Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Actual Total Cost July 2022
Duration Complete
03 10 17
335 BUILDING 150 104 57.61% 01-Aug-22 A 30-Jan-23 68 $76,480.00
Actual Level of Effort Remaining Work Page 1 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
BUILDING Classic Schedule Layout 08-Aug-22 11:08
August 2022 September 2022 October 2022
17 24 31 07 14 21 28 04 11 18 25 02 09
plumbing layout
fire alarm layout
sewerage design
earthing design
project budget estimation
contractor bidding
Actual Level of Effort Remaining Work Page 2 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
BUILDING Classic Schedule Layout 08-Aug-22 11:08
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Actual Total Cost July 2022
Duration Complete
03 10 17
A1230 erection of columns 0 0 100% 18-Jan-23 A 24-Jan-23 A $0.00
A1240 beam construction 0 0 100% 10-Jan-23 A 18-Jan-23 A $0.00
A1250 slab 5 0 100% 04-Jan-23 A 10-Jan-23 A $1,400.00
A1260 septic tank 5 6 80% 28-Dec-22 A 04-Jan-23 68 $0.00
A1280 car ramp 5 5 0% 22-Dec-22* 28-Dec-22 68 $0.00
A1270 lift pit 5 5 0% 16-Dec-22* 22-Dec-22 68 $0.00
A1290 stairs construction 5 5 0% 12-Dec-22 16-Dec-22 68 $0.00
A1300 brickwork 5 5 0% 06-Dec-22* 12-Dec-22 68 $0.00
335.6 Finishing Work 30 30 0% 04-Oct-22 15-Nov-22 68 $0.00
Actual Level of Effort Remaining Work Page 3 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
BUILDING Classic Schedule Layout 08-Aug-22 11:08
August 2022 September 2022 October 2022
17 24 31 07 14 21 28 04 11 18 25 02 09
Actual Level of Effort Remaining Work Page 4 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation