapets, shikhars, arches, portals and chhatris above the roof
were very badly damaged

 Bastions at the extreme corners of the structure sustained severe damage

10
Fig. 5: Damage above Roof Level: (a) Destruction of Arches in Elevational Elements,
(b) Partial Collapse of Bastions

11
Fig. 7: Damage to Vertical Elements: (a) Openings of Joints in Arch;
(b) Diagonal Cracks in Walls

Fig. 6: Floor Level Damage:

12
Previous Attempts of Retrofit

 Keystones of some arches and stone blocks of a few walls and portals were stapled
to adjacent stones

 Plastering the surface with cement mortar

 Arch pillars had been fully jacketed in concrete

13
Fig. 8: Earlier Interventions towards Restoration: (a) Fastening of Stones Using Mild Steel Staples;
(b) Repairing of Weathered Stone.

14
BEHAVIOUR ANALYSIS

 Poor Bonding Between Stones

 Lack of Rigid Diaphragm Action of Slab

 Lack of Rigid Diaphragm Action of Slab

 Reentrant Corners

 Arches

15
STRUCTURAL ANALYSIS

 Material Tests

 Modeling and Analysis of the Existing Structure

- Design Force Level for the Buildings

- Modeling

 Verification of the Analysis and Structural Adequacy

16
METHODOLOGIES FOR REPAIR,
RESTORATION AND RETROFITTING
 Elements to be Added/Enhanced for Improved Seismic Behaviour of Structure

- Introducing rigid diaphragm action of slab

- Enhancing Strength of the Structure

- End-pinning of Wall Corners

- Introducing Horizontal Reinforced Bands To Existing Masonry Walls

- Strengthening of Arches

- Cross-Pinning of Corridor Columns

- Stitching and Grouting of Cracks in Walls


17
Fig. 7: Location of Proposed Bracings and R.C. Skin Walls at First
Floor Level

18
Fig. 8: Sectional Details of Anchoring of Diagonal Floor Bracing in Walls

19
(a) (b)
FIG. 9: Details of New R.C. Skin Wall (a) R.C. Skin Wall Nogged in to Masonry Wall;
(b) New R.C. Skin Wall Foundation
20
(a) (b)
Fig. 10: Intervention in Walls: (a) End Pining at Wall Corners;
(b) Seismic Reinforcement Bands
21
Fig. 11: Detail of Interventions in Arches: (a) Strengthening of Arches Using Ties;
(b) Strengthening Of Arches by Pining And Reinforcement Band.

22
Fig. 12: Interventions in Vertical Elements: (a) Cross Pining of Corridor Columns
(b) Detail of Stitching Cracks in Walls

23
 Areas Requiring Demolition and Rebuild

- Roof Slab

- Bastions

- Elevation Features above Roof (Chhatris and Shikhars) and Decorative Balconies

- Roof Parapets

- Weather Sheds

24
Fig. 13: Plan of Bastion with New R.C. Skin Wall

25
Fig. 14 Pinning Details For Weather Shed

26
Conclusions
 The total area of new reinforced concrete skin walls introduced is less than 10% of
the area of the existing masonry walls

 The estimated cost of the proposed retrofit worked out to less than Rs. 4300/m2

 Reinforced concrete skin walls, diagonal bracing on the underside of the floor slabs
for diaphragm action, horizontal stainless steel reinforcement bands in existing
masonry walls have been proposed to improve lateral strength and behaviour

 Cross-pinning and end pinning have been recommended to improve the seismic
behaviour of walls, weather sheds and stone pillars

27
REFERENCES

 Alpa Sheth et. al., (2004), “Seismic Retrofitting of Mani Mandir Complex at
Morbi, Gujarat, India”, World Conference on Earthquake Engineering, 2430;1-6

28
Thank you

29

You might also like