You are on page 1of 11

STATUS CIVIL MECHANICAL ELECTRICAL TOTAL

MARGALLA BUILDING SUBMITTED 160 152 95 407

SHOP DRAWING STATUS FOR CIVIL & MEP APPROVED 110 31 15 156
APPROVED WITH COMMENTS 17 35 47 99
APPROVAL TIME 15 DAYS PENDING 6 30 41 77
UPDATED September 29, 2015 REJECTED 13 59 4 76
Submitted For Information
14 14
Only

CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
Approved by Engineer
1 Civil PCL/MBI/14-001a Parking Proposed Excavation Layout Plan 1st 10-Jun-14 25-Jun-14 13-Jun-14 12 On-Time Approved
on Site
Approved by Engineer
2 Civil PCL/MBI/14-001b Parking Proposed Excavation Layout Plan(Sections) 1st 10-Jun-14 25-Jun-14 13-Jun-14 12 On-Time Approved
on Site
Approved by Engineer
3 Civil PCL/MBI/14-001c Parking Proposed Excavation Layout Plan(Sections) 1st 10-Jun-14 25-Jun-14 13-Jun-14 12 On-Time Approved
on Site
Approved by Engineer
4 Civil PCL/MBI/14-002 Misc. Foundation Sections & Details 1st 9-Jun-14 24-Jun-14 9-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
5 Civil PCL/MBI/14-003 Foundation Layout Plan Proposed Expansion Joint 1st 9-Jun-14 24-Jun-14 9-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
6 Civil PCL/MBI/14-004a Grid Reference W.R.T Plot Boundary (As Per Drawing) 1st 13-Jun-14 28-Jun-14 13-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
7 Civil PCL/MBI/14-004b Grid Reference W.R.T Plot Boundary (As Per Site/Deep Well Working) 1st 13-Jun-14 28-Jun-14 13-Jun-14 15 On-Time Approved
on Site
Approved by Engineer
8 Civil PCL/MBI/14-005 Parking Excavation Level Plan 1st 13-Jun-14 28-Jun-14 25-Jun-14 3 On-Time Approved
on Site
9 Civil PCL/MBI/14-007 Block C Excavation Layout Plan 1st 7-Jul-14 22-Jul-14 27-Aug-14 (36) Delayed Approved -
10 Civil PCL/MBI/14-008a Parking Footing Section (Bottom Lvl. 206175) Revised Dwg Level 206500 1st 3-Jul-14 18-Jul-14 5-Aug-14 (18) Delayed Approved -
11 Civil PCL/MBI/14-008b Parking Footing Section (Bottom Lvl. 204950) Revised Dwg Level 205275 1st 3-Jul-14 18-Jul-14 5-Aug-14 (18) Delayed Approved -
12 Civil PCL/MBI/14-008c Parking Footing Section (Bottom Lvl. 205775) Revised Dwg Level 206100 1st 3-Jul-14 18-Jul-14 5-Aug-14 (18) Delayed Approved -
13 Civil PCL/MBI/14-009 Main Building Lower Ground Floor Excavation Level Plan & Section 1st 17-Jul-14 1-Aug-14 7-Aug-14 (6) Delayed Approved -
14 Civil PCL/MBI/14-010 Parking Retaining Wall Proposed Vertical Steel Bars 1st 22-Jul-14 6-Aug-14 25-Aug-14 (19) Delayed Approved -
15 Civil PCL/MBI/14-011 Parking Footing Plan & Details 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
16 Civil PCL/MBI/14-011A Parking Footing Plan & Details A 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
17 Civil PCL/MBI/14-012 Parking Footing Section Footing F-5 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
18 Civil PCL/MBI/14-013 Parking Footing Section (Bottom Lvl. 206175) 1st 13-Aug-14 28-Aug-14 25-Aug-14 3 On-Time Approved -
SUBMITTED FOR
19 Civil PCL/MBI/14-014 Parking Columns Layout Plan 1st 21-Aug-14 - - - -
INFORMATION ONLY
20 Civil PCL/MBI/14-014A Typical Columns Detail 1st 21-Aug-14 5-Sep-14 7-Nov-14 (63) Delayed Approved

SUBMITTED FOR
21 Civil PCL/MBI/14-014B Typical Columns Section 1st 21-Aug-14 - - - -
INFORMATION ONLY
22 Civil PCL/MBI/14-015 U.G Storm Water sedimentation Tank Proposed Size & Location Coordinate 1st 28-Aug-14 12-Sep-14 9-Oct-14 (27) Delayed Approved

SUBMITTED FOR
23 Civil PCL/MBI/14-016 Pile as Built Location and Detail 1st 4-Sep-14 - - - -
INFORMATION ONLY
Proposal Rejected(
24 Civil PCL/MBI/14-017 Parking Basement wall Section & Detail 150mm Thick Gravel With Water Drain Out Arrangement 1st 6-Sep-14 - - - - Work on the basis of
original Drawings)
SUBMITTED FOR
25 Civil PCL/MBI/14-018 NGL Plan Margalla Building Lower Ground Floor Block C & Part Block D (Joint Survey) 1st 11-Sep-14 - - - -
INFORMATION ONLY
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE

SUBMITTED FOR
26 Civil PCL/MBI/14-019 NGL Plan Margalla Building Ground Floor Block D ( Joint Survey) 1st 11-Sep-14 - - - -
INFORMATION ONLY

SUBMITTED FOR
27 Civil PCL/MBI/14-020 NGL Plan Margalla Building Ground Floor Block A ( Joint Survey) 2nd 12-Sep-14 - - - -
INFORMATION ONLY
28 Civil PCL/MBI/14-021 Propsed Pile Cap Reinforcement 1st 13-Sep-14 28-Sep-14 22-Sep-14 6 On-Time Approved -
Welding will be done
29 Civil PCL/MBI/14-022 Propsed Steel Anchoring in Pile 1st 15-Sep-14 30-Sep-14 25-Sep-14 5 On-Time Approved
instead of anchoring
Sent To Client Office on
30 Civil PCL/MBI/14-023 Propsed SOG Dowels in Columns Plan 1st 20-Sep-14 5-Oct-14 22-Sep-14 13 On-Time Approved
Site
Sent To Client Office on
31 Civil PCL/MBI/14-023A Propsed SOG Dowels in Columns Sections 1st 20-Sep-14 5-Oct-14 22-Sep-14 13 On-Time Approved
Site
Sent To Client Office on
32 Civil PCL/MBI/14-024 Detail of Air Proofing 1st 23-Sep-14 8-Oct-14 To be re-submitted
Site
SUBMITTED FOR
33 Civil PCL/MBI/14-025 Pile as Built Location and Detail (upto Date) 1st 27-Sep-14 - - -
INFORMATION ONLY

SUBMITTED FOR
34 Civil PCL/MBI/14-026 NGL Plan Margalla Building Ground Floor Block B ( Joint Survey) 1st 30-Sep-14 - - -
INFORMATION ONLY

SUBMITTED FOR
35 Civil PCL/MBI/14-027 NGL Plan Margalla Building Ground Floor Block E (Joint Survey) 1st 21-Oct-14 5-Nov-14 -
INFORMATION ONLY
Approved Re- Submission Re submitted on 8-11-
1st 8-Nov-14 23-Nov-14 7-Nov-14 16 On-Time
Required. 14
36 Civil PCL/MBI/14-028 LOWER GROUND FLOOR PILE CAP LAYOUT PLAN
SUBMITTED FOR
2nd 8-Nov-14 -
INFORMATION ONLY
37 Civil PCL/MBI/14-029 Block A PILE CAP LAYOUT PLAN 1st 30-Oct-14 14-Nov-14 7-Nov-14 7 On-Time Approved
Approved Re- Submission Re submitted on 11-11-
1st 30-Oct-14 14-Nov-14 7-Nov-14 7 On-Time
Required. 14
38 Civil PCL/MBI/14-030 Block E PILE CAP LAYOUT PLAN
SUBMITTED FOR
2nd 11-Nov-14 -
INFORMATION ONLY
39 Civil PCL/MBI/14-031 Block B PILE CAP LAYOUT PLAN 1st 31-Oct-14 15-Nov-14 7-Nov-14 8 On-Time Approved
40 Civil PCL/MBI/14-032 PILE CAP LAYOUT PLAN Water Body-3 1st 1-Nov-14 16-Nov-14 22-Nov-14 (6) Delayed Approved
41 Civil PCL/MBI/14-033 Block B Excavation Level Plan & Section 1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Approved
1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Rejected
42 Civil PCL/MBI/14-034 Lower Ground Floor SOG Beams 2nd 6-Dec-14 21-Dec-14 11-Dec-14 10 On-Time To be revised
3rd 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time Approved
1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Rejected
43 Civil PCL/MBI/14-035 Water Body Part-1 Beams
2nd 1-Jan-15 16-Jan-15 6-Jan-15 10 On-Time Approved
1st 6-Nov-14 21-Nov-14 7-Nov-14 14 On-Time Rejected
44 Civil PCL/MBI/14-036 Lower GF Column-Wall Plan and Detail
2nd 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved

SUBMITTED FOR
45 Civil PCL/MBI/14-037 Parking Building Proposed Stone Ballast Under SOG 1st 8-Nov-14 23-Nov-14 -
INFORMATION ONLY

SUBMITTED FOR
46 Civil PCL/MBI/14-038 Pile As Built LOCATION/COORDINATES (Up To Date) 1st 7-Nov-14 22-Nov-14 -
INFORMATION ONLY
SUBMITTED FOR
47 Civil 2nd 11-Nov-14 26-Nov-14 Approved
PCL/MBI/14-030 GROUND FLOOR BLOCK E PILE CAP LAYOUT- REV01 INFORMATION ONLY
SUBMITTED FOR
48 Civil 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY
PCL/MBI/14-039 PARKING RETAINING WALL POUR PLANS AND SECTIONS

SUBMITTED FOR
49 Civil 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY
PCL/MBI/14-040 GROUND FLOOR BLOCK A PILE CAP LAYOUT (REVISED)

SUBMITTED FOR
50 Civil GROUND FLOOR BLOCK B PILE CAP LAYOUT (REVISED) 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY
PCL/MBI/14-041
SUBMITTED FOR
51 Civil PCL/MBI/14-042 Block F PILE CAP LAYOUT PLAN 1st 11-Nov-14 26-Nov-14 Approved
INFORMATION ONLY

SUBMITTED FOR
52 Civil PCL/MBI/14-043 Pile As Built LOCATION/COORDINATES (Up To Date) 1st 11-Nov-14 26-Nov-14 -
INFORMATION ONLY
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
53 Civil PCL/MBI/14-044 Parking Ramp Level Plan & Sections 1st 12-Nov-14 27-Nov-14 26-Nov-14 1 On-Time Approved with Comments
54 Civil PCL/MBI/14-045 Block E Excavation Level Plan & Section 1st 17-Nov-14 2-Dec-14 17-Nov-14 15 On-Time Approved
55 Civil PCL/MBI/14-046 Block A Excavation Level Plan & Section 1st 17-Nov-14 2-Dec-14 17-Nov-14 15 On-Time Approved
56 Civil PCL/MBI/14-047 U.G. STORM WATER SEDIMENTATION TANK Raft & Framing Plan 1st 17-Nov-14 2-Dec-14 21-Nov-14 11 On-Time Approved
57 Civil PCL/MBI/14-048 Parking SOG Pour Plan and Sections 1st 17-Nov-14 2-Dec-14 19-Nov-14 13 On-Time Approved

SUBMITTED FOR
58 Civil PCL/MBI/14-049 Pile As Built LOCATION/COORDINATES (Up To Date) 1st 18-Nov-14 3-Dec-14 -
INFORMATION ONLY
59 Civil PCL/MBI/14-050 Block D Ground Floor PILE CAP LAYOUT PLAN 1st 19-Nov-14 4-Dec-14 21-Nov-14 13 On-Time Approved

SUBMITTED FOR
60 Civil PCL/MBI/14-051 WB-1 PILE CAP LAYOUT PLAN 1st 20-Nov-14 5-Dec-14 -
INFORMATION ONLY
61 Civil PCL/MBI/14-052 Water Body Part-1 Excavation Level Plan & Section 1st 20-Nov-14 5-Dec-14 4-Dec-14 1 On-Time Approved
62 Civil PCL/MBI/14-053 LOWER GROUND FLOOR RETAINING WALL FORMWORK & SOG DOWEL DETAIL 1st 22-Nov-14 7-Dec-14 22-Nov-14 15 On-Time Approved
63 Civil PCL/MBI/14-054 U.G Storm Water sedimentation Tank wall beam & Slab Reinforcement 1st 25-Nov-14 10-Dec-14 26-Nov-14 14 On-Time Approved
64 Civil PCL/MBI/14-055 Excavation Plan & Section Water Body-2 1st 28-Nov-14 13-Dec-14 4-Dec-14 9 On-Time Approved
65 Civil PCL/MBI/14-056 Excavation Plan & Section Water Body-3 1st 28-Nov-14 13-Dec-14 4-Dec-14 9 On-Time Approved
1st 28-Nov-14 13-Dec-14 4-Dec-14 9 On-Time Resubmit
66 Civil PCL/MBI/14-057 Excavation Plan & Section Block D Ground Floor
2nd 6-Dec-14 21-Dec-14 11-Dec-14 10 On-Time Approved

SUBMITTED FOR
67 Civil PCL/MBI/14-058 Pile As Built LOCATION/COORDINATES (Final) 1st 28-Nov-14 13-Dec-14 -
INFORMATION ONLY
68 Civil PCL/MBI/14-059 Block F PILE CAP LAYOUT PLAN (Revised) 1st 2-Dec-14 17-Dec-14 4-Dec-14 13 On-Time Approved
69 Civil PCL/MBI/14-060 Water Body Part-2 PILE CAP LAYOUT PLAN 1st 2-Dec-14 17-Dec-14 4-Dec-14 13 On-Time Approved
70 Civil PCL/MBI/14-061 MS Tower FRAMING PLAN & BASE PLATE DETAIL 1st 2-Dec-14 17-Dec-14 Delayed Design Revised
2nd 21-Apr-15 6-May-15 30-Apr-15 6 On-Time Approved
71 Civil PCL/MBI/14-061A MS Tower ELEVATION 1st 2-Dec-14 17-Dec-14 Delayed Design Revised
2nd 21-Apr-15 6-May-15 30-Apr-15 (6) On-Time Approved
72 Civil PCL/MBI/14-061B MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 Delayed Design Revised
2nd 21-Apr-15 6-May-15 30-Apr-15 6 On-Time Approved
73 Civil PCL/MBI/14-061C MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 Delayed Deleted
74 Civil PCL/MBI/14-061D MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 Delayed Deleted
75 Civil PCL/MBI/14-061E MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 Delayed Deleted
76 Civil PCL/MBI/14-061F MS Tower TYPICAL CONNECTION DETAILS 1st 2-Dec-14 17-Dec-14 Delayed Deleted
77 Civil PCL/MBI/14-062 Parking Slab & Column Pour Plan 1st 6-Dec-14 21-Dec-14 24-Dec-14 3 Delayed Approved
78 Civil PCL/MBI/14-063 Block F Excavation Level Plan & Section 1st 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved
79 Civil PCL/MBI/14-064 Collection & STP Water Tanks Size and Location Coordinates 1st 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved Architect to confirm
80 Civil PCL/MBI/14-065 Fuel Storage & Domestic Water Tanks Size and Location Coordinates 1st 9-Dec-14 24-Dec-14 11-Dec-14 13 On-Time Approved Architect to confirm
81 Civil PCL/MBI/14-066 Block F Ground Beams & SOG 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time To be revised
82 Civil PCL/MBI/14-067 Domestic Water Tank Wall & Slab (Top & Bottom) 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time Approved Follow Arch Levels
83 Civil PCL/MBI/14-068 STP Water Tank Wall & Slab (Top & Bottom) 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time Approved Follow Arch Levels
84 Civil PCL/MBI/14-069 Block F R.Wall Plan & Section 1st 11-Dec-14 26-Dec-14 15-Dec-14 11 On-Time To be revised
85 Civil PCL/MBI/14-070 Bloc E Ground Beam & SOG 1st 12-Dec-14 27-Dec-14 17-Dec-14 10 On-Time Approved
86 Civil PCL/MBI/14-071 Block A Column & Wall Setting out Plan 1st 12-Dec-14 27-Dec-14 17-Dec-14 10 On-Time Approved
87 Civil PCL/MBI/14-072 Block A SOG & Beams 1st 15-Dec-14 30-Dec-14 17-Dec-14 13 On-Time Approved
88 Civil PCL/MBI/14-073 Block B Ground Floor Column & Wall Setting out Plan 1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Approved
89 Civil PCL/MBI/14-074 Block E Ground Floor Column & Wall Setting out Plan 1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Approved
90 Civil PCL/MBI/14-075 Block B Ground Beams & SOG 1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Approved
1st 19-Dec-14 3-Jan-15 22-Dec-14 12 On-Time Rejected
91 Civil PCL/MBI/14-076 Block D Ground Beams & SOG
2nd 21-Jan-15 5-Feb-15 9-Feb-15 (4) Delayed Approved
92 Civil PCL/MBI/14-077 Fuel Storage Tank Wall & Slab 1st 1-Jan-15 16-Jan-15 6-Jan-15 10 On-Time Approved with Comments
1st 26-Dec-14 10-Jan-15 6-Jan-15 4 On-Time Rejected
93 Civil PCL/MBI/14-078 Collection Tank Wall & Slab 2nd 21-Jan-15 5-Feb-15 1-Feb-15 4 On-Time Rejected
3rd 2-Feb-15 17-Feb-15 2-Feb-15 15 On-Time Approved with Comments
94 Civil PCL/MBI/14-079 GROUND FLOOR BLOCK C & D COLUMN & WALL SETTING OUT PLAN 1st 21-Jan-15 5-Feb-15 9-Feb-15 (4) Delayed Approved
95 Civil PCL/MBI/14-080 Block F Ground Floor Column & Wall Setting Out Plan 1st 30-Jan-15 14-Feb-15 26-Feb-15 (12) Delayed Approved
96 Civil PCL/MBI/14-081 U.G Storm Water Tank Excavation Plan & Sections 1st 30-Jan-15 14-Feb-15 26-Feb-15 (12) Delayed Approved
97 Civil PCL/MBI/14-082 Water Body Part-2 SOG Bams & Wall 1st 30-Jan-15 14-Feb-15 26-Feb-15 (12) Delayed Approved
1st 7-Feb-15 22-Feb-15
98 Civil PCL/MBI/14-083 Parking Upper Basement Slab & Column Pour Plan & Detail
2nd 5-May-15 20-May-15 21-May-15 (1) Delayed Approved with Comments
99 Civil PCL/MBI/14-084 Block F Ground Floor Slab & Column pour Plan 1st 7-Feb-15 22-Feb-15 18-Feb-15 4 On-Time Approved
100 Civil PCL/MBI/14-085 Block F First Floor Slab & Column pour Plan 1st 7-Feb-15 22-Feb-15 18-Feb-15 4 On-Time Approved
101 Civil PCL/MBI/14-086 Block D Lower Ground Floor Slab & Ground SOG Pour Plan & Detail 1st 7-Feb-15 22-Feb-15 18-Feb-15 4 On-Time Approved
102 Civil PCL/MBI/14-087 Block C Lower Ground Slab Pour Plan 1st 7-Feb-15 22-Feb-15 18-Feb-15 4 On-Time Approved
103 Civil PCL/MBI/14-088 MS TOWER BASE PLATE SETTING OUT PLAN AND SECTION 1st 9-Feb-15 24-Feb-15 10-Feb-15 14 On-Time Approved
104 Civil PCL/MBI/14-089 BLOCK C & d FIRST FLOOR COLUMN & WALL SETTING OUT PLAN 1st 24-Feb-15 11-Mar-15 25-Feb-15 14 On-Time Approved
105 Civil PCL/MBI/14-090 BLOCK C & D 2ND FLOOR COLUMNS & WALL SETTING OUT PLAN 1st 24-Feb-15 11-Mar-15 25-Feb-15 14 On-Time Approved
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
106 Civil PCL/MBI/14-091 BLOCK F FIRST FLOOR COLUMN & WALL SETTING OUT PLAN 1st 24-Feb-15 11-Mar-15 25-Feb-15 14 On-Time Approved
107 Civil PCL/MBI/14-092 GROUND FLOOR FAIR FACED ELEMENTS 1st 2-Mar-15 17-Mar-15 (196) Delayed Pending
108 Civil PCL/MBI/14-093 FIRST FLOOR FAIR FACED ELEMENTS 1st 2-Mar-15 17-Mar-15 23-May-15 (67) Delayed Approved with comments AutoCAD file with
109 Civil PCL/MBI/14-094 SECOND FLOOR FAIR FACED ELEMENTS 1st 2-Mar-15 17-Mar-15 23-May-15 (67) Delayed Approved with comments amendments shared.
110 Civil PCL/MBI/14-095 MECHANICAL FLOOR FAIR FACED ELEMENTS 1st 2-Mar-15 17-Mar-15 23-May-15 (67) Delayed Approved with comments Formal approval is
111 Civil PCL/MBI/14-096 DOMESTIC WATER TANK WALL & SLAB (TOP & BOTTOM) 1st 2-Mar-15 17-Mar-15 16-Mar-15 1 On-Time Approved
112 Civil PCL/MBI/14-097 PARKING UPPER BASEMENT R-WALL POUR PLAN 1st 2-Mar-15 17-Mar-15 6-Mar-15 11 On-Time Approved
113 Civil PCL/MBI/14-098 TYPICAL CONSTRUCTION JOINT IN SHARE WALLS 1st 2-Mar-15 17-Mar-15 16-Mar-15 1 On-Time Approved
114 Civil PCL/MBI/14-099 BOUNDARY WALL DETAIL 1st 7-Mar-15 22-Mar-15 12-Mar-15 10 On-Time Approved
115 Civil PCL/MBI/14-100 STAIR #5 1st 3-Mar-15 18-Mar-15 14-Mar-15 4 On-Time Approved
116 Civil PCL/MBI/14-101 BOUNDARY WALL SURVEY PLAN 1st 7-Mar-15 22-Mar-15 12-Mar-15 10 On-Time Approved
117 Civil PCL/MBI/14-102 BOUNDARY WALL ELEVATION & SECTIONS 1st 7-Mar-15 22-Mar-15 10-Mar-15 12 On-Time Approved
118 Civil PCL/MBI/14-103 STAIR # 8 1st 11-Mar-15 26-Mar-15 17-Mar-15 9 On-Time Approved
119 Civil PCL/MBI/14-104 BLOCK A 1ST FLOOR- FLOOR SLAB POUR PLAN 1st 30-Mar-15 14-Apr-15 19-Jun-15 (66) Delayed Approved with Comments
120 Civil PCL/MBI/14-105 BLOCK B 1ST FLOOR- FLOOR SLAB POUR PLAN 1st 30-Mar-15 14-Apr-15 Superseded
121 Civil PCL/MBI/14-106 BLOCK C 1ST FLOOR- FLOOR SLAB POUR PLAN 1st 30-Mar-15 14-Apr-15 21-Jun-15 (68) Delayed Approved with Comments
122 Civil PCL/MBI/14-107 BLOCK D 1ST FLOOR- FLOOR SLAB POUR PLAN 1st 30-Mar-15 14-Apr-15 22-Jun-15 (69) Delayed Approved
123 Civil PCL/MBI/14-108 BLOCK E 1ST FLOOR- FLOOR SLAB POUR PLAN 1st 30-Mar-15 14-Apr-15 Superseded
124 Civil PCL/MBI/14-109 BLOCK B FF SETTING OUT PLAN 1st 11-Mar-15 26-Mar-15 17-Mar-15 9 On-Time Approved
125 Civil PCL/MBI/14-110 BLOCK B 2F SETTING OUT PLAN 1st 11-Mar-15 26-Mar-15 17-Mar-15 9 On-Time Approved
126 Civil PCL/MBI/14-111 BLOCK E FF SETTING OUT PLAN 1st 11-Mar-15 26-Mar-15 17-Mar-15 9 On-Time Approved
127 Civil PCL/MBI/14-112 BLOCK E 2F SETTING OUT PLAN 1st 11-Mar-15 26-Mar-15 17-Mar-15 9 On-Time Approved
128 Civil PCL/MBI/14-113 NORTH & EAST ELEVATION – FAIR FACED ELEMENTS 1st 30-Mar-15 14-Apr-15 28-May-15 (44) Delayed Approved with Comments
129 Civil PCL/MBI/14-114 SOUTH & WEST ELEVATION – FAIR FACED ELEMENTS 1st 30-Mar-15 14-Apr-15 28-May-15 (44) Delayed Approved
130 Civil PCL/MBI/14-115 NORTH COURTYARD ELEVATION & SOUTH COURTYARD ELEVATION – FAIR FACED ELEMENTS 1st 30-Mar-15 14-Apr-15 28-May-15 (44) Delayed Approved
131 Civil PCL/MBI/14-116 COURTYARD-2 NORTH & EAST ELEVATION – FAIR FACED ELEMENTS 1st 30-Mar-15 14-Apr-15 28-May-15 (44) Delayed Approved
132 Civil PCL/MBI/14-117 COURTYARD-2 SOUTH & WEST ELEVATION – FAIR FACED ELEMENTS 1st 30-Mar-15 14-Apr-15 28-May-15 (44) Delayed Approved
133 Civil PCL/MBI/14-118 SEWAGE TREATMENT PLANT 1st 16-Apr-15 21-Apr-15 21-Apr-15 - On-Time Approved As corrected
134 Civil PCL/MBI/14-119 STAIR #1 1st 30-Mar-15 14-Apr-15 25-May-15 (41) Delayed Approved
135 Civil PCL/MBI/14-120 STAIR #2 1st 30-Mar-15 14-Apr-15 25-May-15 (41) Delayed Approved
136 Civil PCL/MBI/14-121 STAIR #4 1st 30-Mar-15 14-Apr-15 14-May-15 (30) Delayed Approved
137 Civil PCL/MBI/14-122 STAIR #6 1st 30-Mar-15 14-Apr-15 14-May-15 (30) Delayed Approved
138 Civil PCL/MBI/14-123 STAIR #7 1st 30-Mar-15 14-Apr-15 23-Jun-15 (70) Delayed Approved
139 Civil PCL/MBI/14-124 STAIR #9 1st 30-Mar-15 14-Apr-15 23-Jun-15 (70) Delayed Approved
140 Civil PCL/MBI/14-125 EC-1 SUPPORT FACILITY PLAN & DETAIL 1st 18-Apr-15 3-May-15 20-Apr-15 13 On-Time Approved
141 Civil PCL/MBI/14-126 SC-3 SECURITY ROMM-1 PLAN & DETAIL 1st 16-Apr-15 1-May-15 21-Apr-15 10 On-Time Approved As corrected
As corrected Arch. To
142 Civil PCL/MBI/14-127 STAIR # 10 1st 16-Apr-15 1-May-15 21-Apr-15 10 On-Time Approved
confirm
As corrected Arch. To
143 Civil PCL/MBI/14-128 STAIR # 11 1st 16-Apr-15 1-May-15 21-Apr-15 10 On-Time Approved
confirm
144 Civil PCL/MBI/14-129 BLOCK A FIRST FLOOR SETTING OUT PLAN 1st 16-Apr-15 1-May-15 20-Apr-15 11 On-Time Approved As corrected
145 Civil PCL/MBI/14-130 BLOCK A SECONDT FLOOR SETTING OUT PLAN 1st 16-Apr-15 1-May-15 20-Apr-15 11 On-Time Approved As corrected
Re-Submission
1st 20-Apr-15 5-May-15 29-Apr-15 6 On-Time Rejected
146 Civil PCL/MBI/14-131 BOUNDARY WALL SOUTH SIDE SURVEY PLAN Required
2nd 11-May-15 26-May-15 (126) Delayed Pending
Re-Submission
1st 20-Apr-15 5-May-15 29-Apr-15 6 On-Time Rejected
147 Civil PCL/MBI/14-131A BOUNDARY WALL SOUTH SIDE ELEVATION Required
2nd 11-May-15 26-May-15 (126) Delayed Pending
148 Civil PCL/MBI/14-132 SURFACE PARKING SETTING OUT PLAN 1st 25-Apr-15 10-May-15 29-Apr-15 11 On-Time Approved with Comments
1ST 18-Dec-14 2-Jan-15 Rejected
149 Civil SH-RCP-PCL-A1-103 GROUND FLOOR REFLECTED CEILING DETAILS / PLANS Edge details required
2ND 18-Mar-15 2-Apr-15 (180) Delayed Pending
from GC.
1ST 16-Mar-15 31-Mar-15 Rejected
150 Civil SH-FL-PCL-A1-101 GROUND FLOOR FLOORING DETAILS / PLANS
2ND 13-Apr-15 28-Apr-15 28-May-15 (30) Delayed Approved
1ST 2-Apr-15 17-Apr-15 Rejected
151 Civil SH-FL-PCL-A1-201 FIRST FLOOR FLOORING DETAILS / PLANS
2ND 13-Apr-15 28-Apr-15 28-May-15 (30) Delayed Approved
152 Civil SH-FL-PCL-A1-201 SECOND FLOOR FLOORING DETAILS / PLANS 1ST 13-Apr-15 28-Apr-15 28-May-15 (30) Delayed Approved
Edge details required
153 Civil SH-RCP-PCL-A1-203 FIRST FLOOR REFLECTED CEILING DETAILS / PLANS 1ST 20-Apr-15 5-May-15 (147) Delayed Pending
from GC.
Edge details required
154 Civil SH-RCP-PCL-A1-303 SECOND FLOOR REFLECTED CEILING DETAILS / PLANS 1ST 28-Apr-15 13-May-15 (139) Delayed Pending
from GC.
1st 6-May-15 21-May-15 6-May-15 15 On-Time Rejected
155 Civil PCL/MBI/14-133 W-64 FRONT WALL 2nd 13-May-15 28-May-15 13-May-15 15 On-Time Rejected
3rd 13-May-15 28-May-15 3-Jun-15 (6) Delayed Approved with Comments
156 Civil PCL/MBI/14-134 BLOCK A SECOND FLOOR POUR PLAN 1st 13-Jun-15 28-Jun-15 22-Jun-15 6 Delayed Approved with Comments
157 Civil PCL/MBI/14-135 BLOCK B SECOND FLOOR POUR PLAN 1st 13-Jun-15 28-Jun-15 22-Jun-15 6 Delayed Approved with Comments
158 Civil PCL/MBI/14-136 BLOCK C SECOND FLOOR POUR PLAN 1st 13-Jun-15 28-Jun-15 22-Jun-15 6 Delayed Approved with Comments
159 Civil PCL/MBI/14-137 BLOCK D SECOND FLOOR POUR PLAN 1st 13-Jun-15 28-Jun-15 22-Jun-15 6 Delayed Approved with Comments
160 Civil PCL/MBI/14-138 BLOCK E SECOND FLOOR POUR PLAN 1st 13-Jun-15 28-Jun-15 22-Jun-15 6 Delayed Approved with Comments
PCL/MBI/14-139 PARKING LOWER BASEMENT FLOORING DETAIL 1st 7-Aug-15 22-Aug-15 (38) Pending
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
1 Mechanical SEL-193-SD-D-DETAIL-1 DRAINAGE STANDARD DETAIL-1 1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) On-Time REJECTED
2 Mechanical SEL-193-SD-D-DETAIL-2 DRAINAGE STANDARD DETAIL-2 1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed REJECTED
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
3 Mechanical SEL-193-SD-D-BAS.2 DRAINAGE LAYOUT FOR BASEMENT 2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
4 Mechanical SEL-193-SD-D-BAS.2.1 DRAINAGE LAYOUT FOR BASEMENT 2 (Part-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
5 Mechanical SEL-193-SD-D-BAS.2.2 DRAINAGE LAYOUT FOR BASEMENT 2 (Part-2) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
6 Mechanical SEL-193-SD-P-DETAIL-1 WATER SUPPLY STANDARD DETAIL 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed REJECTED To be re-submitted
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
7 Mechanical SEL-193-SD-P-BAS.2 WATER SUPPLY LAYOUT FOR BASEMENT 2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
8 Mechanical SEL-193-SD-P-BAS.2.1 WATER SUPPLY LAYOUT FOR BASEMENT 2 (Part-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
9 Mechanical SEL-193-SD-P-BAS.2.2 WATER SUPPLY LAYOUT FOR BASEMENT 2 (Part-2) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
10 Mechanical SEL-193-SD-M-DETAIL-1 HVAC STANDARD DETAIL-1 1st 28-Jul-14 12-Aug-14 5-Sep-14 (24) Delayed REJECTED To be re-submitted
11 Mechanical SEL-193-SD-M-DETAIL-2 HVAC STANDARD DETAIL-2 1st 28-Jul-14 12-Aug-14 5-Sep-14 (24) Delayed REJECTED To be re-submitted
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
12 Mechanical SEL-193-SD-M-BAS.1 HVAC LAYOUT FOR BASEMENT 2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
13 Mechanical SEL-193-SD-M-BAS.1.1 HVAC LAYOUT FOR BASEMENT 2 (Part-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 10-Jul-14 25-Jul-14 5-Sep-14 (42) Delayed 1st Rejected
14 Mechanical SEL-193-SD-M-BAS.1.2 HVAC LAYOUT FOR BASEMENT 2 (Part-2) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved

15 Mechanical PCL-SEL-193-SD-P-PARK WATER SUPPLY LAYOUT FOR SURFACE PARKING 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time REJECTED To be re-submitted

16 Mechanical PCL-SEL-193-SD-P-PARK-1.1 WATER SUPPLY LAYOUT FOR SURFACE PARKING (PART-1) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time REJECTED To be re-submitted

17 Mechanical PCL-SEL-193-SD-P-PARK-1.2 WATER SUPPLY LAYOUT FOR SURFACE PARKING (PART-2) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time REJECTED To be re-submitted

18 Mechanical PCL-SEL-193-SD-D-S.PARKING DRAINAGE LAYOUT FOR SURFACE PARKING 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time REJECTED To be re-submitted

19 Mechanical PCL-SEL-193-SD-D-S.PARK.1 DRAINAGE LAYOUT FOR SURFACE PARKING (PART-1) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time REJECTED To be re-submitted

20 Mechanical PCL-SEL-193-SD-D-S.PARK.2 DRAINAGE LAYOUT FOR SURFACE PARKING (PART-2) 1st 25-Aug-14 9-Sep-14 5-Sep-14 4 On-Time REJECTED To be re-submitted
1st 25-Aug-14 9-Sep-14 5-Sep-14 4 Delayed 1st Rejected
21 Mechanical PCL-SEL-193-SD-F-BAS.2 FIRE FIGHTING LAYOUT FOR BASEMENT-2 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 25-Aug-14 9-Sep-14 5-Sep-14 4 Delayed 1st Rejected
22 Mechanical PCL-SEL-193-SD-F-BAS.2.1 FIRE FIGHTING LAYOUT FOR BASEMENT-2 (PART-1) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved
1st 25-Aug-14 9-Sep-14 5-Sep-14 4 Delayed 1st Rejected
23 Mechanical PCL-SEL-193-SD-F-BAS.2.2 FIRE FIGHTING LAYOUT FOR BASEMENT-2 (PART-2) 2nd 3-Oct-14 18-Oct-14 27-Oct-14 (9) Delayed Rejected
3rd 30-Oct-14 14-Nov-14 11-Nov-14 3 On-Time Approved

24 Mechanical PCL-SEL-193-SD-D-LGF DRAINAGE LAYOUT FOR LOWER GROUND FLOOR 1st 10-Nov-14 25-Nov-14 Delayed Approved with Comments

25 Mechanical PCL-SEL-193-SD-D-LGF-1.1 DRAINAGE LAYOUT FOR LOWER GROUND FLOOR (PART-1) 1st 10-Nov-14 25-Nov-14 Delayed Approved with Comments

26 Mechanical PCL-SEL-193-SD-P-LGF WATER SUPPLY LAYOUT FOR LOWER GROUND FLOOR 1st 10-Nov-14 25-Nov-14 21-Jan-15 (57) Delayed Approved with Comments

27 Mechanical PCL-SEL-193-SD-P-LGF-1.1 WATER SUPPLY LAYOUT FOR LOWER GROUND FLOOR (PART-1) 1st 10-Nov-14 25-Nov-14 8-Jan-15 (44) Delayed Approved with Comments

28 Mechanical SEL-193-SD-M-BAS.1 HVAC LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

29 Mechanical SEL-193-SD-M-BAS.1.1 HVAC LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

30 Mechanical SEL-193-SD-M-BAS.1.2 HVAC LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE

31 Mechanical SEL-193-SD-F-BASE.1 FIRE PROTECTION LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

32 Mechanical SEL-193-SD-F-BASE.1.1 FIRE PROTECTION LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

33 Mechanical SEL-193-SD-F-BASE.1.2 FIRE PROTECTION LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved

34 Mechanical SEL-193-SD-D-BAS.1 DRAINAGE LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
35 Mechanical SEL-193-SD-D-BAS.1.1 DRAINAGE LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
36 Mechanical SEL-193-SD-D-BAS.1.2 DRAINAGE LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
37 Mechanical SEL-193-SD-P-BAS.1 WATER SUPPLY LAYOUT FOR BASEMENT 1 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
38 Mechanical SEL-193-SD-P-BAS.1.1 WATER SUPPLY LAYOUT FOR BASEMENT 1 (Part-1) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
39 Mechanical SEL-193-SD-P-BAS.1.2 WATER SUPPLY LAYOUT FOR BASEMENT 1 (Part-2) 1st 17-Nov-14 2-Dec-14 3-Dec-14 (1) Delayed Approved
HVAC LAYOUT FOR LOWER GROUND FLOOR 1 of 3 1st 13-Feb-14 Returned
40 Mechanical SEL-193-SD-M-LGF.1.1 HVAC LAYOUT FOR LOWER GROUND FLOOR 2 of 3
2nd 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
HVAC LAYOUT FOR LOWER GROUND FLOOR 3 of 3
41 Mechanical SEL-193-SD-M-GF HVAC LAYOUT FOR GROUND FLOOR 1st 8-Jan-15 23-Jan-15 13-Feb-15 (21) Delayed Returned
42 Mechanical SEL-193-SD-M-GF.1 HVAC LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
43 Mechanical SEL-193-SD-M-GF-1.2 HVAC Layout for Ground Floor (Block-B & C) 1st 24-Dec-14 8-Jan-15 13-Feb-15 (36) Delayed Returned
44 Mechanical SEL-193-SD-M-GF.1.3 HVAC LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 8-Jan-15 23-Jan-15 13-Feb-15 (21) Delayed Returned
45 HVAC LAYOUT FOR GROUND FLOOR (Block D) Part 1 of 2 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
Mechanical SEL-193-SD-M-GF.1.4
HVAC LAYOUT FOR GROUND FLOOR (Block D) Part 2 of 2 2nd 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
46 Mechanical SEL-193-SD-M-GF.1.5 HVAC LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
47 Mechanical SEL-193-SD-M-FF-1.2 HVAC LAYOUT FOR FIRST FLOOR (Block-B & C) 1st 11-Feb-15 26-Feb-15 19-Feb-15 7 On-Time REJECTED
48 Mechanical SEL-193-SD-D-GF DRAINAGE LAYOUT FOR GROUND FLOOR 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
49 Mechanical SEL-193-SD-D-GF-1.1 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
50 Mechanical SEL-193-SD-D-GF-1.2 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-B & C) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
51 Mechanical SEL-193-SD-D-GF-1.3 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
52 Mechanical SEL-193-SD-D-GF-1.4 DRAINAGE LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
53 Mechanical SEL-193-SD-D-FF DRAINAGE LAYOUT FOR FIRST FLOOR 1st 11-Feb-15 26-Feb-15 19-Feb-15 7 On-Time REJECTED
DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-A) 1st 11-Feb-15 26-Feb-15 19-Feb-15 7 On-Time REJECTED
54 Mechanical SEL-193-SD-D-FF-1.1 DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-A) PART 1 OF 2 2nd 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed REJECTED
DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-A) PART 2 OF 2 2nd 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed REJECTED
DRAINAGE LAYOUT FOR FIRST FLOOR (Block-B &C) 1st 11-Feb-15 26-Feb-15 19-Feb-15 7 On-Time REJECTED
55 Mechanical SEL-193-SD-D-FF-1.2
DRAINAGE LAYOUT FOR FIRST FLOOR (Block-B) 2nd 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed REJECTED
DRAINAGE LAYOUT FOR FIRST FLOOR (Block - E) 1st 11-Feb-15 26-Feb-15 19-Feb-15 7 On-Time REJECTED
56 Mechanical SEL-193-SD-D-FF-1.3 DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-C) PART 1 OF 2 2nd 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-C) PART 2 OF 2 2nd 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
DRAINAGE LAYOUT FOR FIRST FLOOR (Block-D & F) 1st 11-Feb-15 26-Feb-15 19-Feb-15 7 On-Time REJECTED
Re-Submission
57 Mechanical SEL-193-SD-D-FF-1.4 DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-D) PART 1 OF 2 2nd 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
Required
DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-D) PART 2 OF 2 2nd 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
58 Mechanical SEL-193-SD-D-FF-1.5 DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-E) 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Rejected
59 Mechanical SEL-193-SD-D-FF-1.6 DRAINAGE LAYOUT FOR FIRST FLOOR ( Block-F) 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Rejected
DRAINAGE LAYOUT FOR SECOND FLOOR ( Block-A) PART 1 OF 2 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Rejected
60 Mechanical SEL-193-SD-D-SF-1.1
DRAINAGE LAYOUT FOR SECOND FLOOR ( Block-A) PART 2 OF 2 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Rejected
61 Mechanical SEL-193-SD-D-SF-1.2 DRAINAGE LAYOUT FOR SECOND FLOOR (Block-B) 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Rejected
DRAINAGE LAYOUT FOR SECOND FLOOR ( Block-C) PART 1 OF 2 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Rejected
62 Mechanical SEL-193-SD-D-SF-1.3
DRAINAGE LAYOUT FOR SECOND FLOOR ( Block-C) PART 2 OF 2 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
Re-Submission
DRAINAGE LAYOUT FOR SECONDFLOOR ( Block-D) PART 1 OF 2 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
Required
63 Mechanical SEL-193-SD-D-SF-1.4
Re-Submission
DRAINAGE LAYOUT FOR SECOND FLOOR ( Block-D) PART 2 OF 2 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
Required
64 Mechanical SEL-193-SD-D-SF-1.5 DRAINAGE LAYOUT FOR SECOND FLOOR ( Block-E) 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
65 Mechanical SEL-193-SD-D-SF-1.6 DRAINAGE LAYOUT FOR SECOND FLOOR ( Block-F) 1st 13-Apr-15 28-Apr-15 26-May-15 (28) Delayed Approved with Comments
66 Mechanical SEL-193-SD-P-GF WATER SUPPLY LAYOUT FOR GROUND FLOOR 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
67 Mechanical SEL-193-SD-P-GF-1.1 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 24-Feb-15 (66) Delayed Rejected
68 Mechanical SEL-193-SD-P-GF-1.2 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-B & C) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
69 Mechanical SEL-193-SD-P-GF-1.3 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
70 Mechanical SEL-193-SD-P-GF-1.4 WATER SUPPLY LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
71 Mechanical SEL-193-SD-P-FF WATER SUPPLY LAYOUT FOR FIRST FLOOR 1st 11-Feb-15 26-Feb-15 3-Mar-15 (5) Delayed Rejected
72 Mechanical SEL-193-SD-P-FF-1.1 WATER SUPPLY LAYOUT FOR FIRST FLOOR(BLOCK A) 1st 11-Feb-15 26-Feb-15 3-Mar-15 (5) Delayed Rejected
73 Mechanical SEL-193-SD-P-FF-1.2 WATER SUPPLY LAYOUT FOR FIRST FLOOR(BLOCK- B & C) 1st 11-Feb-15 26-Feb-15 3-Mar-15 (5) Delayed Rejected
74 Mechanical SEL-193-SD-P-FF-1.3 WATER SUPPLY LAYOUT FOR FIRST FLOOR (BLOCK-E) 1st 11-Feb-15 26-Feb-15 3-Mar-15 (5) Delayed Rejected
75 Mechanical SEL-193-SD-P-FF-1.4 WATER SUPPLY LAYOUT FOR FIRST FLOOR (BLOCK-D & F) 1st 11-Feb-15 26-Feb-15 3-Mar-15 (5) Delayed Rejected
76 Mechanical SEL-193-SD-P-SWT UNDER GROUND STORM WATER TANK 1st 5-Dec-14 20-Dec-14 26-Dec-14 (6) Delayed Approved
77 Mechanical SEL-193-SD-F-GF FIRE FIGHTING LAYOUT FOR GROUND FLOOR 1st 8-Jan-15 23-Jan-15 13-Feb-15 (21) Delayed Returned
78 Mechanical SEL-193-SD-F-GF-1 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-A) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
79 Mechanical SEL-193-SD-F-GF-1.3 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-E) 1st 8-Jan-15 23-Jan-15 13-Feb-15 (21) Delayed Returned
80 Mechanical SEL-193-SD-F-GF-1.4 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
81 Mechanical SEL-193-SD-F-GF-1.5 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-D & F) 1st 5-Dec-14 20-Dec-14 13-Feb-15 (55) Delayed Returned
82 Mechanical SEL-193-SD-F-GF-1.2 FIRE FIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-B & C) 1st 24-Dec-14 8-Jan-15 13-Feb-15 (36) Delayed Returned
83 Mechanical SEL-193-SD-F-FF-1.2 FIRE FIGHTING LAYOUT FOR FIRST FLOOR (BLOCK-B & C) 1st 11-Feb-15 26-Feb-15 Superseded
Adjustment due to
84 Mechanical SEL-193-SD- P & F -LGF-1 DOMESTIC WATER & FIRE RESERVE UG TANK 1 & 2 1st 31-Dec-14 15-Jan-15 7-Jan-15 8 Delayed Approved with Comments design change to be re-
submitted
85 Mechanical SEL-193-SD- Slee-LGF LOWER GROUND FLOOR SLEEVE 1st 31-Dec-14 15-Jan-15 8-Jan-15 7 On-Time Approved
86 Mechanical SEL-193-SD-P-WB-GF WATER BODY LAYOUT FOR GROUND FLOOR 1st 15-Jan-15 30-Jan-15 13-Feb-15 (14) Delayed Returned
87 Mechanical SEL-193-SD-P-WB-GF-1.1 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-1) 1st 15-Jan-15 30-Jan-15 13-Feb-15 (14) Delayed Returned
88 Mechanical SEL-193-SD-P-WB-GF-1.2 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-2) 1st 15-Jan-15 30-Jan-15 13-Feb-15 (14) Delayed Returned
89 Mechanical SEL-193-SD-P-WB-GF-1.3 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-3) 1st 15-Jan-15 30-Jan-15 13-Feb-15 (14) Delayed Returned
90 Mechanical SEL-193-SD-P-WB-GF-1.4 WATER SUPPLY LAYOUT FOR GROUND FLOOR (PART-4) 1st 15-Jan-15 30-Jan-15 13-Feb-15 (14) Delayed Returned
91 Mechanical PCL.MEP.06.0..01 PROPOSED LOCATION OF WALL OPENING 1st 23-Feb-15 10-Mar-15 Delayed Pending Not received by SMC
92 Mechanical PCL.MEP.06.04..01 PROPOSED LOCATION OF WALL OPENING (BLOCK C) 1st 23-Feb-15 10-Mar-15 Delayed Pending Not received by SMC
93 Mechanical SEL-193-SD-F-FF-1.2 5-Mar-15 20-Mar-15 6-Mar-15 14 REJECTED
1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED
94 Mechanical PCL-SEL-193-SD-M-GF-1.1 HVAC LAYOUT FOR GROUND FLOOR ( Block- A) Part 1 of 2
2nd 11-Sep-15 26-Sep-15
1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED
95 Mechanical PCL-SEL-193-SD-M-GF-1.1 HVAC LAYOUT FOR GROUND FLOOR ( Block- A) Part 2 of 2
2nd 11-Sep-15 26-Sep-15
1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED
96 Mechanical PCL-SEL-193-SD-M-GF-1.2 HVAC LAYOUT FOR GROUND FLOOR ( Block- B)
2nd 10-Sep-15 25-Sep-15
1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED
97 Mechanical PCL-SEL-193-SD-M-GF-1.3 HVAC LAYOUT FOR GROUND FLOOR ( Block- C) Part 1 of 2
2nd 10-Sep-15 25-Sep-15
1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED
98 Mechanical PCL-SEL-193-SD-M-GF-1.3 HVAC LAYOUT FOR GROUND FLOOR ( Block- C) Part 2 of 2
2nd 10-Sep-15 25-Sep-15
99 Mechanical PCL-SEL-193-SD-M-GF-1.4 HVAC LAYOUT FOR GROUND FLOOR ( Block- D) Part 1 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
100 Mechanical PCL-SEL-193-SD-M-GF-1.4 HVAC LAYOUT FOR GROUND FLOOR ( Block- D) Part 2 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED
101 Mechanical PCL-SEL-193-SD-M-GF-1.5 HVAC LAYOUT FOR GROUND FLOOR ( Block- E)
2nd 10-Sep-15 25-Sep-15
102 Mechanical PCL-SEL-193-SD-M-GF-1.6 HVAC LAYOUT FOR GROUND FLOOR ( Block- F) 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
103 Mechanical PCL-SEL-193-SD-M-FF-1.1 HVAC LAYOUT FOR FIRST FLOOR ( Block- A) Part 1 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
104 Mechanical PCL-SEL-193-SD-M-FF-1.1 HVAC LAYOUT FOR FIRST FLOOR ( Block- A) Part 2 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
105 Mechanical PCL-SEL-193-SD-M-FF-1.2 HVAC LAYOUT FOR FIRST FLOOR ( Block- B) 1st 21-Sep-15 6-Oct-15 7 Pending
106 Mechanical PCL-SEL-193-SD-M-FF-1.3 HVAC LAYOUT FOR FIRST FLOOR ( Block- C) 1st 21-Sep-15 6-Oct-15 7 Pending
107 Mechanical PCL-SEL-193-SD-M-FF-1.4 HVAC LAYOUT FOR FIRST FLOOR ( Block- D) Part 1 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
108 Mechanical PCL-SEL-193-SD-M-FF-1.4 HVAC LAYOUT FOR FIRST FLOOR ( Block- D) Part 2 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
109 Mechanical PCL-SEL-193-SD-M-FF-1.5 HVAC LAYOUT FOR FIRST FLOOR ( Block- E) 1st 21-Sep-15 6-Oct-15 7 Pending
110 Mechanical PCL-SEL-193-SD-M-FF-1.6 HVAC LAYOUT FOR FIRST FLOOR ( Block- E) 1st 21-Sep-15 6-Oct-15 7 Pending
111 Mechanical PCL-SEL-193-SD-P-GF-1.1 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- A) Part 1 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required

112 Mechanical PCL-SEL-193-SD-P-GF-1.1 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- A) Part 2 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required

113 Mechanical PCL-SEL-193-SD-P-GF-1.2 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- B) 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required

114 Mechanical PCL-SEL-193-SD-P-GF-1.3 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- C) Part 1 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required

115 Mechanical PCL-SEL-193-SD-P-GF-1.3 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- C Part 2 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required
116 Mechanical PCL-SEL-193-SD-P-GF-1.4 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- D) Part 1 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
117 Mechanical PCL-SEL-193-SD-P-GF-1.4 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- D) Part 2 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
118 Mechanical PCL-SEL-193-SD-P-GF-1.5 WATER SUPPLY LAYOUT FOR GROUND FLOOR ( Block- E) 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required

119 Mechanical PCL-SEL-193-SD-P-GF-1.6 WATER SUPPLYLAYOUT FOR GROUND FLOOR ( Block- F) 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required
120 Mechanical PCL-SEL-193-SD-P-FF-1.1 WATER SUPPLY LAYOUT FOR FIRST FLOOR (BLOCK-A) 1st 21-Sep-15 6-Oct-15 7 Pending
121 Mechanical PCL-SEL-193-SD-P-FF-1.2 WATER SUPPLY LAYOUT FOR FIRST FLOOR (BLOCK-B) 1st 21-Sep-15 6-Oct-15 7 Pending
122 Mechanical PCL-SEL-193-SD-P-FF-1.3 WATER SUPPLY LAYOUT FOR FIRST FLOOR (BLOCK-D) 1st 21-Sep-15 6-Oct-15 7 Pending
123 Mechanical PCL-SEL-193-SD-P-FF-1.4 WATER SUPPLY LAYOUT FOR FIRST FLOOR (BLOCK-E) 1st 21-Sep-15 6-Oct-15 7 Pending
124 Mechanical PCL-SEL-193-SD-P-FF-1.5 WATER SUPPLY LAYOUT FOR FIRST FLOOR (BLOCK-F) 1st 21-Sep-15 6-Oct-15 7 Pending
125 Mechanical PCL-SEL-193-SD-F-GF-1.1 FIRE WORK LAYOUT FOR GROUND FLOOR ( Block- A) Part 1 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
126 Mechanical PCL-SEL-193-SD-F-GF-1.1 FIRE WORK LAYOUT FOR GROUND FLOOR ( Block- A) Part 2 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
127 Mechanical PCL-SEL-193-SD-F-GF-1.2 FIRE WORK LAYOUT FOR GROUND FLOOR ( Block- B) 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
128 Mechanical PCL-SEL-193-SD-F-GF-1.3 FIRE WORK LAYOUT FOR GROUND FLOOR ( Block- C) Part 1 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
129 Mechanical PCL-SEL-193-SD-F-GF-1.3 FIRE WORK LAYOUT FOR GROUND FLOOR ( Block- C) Part 2 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
130 Mechanical PCL-SEL-193-SD-F-GF-1.4 FIRE WORKLAYOUT FOR GROUND FLOOR ( Block- D) Part 1 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
131 Mechanical PCL-SEL-193-SD-F-GF-1.4 FIRE WORK LAYOUT FOR GROUND FLOOR ( Block- D) Part 2 of 2 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
132 Mechanical PCL-SEL-193-SD-F-GF-1.5 FIRE WORK LAYOUT FOR GROUND FLOOR ( Block- E) 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
133 Mechanical PCL-SEL-193-SD-F-GF-1.6 FIRE WORKLAYOUT FOR GROUND FLOOR ( Block- F) 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
134 Mechanical PCL-SEL-193-SD-F-FF-1 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- A) Part 1 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
135 Mechanical PCL-SEL-193-SD-F-FF-1 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- A) Part 2 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
136 Mechanical PCL-SEL-193-SD-F-FF-1.2 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- B) 1st 21-Sep-15 6-Oct-15 7 Pending
137 Mechanical PCL-SEL-193-SD-F-FF-1.3 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- C) 1st 21-Sep-15 6-Oct-15 7 Pending
138 Mechanical PCL-SEL-193-SD-F-FF-1.4 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- D) Part 1 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
139 Mechanical PCL-SEL-193-SD-F-FF-1.4 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- D) Part 2 of 2 1st 21-Sep-15 6-Oct-15 7 Pending
140 Mechanical PCL-SEL-193-SD-F-FF-1.5 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- E) 1st 21-Sep-15 6-Oct-15 7 Pending
141 Mechanical PCL-SEL-193-SD-F-FF-1.6 FIRE WORK LAYOUT FOR FIRST FLOOR ( Block- F) 1st 21-Sep-15 6-Oct-15 7 Pending
142 Mechanical PCL-SEL-193-SD-GF-01 OF 3 MEP TYP COORDINATED SECTION DRAWINGS 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed REJECTED Resubmission Required
143 Mechanical PCL-SEL-193-SD-GF-02 OF 3 MEP TYP COORDINATED SECTION DRAWINGS
2nd 10-Sep-15 25-Sep-15
144 Mechanical PCL-SEL-193-SD-GF-03 OF 3 MEP TYP COORDINATED SECTION DRAWINGS 1st 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
145 Mechanical PCL-SEL-193-SD-M-PR-1 MEP DRAWING CENTRAL PLANT ROOM 1st 9-Jun-15 24-Jun-15 (97) Delayed Pending
146 Mechanical PCL-SEL-193-SD-M-PR-1.1 MEP DRAWING CENTRAL PLANT ROOM 1st 9-Jun-15 24-Jun-15 (97) Delayed Pending
147 Mechanical PCL-SEL-193-SD-STP-1 MEP DRAWING SEWERAGE TREATMENT TANK 1st 9-Jun-15 24-Jun-15 (97) Delayed Pending
148 Mechanical PCL-SEL-193-SD-M-LGF MEP Coordination Sections Lower Ground Floor 1st 25-Apr-15 42134 6-Aug-15 (142) Approved with Comments
Delayed
SEL-193-SD-F-LGF-1.1 FIRE FIGHTING LAYOUT FOR LOWER GROUND FLOOR 1st 13-Feb-15 Returned
PCL-SEL-193-SD-F-LGF-1.1 Fire Fighting Layout L.G Floor 1 of 3
149 Mechanical
PCL-SEL-193-SD-F-LGF-1.1 Fire Fighting Layout L.G Floor 2of 3 2nd 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
PCL-SEL-193-SD-F-LGF-1.1 Fire Fighting Layout L.G Floor 3of 3
PCL-SEL-193-SD-P-LGF-1.1 Water Supply Layout For G.F Part 1 of 3
150 Mechanical PCL-SEL-193-SD-P-LGF-1.1 Water Supply Layout For G.F Part 2 of 3 2nd 25-Apr-15 10-May-15 6-Aug-15 (88) Delayed Approved with Comments
PCL-SEL-193-SD-P-LGF-1.1 Water Supply Layout For G.F Part 3 of 3
151 Mechanical PCL-SEL-193-SD-F-PR-1 1st 11-Sep-15 26-Sep-15 (3) Delayed Pending
152 Mechanical PCL-SEL-193-SD-F-PR-1.1 1st 11-Sep-15 26-Sep-15 (3) Delayed Pending
153 Mechanical PCL-SEL-193-FF-1.7 MEP TYP COORN SECTION -FIRST FLOOR- PAGE 1 OF 2 1st 21-Sep-15 6-Oct-15 Pending
154 Mechanical PCL-SEL-193-FF-1.7 MEP TYP COORN SECTION -FIRST FLOOR- PAGE 2 OF 2 1st 21-Sep-15 6-Oct-15 Pending
Returned due to minor
changes "Re-
1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
Mechanical Shop
1 Electrical MEP-E-04-05-01.01 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-A) PART 1 of 2
Drawing is required"
2nd 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed
3rd 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Resubmission Required

2 Electrical MEP-E-04-05-01.02 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR GROUND FLOOR (BLOCK-A) PART 2 of 2 1st 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Resubmission Required
Returned due to minor
changes "Re-
1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
3 Electrical MEP-E-05-05-01 ELECTRICAL SYSTEM 1 LAYOUT FOR GROUND FLOOR (BLOCK- A)
Mechanical Shop
Drawing is required"
2nd 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed Approved with comments
Returned due to minor
changes "Re-
1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
4 Electrical MEP-E-07-05-01 IT & SECURITY LAYOUT FOR GROUND FLOOR (BLOCK- A)
Mechanical Shop
Drawing is required"
2nd 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed REJECTED
Returned due to minor
changes "Re-
1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
5 Electrical MEP-E-04-05-03 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR GROUND FLOOR (BLOCK- E) Mechanical Shop
Drawing is required"
Re-submission
2nd 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved with comments
Required
Returned due to minor
changes "Re-
6 Electrical MEP-E-05-05-03 ELECTRICAL SYSTEM 1 LAYOUT FOR GROUND FLOOR (BLOCK- E) 1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
Mechanical Shop
Drawing is required"
Returned due to minor
changes "Re-
7 Electrical MEP-E-07-05-03 IT & SECURITY LAYOUT FOR GROUND FLOOR (BLOCK- E) 1st 14-Jul-14 29-Jul-14 15-Aug-14 (17) Delayed Returned submission along
Mechanical Shop
Drawing is required"
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
8 Electrical PCL-MEP-E04-01.01 Required
LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed Approved with comments
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
9 Required
Electrical PCL-MEP-E04-01.02 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 29-Oct-14 (15) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
10 Required
Electrical PCL-MEP-E05-01.01 ELECTRICAL SYSTEM 1 LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
11 Required
Electrical PCL-MEP-E05-01.02 ELECTRICAL SYSTEM 1 LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
Required
12 Electrical PCL-MEP-E06-01.01 ELECTRICAL SYSTEM 2 LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
13 Required
Electrical PCL-MEP-E06-01.02 ELECTRICAL SYSTEM 2 LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
14 Required
Electrical PCL-MEP-E07-01.01 IT & SECURITY LAYOUT FOR BASEMENT-2 (PART-1)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
15 Required
Electrical PCL-MEP-E07-01.02 IT & SECURITY LAYOUT FOR BASEMENT-2 (PART-2)
2nd 1-Sep-14 16-Sep-14 16-Sep-14 -
3rd 29-Sep-14 14-Oct-14 5-Nov-14 (22) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
Required
Returned due to minor
changes "Re-
2nd 1-Sep-14 16-Sep-14 17-Sep-14 (1) Delayed submission along
16 Electrical PCL-MEP-E06-05.01 ELECTRICAL SYSTEM 2 LAYOUT FOR GROUND FLOOR BLOCK A PART 1 OF 2
Mechanical Shop
Drawing is required"
3rd 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed
4th 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Resubmission Required

17 Electrical PCL-MEP-E06-05.02 ELECTRICAL SYSTEM 2 LAYOUT FOR GROUND FLOOR BLOCK A PART 2 OF 2 1ST 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Resubmission Required
Re Submission
1st 9-Jul-14 24-Jul-14 7-Aug-14 (14) Delayed Approved with comments
Required
Returned due to minor
changes "Re-
18 Electrical PCL-MEP-E06-05.03 ELECTRICAL SYSTEM 2 LAYOUT FOR GROUND FLOOR BLOCK E 2nd 1-Sep-14 16-Sep-14 17-Sep-14 (1) Delayed Returned submission along
Mechanical Shop
Drawing is required"
3rd 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Resubmission Required
Re Submission
1st 9-Jul-14 24-Jul-14 13-Aug-14 (20) Delayed Approved with comments
19 Electrical PCL-MEP-E10.01 LIGHTNING PROTECTION LAYOUT FOR ROOF Required
2nd 1-Sep-14 16-Sep-14 18-Sep-14 (2) Delayed Approved with comments
Re Submission
1st 9-Jul-14 24-Jul-14 13-Aug-14 (20) Delayed Approved with comments
20 Electrical PCL-MEP-E10.02 EARTHING SYSTEM LAYOUT Required
2nd 1-Sep-14 16-Sep-14 18-Sep-14 (2) Delayed Approved with comments
21 Electrical MEP-E-04-04-01 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR LOWER GROUND FLOOR ( PART PLAN) 1st 22-Oct-14 6-Nov-14 16-Feb-15 (102) Delayed Approved with comments
22 Electrical MEP-E-05-04-01 ELECTRICAL SYSTEM 1 LAYOUT FOR LOWER GROUND FLOOR ( PART PLAN ) 1st 22-Oct-14 6-Nov-14 16-Feb-15 (102) Delayed Approved with comments
1st 22-Oct-14 6-Nov-14 16-Feb-15 (102) Delayed Rejected
23 Electrical MEP-E-06-04-01.1 ELECTRICAL SYSTEM II LAYOUT FOR LOWER GROUND FLOOR ( PART PLAN )
2nd 11-May-15 26-May-15 5-Aug-15 (71) Delayed Approved with comments
23.1 Electrical MEP-E-06-04-01.1 ELECTRICAL SYSTEM II LAYOUT FOR LOWER GROUND FLOOR ( PLANT ROOM ) 1st 11-May-15 26-May-15 5-Aug-15 (71) Delayed Approved with comments
23.2 Electrical MEP-E-06-04-01.1 MEP SECTIONS AND GENERAL DETAIL FOR LOWER GROUND FLOOR 1st 11-May-15 26-May-15 5-Aug-15 (71) Delayed Approved with comments
24 Electrical MEP-E-07-04-01 IT & SECURITY LAYOUT FOR LOWER GROUND FLOOR ( PART PLAN ) 1st 22-Oct-14 6-Nov-14 16-Feb-15 (102) Delayed Pending
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
25 Electrical MEP-E-04-02-01 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT - 1 ( PART-I)
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Approved with comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
26 Electrical MEP-E-04-02-02 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR BASEMENT - 1 ( PART-II )
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Approved with comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
27 Electrical MEP-E-05-02-01 ELECTRICAL SYSTEM I LAYOUT FOR BASEMENT 1 ( PART I)
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Approved with comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
28 Electrical MEP-E-05-02-02 ELECTRICAL SYSTEM I LAYOUT FOR BASEMENT 1 ( PART II)
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
28 Electrical MEP-E-05-02-02 ELECTRICAL SYSTEM I LAYOUT FOR BASEMENT 1 ( PART II)
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Approved with comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
29 Electrical MEP-E-06-02.01 ELECTRICAL SYSTEM II LAYOUT FOR BASEMENT 1 ( PART I )
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Approved with comments
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
30 Electrical MEP-E-06-02.02 ELECTRICAL SYSTEM II LAYOUT FOR BASEMENT 1 ( PART II )
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time Approved with comments
Re-Submission
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
Required
31 Electrical MEP-E-07-02-01 IT & SECURITY LAYOUT FOR BASEMENT 1 ( PART - I ) Re-Submission
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Required
3rd 9-Dec-14 24-Dec-14 16-Feb-15 (54) Delayed Approved with comments
Re-Submission
1st 31-Oct-14 15-Nov-14 13-Nov-14 2 On-Time Returned
Required
32 Electrical MEP-E-07-02-02 IT & SECURITY LAYOUT FOR BASEMENT 1 ( PART - II) Re-Submission
2nd 17-Nov-14 2-Dec-14 25-Nov-14 7 On-Time
Required
3rd 9-Dec-14 24-Dec-14 16-Feb-15 (54) Delayed Approved with comments
Re-Submission
1st 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed Approved with comments
Required
33 Electrical MEP-E04-05.04.01 Lighting & Emergency Lighting Layout for Ground Floor Block D Part 1 of 2
2nd 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Re-Submission required
34 Electrical MEP-E04-05.04.02 Lighting & Emergency Lighting Layout for Ground Floor Block D Part 2 of 2 1st 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved with comments
35 Electrical MEP-E04-05.04.03 Lighting & Emergency Lighting Layout for Ground Floor BlockF Part Plan Block D 1st 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved with comments
36 Electrical MEP-E05-05.04 Electrical System 1 Layout for Ground Floor D & F 1st 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed Approved with comments
1st 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed
37 Electrical MEP-E06-05.04.01 Electrical System 2 Layout for Ground Floor D PART 1 of 2
2nd 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Re-Submission required

38 Electrical MEP-E06-05.04.02 Electrical System 2 Layout for Ground Floor D PART 2 of 2 1st 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved with comments Re-Submission required

39 Electrical MEP-E06-05.04.03 Electrical System 2 Layout for Ground Floor Block F PART PLAN BLOCK D 1st 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Without Coments and Status
40 Electrical MEP-E07-05.04 I.T & Security Layout for Ground Floor D & F 1st 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed Rejected
41 Electrical MEP-E06-09 Electrical System 2 Layout for Kitchen Equipment Ground Floor D & F 1st 5-Dec-14 20-Dec-14 16-Feb-15 (58) Delayed Approved with comments
1st 31-Dec-14 15-Jan-15 16-Feb-15 (32) Delayed
42 Electrical MEP-E-04-05-02.01 Lighting and Emergency Lighting Layout for Ground Floor ( Block -B)
2nd 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Re-Submission required

43 Electrical MEP-E-04-05-02.02 Lighting and Emergency Lighting Layout for Ground Floor ( Block -C)Part Plan of Block B 1st 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Re-Submission required
44 Electrical MEP-E-05-05-02 Electrical System 1 Layout For Ground Floor ( Block- B and C ) 1st 31-Dec-14 15-Jan-15 16-Feb-15 (32) Delayed Approved with comments
1st 31-Dec-14 15-Jan-15 16-Feb-15 (32) Delayed
45 Electrical MEP-E-06-05-02.01 Electrical System II Layout for Ground Floor ( Block B)
2nd 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Approved Re-Submission required

46 Electrical MEP-E-06-05-02.02 Electrical System II Layout for Ground Floor ( Block C) Part Plan of Block B 1st 16-Apr-15 1-May-15 30-Jun-15 (60) Delayed Comments Without Status

47 Electrical MEP-E-07-05-02 IT & Security Layout for Ground Floor ( Block-B and C) 1st 31-Dec-14 15-Jan-15 16-Feb-15 (32) Delayed REJECTED
48 Electrical MEP-E02 Standard Electrical Details 1st 15-Apr-15 30-Apr-15 Delayed Pending
49 Electrical MEP-E012.05.01 Lighting & Power DB Schedule for Ground Floor (Part 1 of 2) 1st 15-Apr-15 30-Apr-15 Delayed Pending
50 Electrical MEP-E012.05.02 Lighting & Power DB Schedule for Ground Floor (Part 2 of 2) 1st 15-Apr-15 30-Apr-15 Delayed Pending
51 Electrical MEP-E013.05.01 MEP Co-ordinated Section for Ground Floor Block A , B & C) 1st 15-Apr-15 30-Apr-15 6-Jul-15 (67) Delayed Approved with comments Re-Submission required

52 Electrical MEP-E013.05.02 MEP Co-ordinated Section for Ground Floor Block D , E & F) 1st 15-Apr-15 30-Apr-15 6-Jul-15 (67) Delayed Approved with comments Re-submission required
53 Electrical MEP-E06.03.01 ELECTRICAL SYSTEM-II LAYOUT FOR SURFACE PARKING (PART I) 1st 20-May-15 4-Jun-15 10-Jul-15 (36) Delayed Approved
54 Electrical MEP-E06.03.02 ELECTRICAL SYSTEM-II LAYOUT FOR SURFACE PARKING (PART II) 1st 20-May-15 4-Jun-15 10-Jul-15 (36) Delayed Approved
55 Electrical MEP-E04.03.01 LIGHTING AND EMERGENCY LIGHTING LAYOUT FOR SURFACE PARKING (PART I) 1st 20-May-15 4-Jun-15 10-Jul-15 (36) Delayed Approved
56 Electrical MEP-E04.03.02 LIGHTING AND EMERGENCY LIGHTINIG LAYOUT FOR SURFACE PARKING (PART I) 1st 20-May-15 4-Jun-15 10-Jul-15 (36) Delayed Approved
57 Electrical MEP-E012.01.SD DB'S SCHEDULE AND TYPICAL GENERAL DETAIL SECTION FOR SURFACE PARKING 1st 20-May-15 4-Jun-15 10-Jul-15 (36) Delayed Approved
58 Electrical MEP-05.05.03 Electrical System - I Layout for Ground Floor Block - E 1st 29-May-15 13-Jun-15 4-Aug-15 (52) Delayed Approved with comments
59 Electrical PCL-MEP-E04-06.01.01 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block A PART1/2) 1st 28-Sep-15 13-Oct-15 Pending
60 Electrical PCL-MEP-E04-06.01.02 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block A PART2/2) 1st 28-Sep-15 13-Oct-15 Pending
61 Electrical PCL-MEP-E04-06.02.01 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block B) 1st 28-Sep-15 13-Oct-15 Pending
62 Electrical PCL-MEP-E04-06.02.02 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block C PART PLAN OF BLOCK B) 1st 28-Sep-15 13-Oct-15 Pending
63 Electrical PCL-MEP-E04-06.03 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block E) 1st 28-Sep-15 13-Oct-15 Pending
64 Electrical PCL-MEP-E04-06.04.01 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block D PART1/2) 1st 28-Sep-15 13-Oct-15 Pending
65 Electrical PCL-MEP-E04-06.04.02 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block D PART2/2) 1st 28-Sep-15 13-Oct-15 Pending
66 Electrical PCL-MEP-E04-06.04.03 LIGHTING & EMERGENCY LAYOUT FOR F.F (Block F PART PLAN OF BLOCK D) 1st 28-Sep-15 13-Oct-15 Pending
67 Electrical PCL-MEP-E05-06 ELECTRICAL SYSTEM -1 LAYOUT FOR FF 1st 28-Sep-15 13-Oct-15 Pending
68 Electrical PCL-MEP-E05-06.01.01 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK A PART1/2) 1st 28-Sep-15 13-Oct-15 Pending
69 Electrical PCL-MEP-E05-06.01.02 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK A PART2/2) 1st 28-Sep-15 13-Oct-15 Pending
70 Electrical PCL-MEP-E05-06.02.01 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK B) 1st 28-Sep-15 13-Oct-15 Pending
71 Electrical PCL-MEP-E05-06.02.02 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK C PART PLAN OF BLOCK B) 1st 28-Sep-15 13-Oct-15 Pending
CONSULTANT'S RESPONSE
VARIANCE
S.NO. S.NO. REF NO. DESCRIPTION SUBMISSION VARIANCE STATUS SUBMITTAL STATUS REMARKS
RESPONSE ACTUAL (DAYS)
DUE RESPONSE
72 Electrical PCL-MEP-E05-06.03 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK E) 1st 28-Sep-15 13-Oct-15 Pending
73 Electrical PCL-MEP-E05-06.04.01 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK D PART 1/2) 1st 28-Sep-15 13-Oct-15 Pending
74 Electrical PCL-MEP-E05-06.04.02 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK D PART 2/2) 1st 28-Sep-15 13-Oct-15 Pending
75 Electrical PCL-MEP-E05-06.04.03 ELECTRICAL SYSTEM -1 LAYOUT FOR FF (BLOCK F PART PLAN BLOCK D) 1st 28-Sep-15 13-Oct-15 Pending
76 Electrical PCL-MEP-E06-06.01.01 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK A PART1/2) 1st 28-Sep-15 13-Oct-15 Pending
77 Electrical PCL-MEP-E06-06.01.02 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK A PART2/2) 1st 28-Sep-15 13-Oct-15 Pending
78 Electrical PCL-MEP-E06-06.02.01 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK B) 1st 28-Sep-15 13-Oct-15 Pending
79 Electrical PCL-MEP-E06-06.02.02 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK C PART PLAN OF BLOCK B) 1st 28-Sep-15 13-Oct-15 Pending
80 Electrical PCL-MEP-E06-06.03 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK E) 1st 28-Sep-15 13-Oct-15 Pending
81 Electrical PCL-MEP-E06-06.04.01 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK D PART 1/2) 1st 28-Sep-15 13-Oct-15 Pending
82 Electrical PCL-MEP-E06-06.04.02 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK D PART 2/2) 1st 28-Sep-15 13-Oct-15 Pending
83 Electrical PCL-MEP-E06-06.04.03 ELECTRICAL SYSTEM -2 LAYOUT FOR FF (BLOCK F PART PLAN BLOCK D) 1st 28-Sep-15 13-Oct-15 Pending
84 Electrical PCL-MEP-E07-06.01.01 IT & SECURITY LAYOUT FOR FF (BLOCK A PART1/2) 1st 28-Sep-15 13-Oct-15 Pending
85 Electrical PCL-MEP-E07-06.01.02 IT & SECURITY LAYOUT FOR FF (BLOCK A PART2/2) 1st 28-Sep-15 13-Oct-15 Pending
86 Electrical PCL-MEP-E07-06.02.01 IT & SECURITY LAYOUT FOR FF (BLOCK B) 1st 28-Sep-15 13-Oct-15 Pending
87 Electrical PCL-MEP-E07-06.02.02 IT & SECURITY LAYOUT FOR FF (BLOCK C PART PLAN OF BLOCK B) 1st 28-Sep-15 13-Oct-15 Pending
88 Electrical PCL-MEP-E07-06.03 IT & SECURITY LAYOUT FOR FF (BLOCK E) 1st 28-Sep-15 13-Oct-15 Pending
89 Electrical PCL-MEP-E07-06.04.01 IT & SECURITY LAYOUT FOR FF (BLOCK D PART 1/2) 1st 28-Sep-15 13-Oct-15 Pending
90 Electrical PCL-MEP-E07-06.04.02 IT & SECURITY LAYOUT FOR FF (BLOCK D PART 2/2) 1st 28-Sep-15 13-Oct-15 Pending
91 Electrical PCL-MEP-E07-06.04.03 IT & SECURITY LAYOUT FOR FF (BLOCK F PART PLAN BLOCK D) 1st 28-Sep-15 13-Oct-15 Pending
92 Electrical PCL-MEP-E012-06 LIGHTING & POWER SYSTEM DB'S SCHEDULE FOR FF 1st 28-Sep-15 13-Oct-15 Pending
93 Electrical PCL-MEP-E06-SD.02 LIGHTING & POWER SYSTEM DB'S CLOSET SECTIONS 1st 28-Sep-15 13-Oct-15 Pending
94 Electrical PCL-MEP-E013-06.01 MEP COORDINATED SECTIONS FOR FF (BLOCK A,B & C) 1st 28-Sep-15 13-Oct-15 Pending
95 Electrical PCL-MEP-E013-06.02 MEP COORDINATED SECTIONS FOR FF (BLOCK D & E) 1st 28-Sep-15 13-Oct-15 Pending
Critical Items

You might also like