BUILDING Classic Schedule Layout 08-Aug-22 11:08

Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Actual Total Cost July 2022
Duration Complete
03 10 17
335 BUILDING 150 104 57.61% 01-Aug-22 A 30-Jan-23 68 $76,480.00

335.1 COMMERCIAL PROCESS/precuring 15 0 100% 01-Aug-22 A 15-Aug-22 A $5,080.00


A1020 Contractor hiring 5 0 100% 09-Aug-22 A 15-Aug-22 A $2,000.00
A1010 Hiring of consultant 5 0 100% 02-Aug-22 A 08-Aug-22 A $3,080.00
A1000 Land purchse 5 0 100% 01-Aug-22 A 05-Aug-22 A $0.00
335.2 Project Management 10 0 100% 16-Aug-22 A 26-Aug-22 A $17,200.00
A1030 project schedule 5 0 100% 20-Aug-22 A 26-Aug-22 A $15,000.00
A1040 communication plan 5 0 100% 16-Aug-22 A 20-Aug-22 A $2,200.00
335.3 Site Analysis 10 0 100% 27-Aug-22 A 06-Sep-22 A $16,000.00

A1050 sample for soil test 5 0 100% 01-Sep-22 A 06-Sep-22 A $8,000.00


A1060 soil report 5 0 100% 27-Aug-22 A 31-Aug-22 A $8,000.00
335.4 Design 45 5 98.32% 07-Sep-22 A 26-Oct-22 173 $21,800.00
A1140 structural design 5 0 100% 21-Oct-22 A 26-Oct-22 A $0.00
A1150 Architectural design 5 0 100% 15-Oct-22 A 20-Oct-22 A $2,000.00
A1160 electric drawings 5 0 100% 08-Oct-22 A 14-Oct-22 A $3,800.00
A1170 plumbing layout 5 0 100% 03-Oct-22 A 08-Oct-22 A $2,000.00
A1180 fire alarm layout 5 0 100% 27-Sep-22 A 03-Oct-22 A $2,000.00
A1200 sewerage design 5 0 100% 21-Sep-22 A 27-Sep-22 A $2,000.00
A1190 earthing design 5 0 100% 16-Sep-22 A 21-Sep-22 A $8,000.00
A1210 project budget estimation 5 0 100% 13-Sep-22 A 16-Sep-22 A $2,000.00
A1220 contractor bidding 5 5 80% 07-Sep-22 A 13-Sep-22 173 $0.00
335.5 Structure 127 22 66.87% 29-Oct-22 A 24-Jan-23 68 $16,400.00

335.5.1 substructure 35 0 100% 29-Oct-22 A 05-Dec-22 A $15,000.00


A1070 boring for piles 5 0 100% 29-Nov-22 A 05-Dec-22 A $2,800.00
A1080 installation of pile cage 5 0 100% 25-Nov-22 A 29-Nov-22 A $2,200.00
A1130 pouring of concrete for raft 5 0 100% 20-Nov-22 A 24-Nov-22 A $1,400.00
A1090 pouring of concrete 5 0 100% 15-Nov-22 A 19-Nov-22 A $1,400.00
A1100 anchoring 5 0 100% 09-Nov-22 A 14-Nov-22 A $2,200.00
A1110 excavation for foundation 5 0 100% 02-Nov-22 A 08-Nov-22 A $2,800.00
A1120 steel fixation for foundation 5 0 100% 29-Oct-22 A 02-Nov-22 A $2,200.00
335.5.2 superstructure 92 22 22.5% 06-Dec-22 A 24-Jan-23 68 $1,400.00

Actual Level of Effort Remaining Work Page 1 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
BUILDING Classic Schedule Layout 08-Aug-22 11:08
August 2022 September 2022 October 2022
17 24 31 07 14 21 28 04 11 18 25 02 09

15-Aug-22 A, 335.1 COMMERCIAL PROCESS/precuring


Contractor hiring
Hiring of consultant
Land purchse
26-Aug-22 A, 335.2 Project Management
project schedule
communication plan
06-Sep-22 A, 335.3 Site Analysis

sample for soil test


soil report

plumbing layout
fire alarm layout
sewerage design
earthing design
project budget estimation
contractor bidding

Actual Level of Effort Remaining Work Page 2 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
BUILDING Classic Schedule Layout 08-Aug-22 11:08
Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Actual Total Cost July 2022
Duration Complete
03 10 17
A1230 erection of columns 0 0 100% 18-Jan-23 A 24-Jan-23 A $0.00
A1240 beam construction 0 0 100% 10-Jan-23 A 18-Jan-23 A $0.00
A1250 slab 5 0 100% 04-Jan-23 A 10-Jan-23 A $1,400.00
A1260 septic tank 5 6 80% 28-Dec-22 A 04-Jan-23 68 $0.00
A1280 car ramp 5 5 0% 22-Dec-22* 28-Dec-22 68 $0.00
A1270 lift pit 5 5 0% 16-Dec-22* 22-Dec-22 68 $0.00
A1290 stairs construction 5 5 0% 12-Dec-22 16-Dec-22 68 $0.00
A1300 brickwork 5 5 0% 06-Dec-22* 12-Dec-22 68 $0.00
335.6 Finishing Work 30 30 0% 04-Oct-22 15-Nov-22 68 $0.00

A1380 glass works 0 0 0% 15-Nov-22 15-Nov-22 68 $0.00


A1370 sanatory work 5 5 0% 08-Nov-22 14-Nov-22 68 $0.00
A1360 windows 5 5 0% 01-Nov-22 07-Nov-22 68 $0.00
A1350 doors 5 5 0% 25-Oct-22 31-Oct-22 68 $0.00
A1340 tiles 5 5 0% 18-Oct-22 24-Oct-22 68 $0.00
A1330 ceiling work 5 5 0% 11-Oct-22 17-Oct-22 68 $0.00
A1320 plaster works 0 0 0% 11-Oct-22 11-Oct-22 68 $0.00
A1310 electrical conduting 5 5 0% 04-Oct-22 10-Oct-22 68 $0.00
335.7 Safety Works 15 15 0% 15-Nov-22 05-Dec-22 68 $0.00
A1410 fire extinguishers 5 5 0% 29-Nov-22 05-Dec-22 68 $0.00
A1400 fire alarm points 5 5 0% 22-Nov-22 28-Nov-22 68 $0.00
A1390 smoke detector 5 5 0% 15-Nov-22 21-Nov-22 68 $0.00
335.8 MEP Works 40 40 0% 06-Dec-22 30-Jan-23 68 $0.00
A1490 lights installation 5 5 0% 24-Jan-23 30-Jan-23 68 $0.00
A1480 cctv installation 5 5 0% 17-Jan-23 23-Jan-23 68 $0.00
A1470 electric duct 5 5 0% 10-Jan-23 16-Jan-23 68 $0.00
A1460 cable tray 5 5 0% 03-Jan-23 09-Jan-23 68 $0.00
A1450 main board 5 5 0% 27-Dec-22 02-Jan-23 68 $0.00
A1440 circuit breaker 5 5 0% 20-Dec-22 26-Dec-22 68 $0.00
A1430 switch board 5 5 0% 13-Dec-22 19-Dec-22 68 $0.00
A1420 fans installation 5 5 0% 06-Dec-22 12-Dec-22 68 $0.00

Actual Level of Effort Remaining Work Page 3 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
BUILDING Classic Schedule Layout 08-Aug-22 11:08
August 2022 September 2022 October 2022
17 24 31 07 14 21 28 04 11 18 25 02 09

Actual Level of Effort Remaining Work Page 4 of 4 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation