You are on page 1of 5

BILL OF QUANTITIES BILL PART PAGE

MOHAMMED BIN RASHID AL MAKTOUM


CITY DISTRICT 11 SECTION Nr. Nr.
EXTERNAL ROADS AND UTILITIES - SEWERAGE WORKS
d 10 d/10/1
ITEM ITEM DESCRIPTION CESMM3 UNIT
AMOUNT
QUANTITY RATE
U.A.E. Dhs.

Ref.

PART 10 - SEWERAGE WORKS

PIPE WORK

Supply, lay and joint uPVC pipeline in trench


including special joints and connections,
detectable warning tape, testing and complete
as specified

A 160mm dia sewer pipe m 17.85 429.99 7,675.32

B Imported granular material bed and surround to m 17.85 72.53 1,294.66


160mm dia uPVC sewer pipe

Geotextile Filter Fabric membrane as per


Specifications

C 160mm dia.uPVC pipe m 17.85 127.85 2,282.12

PIPE WORK

Supply, lay and joint uPVC pipeline in trench


including special joints and connections,
detectable warning tape, testing and complete
as specified

D 200mm dia sewer pipe I515 m 907.19 573.32 520,110.17

E Imported granular material bed and surround to L531 m 907.19 91.72 83,207.47
200mm dia uPVC sewer pipe

Geotextile Filter Fabric membrane as per


Specifications

F 200mm dia.uPVC pipe L901 m 907.19 38.74 35,144.54

PIPE WORK

Supply, lay and joint uPVC pipeline in trench


including special joints and connections,
detectable warning tape, testing and complete
as specified

G 250mm dia sewer pipe I526 m 63.21 736.01 46,523.19

Beds and surrounds including warning tape as


applicable

H Imported granular material bed and surround to L532 m 63.21 105.77 6,685.72
250mm dia uPVC sewer pipe

Geotextile Filter Fabric membrane as per


Specifications

I 250mm dia.uPVC pipe L902 m 63.21 46.50 2,939.27

Carried to Part Summary Dhs. 705,862.46

Page 1 of 5
BILL OF QUANTITIES BILL PART PAGE
MOHAMMED BIN RASHID AL MAKTOUM
CITY DISTRICT 11 SECTION Nr. Nr.
EXTERNAL ROADS AND UTILITIES - SEWERAGE WORKS
d 10 d/10/2
ITEM ITEM DESCRIPTION CESMM3 UNIT AMOUNT
QUANTITY RATE
U.A.E. Dhs.
Ref.

PART 10 - SEWERAGE WORKS (Cont'd…)

PIPE WORK

Supply, lay and joint uPVC pipeline in trench


including special joints and connections,
detectable warning tape, testing and complete
as specified

A 315mm dia sewer pipe I535 m 920.72 838.72 772,226.28

Beds and surrounds including warning tape as


applicable

B Imported granular material bed and surround to L533 m 920.72 134.16 123,523.80
315mm dia uPVC sewer pipe

PIPE WORK MANHOLES AND PIPE WORK


ANCILLARIES

Geotextile Filter Fabric membrane as per


Specifications

C 315mm dia.uPVC pipe L903.1 m 920.72 46.50 42,813.48

PIPE WORK

Supply, lay and joint GRP pipes in trench in


accordance with specification

D 400mm dia sewer pipe I636 m 665.86 1,115.64 742,860.05

Beds and surrounds including warning tape as


applicable

E Imported granular material surround to 400mm dia L533 m 665.86 162.27 108,049.10
GRP pipe

PIPE WORK MANHOLES AND PIPE WORK


ANCILLARIES

Geotextile Filter Fabric membrane as per


Specifications

F for 400mm dia GRP pipe L903.2 m 665.60 54.23 36,095.49

Carried to Part Summary Dhs. 1,825,568.20

Page 2 of 5
BILL OF QUANTITIES BILL PART PAGE
MOHAMMED BIN RASHID AL MAKTOUM
CITY DISTRICT 11 SECTION Nr. Nr.
EXTERNAL ROADS AND UTILITIES - SEWERAGE WORKS
d 10 d/10/3
ITEM ITEM DESCRIPTION CESMM3 UNIT AMOUNT
QUANTITY RATE
U.A.E. Dhs.
Ref.

PART 10 - SEWERAGE WORKS (Cont'd…)

PIPE WORK

Supply, lay and joint GRP pipes in trench in


accordance with specification

A 500mm dia sewer pipe I636 m 247.30 1,348.08 333,380.18

Beds and surrounds including warning tape as


applicable

B Imported granular material surround to 500mm dia L533.1 m 247.30 232.44 57,482.41
GRP pipe

Geotextile Filter Fabric membrane as per


Specifications

C for 500mm dia GRP pipe L903.1 m 247.30 61.98 15,327.65


PIPE WORK

Supply, lay and joint GRP pipes in trench in


accordance with specification

D 600mm dia sewer pipe I638.1 m 256.03 1,580.50 404,655.42

Beds and surrounds including warning tape as


applicable

E Imported granular material surround to 600mm dia L533.2 m 256.03 278.91 71,409.33
GRP pipe

PIPE WORK MANHOLES AND PIPE WORK


ANCILLARIES

Geotextile Filter Fabric membrane as per


Specifications

F for 600mm dia GRP pipe L903.2 m 256.03 61.98 15,868.74

Connection to Pipes/Manhole

Connect new 600mm GRP pipe to existing K853 nr 3.00 89,598.00 268,794.00
manhole / Network including additional fillings,
excavation, backfill, diversions and all necessary
works and accessories to complete as per
drawings and specification.
LM 256.00
Non disruptive special pipe laying using micro
tunneling method for installing pipes. (The
rate shall include for all caissons, grouting,
service diversions, control and diversion of
existing flows in pipes by blocking, plugging
or over pumping during 'no dig' operations.)

G Nominal bore 600 mm dia GRP pipe using Pipe K135 nr 2.00 13,832.42 27,664.84
Jacking Method
LM 56.00

Carried to Part Summary Dhs. 1,194,582.57

Page 3 of 5
BILL OF QUANTITIES BILL PART PAGE
MOHAMMED BIN RASHID AL MAKTOUM
CITY DISTRICT 11 SECTION Nr. Nr.
EXTERNAL ROADS AND UTILITIES - SEWERAGE WORKS
d 10 d/10/4
ITEM ITEM DESCRIPTION CESMM3 UNIT AMOUNT
QUANTITY RATE
U.A.E. Dhs.
Ref.

PART 10 - SEWERAGE WORKS (Cont'd…)

Manhole Type A complete as detailed in dwgs.


including frame and cover

A Depth 0 - 3.5m K134.1 nr 7.00 46,345.89 324,421.23

Manhole Type B complete as detailed in dwgs.


including frame and cover

B Depth 0 - 4.0m K134.2 nr 17.00 48,902.58 831,343.86

Manhole Type C complete as detailed in dwgs.


including frame and cover

C Depth 0 - 5.0m K137 nr 15.00 102,349.34 1,535,240.10

Carried to Part Summary Dhs. 2,691,005.19

Page 4 of 5
BILL OF QUANTITIES BILL PART PAGE
MOHAMMED BIN RASHID AL MAKTOUM
CITY DISTRICT 11 SECTION Nr. Nr.
EXTERNAL ROADS AND UTILITIES - SEWERAGE WORKS
d 10 d/10/5
ITEM ITEM DESCRIPTION AMOUNT
U.A.E. Dhs.

PART 10 - - SEWERAGE WORKS

PART SUMMARY

Page d/10/1 705,862.46

Page d/10/2 1,825,568.20

Page d/10/3 1,194,582.57

Page d/10/4 2,691,005.19

Total for Part 10 - Dubai Municipality - Sewerage Works Dhs. 6,417,018.42


Carried to Grand Summary

Page 5 of 5

You might also like