QCC PROJECT TIE-IN TIME SCHEDULE

标识号 Task Duration Time Start Complete 2023


11 12 1 2 3 4 5
23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28
1 QCC Saudi Clinker grinding Project Schedule 179 days? 2022/11/26 2023/5/23
2 Construction 179 days? 2022/11/26 2023/5/23
3 Mechanical & electrical installation 179 days? 2022/11/26 2023/5/23
4 Tie-in exissting clinker line shedule 179 days? 2022/11/26 2023/5/23
5 Part 1_511AC01 pan conveyor demolition & installation 68 days 2022/11/26 2023/2/1
6 Demolition 42 days 2022/11/26 2023/1/6
7 QCC scope 30 days 2022/11/26 2022/12/26
8 Housekeeping for tunnel under clinker silo,stairs,drive 30 days 2022/11/26 2022/12/26
unit platform
9 QCC provide safe procedure for rod gates and vibration 30 days 2022/11/26 2022/12/26
feeder to CDI
10 CDI scope 11 days 2022/12/27 2023/1/6
11 511AC01 pan conveyor demolition 11 days 2022/12/27 2023/1/6
12 Site mobilization & preparation 2 days 2022/12/27 2022/12/28
13 Remove the bucket & chain & roller 2 days 2022/12/29 2022/12/30
14 Remove the grinding building rain protection roof & 2 days 2022/12/31 2023/1/1
steel bracing
15 Remove the drive unit,drive sprocket & conveyor head 2 days 2023/1/2 2023/1/3
hood
16 Remove rail & supporting legs 3 days 2023/1/4 2023/1/6
17 Rod gate & vabriating feeder demolition 4 days 2022/12/31 2023/1/3
18 Installation 47 days 2022/12/17 2023/2/1
19 511AC01 pan conveyor installation 47 days 2022/12/17 2023/2/1
20 Pre-assemble chain & roller & bucket(section) 20 days 2022/12/17 2023/1/6
21 Steel structure reforcement(Not sure, based on design 5 days 2023/1/7 2023/1/11
calculation)
22 Install drive sprocket and tail sprocket 3 days 2023/1/12 2023/1/14
23 Install supporting legs and rail 5 days 2023/1/15 2023/1/19
24 Install chain & roller & bucket(section) 3 days 2023/1/20 2023/1/22
25 Install drive unit & auxiliary unit & alignment 3 days 2023/1/23 2023/1/25
26 Install conveyor rain shield & safety protection net 3 days 2023/1/23 2023/1/25
27 Refix grinding building steel bracing & rain protection 2 days 2023/1/26 2023/1/27
roof
28 Electrical Installation 10 days 2023/1/23 2023/2/1
29 Chute & dedusting duct installation 7 days 2023/1/26 2023/2/1
30 New rod gate & vabriating feeder 5 days 2023/1/23 2023/1/27
31 Part 2_512AC01 pan conveyor demolition & installation 68 days 2022/11/26 2023/2/1
32 Demolition 42 days 2022/11/26 2023/1/6
33 QCC scope 30 days 2022/11/26 2022/12/26
34 Housekeeping for tunnel under clinker silo,stairs,drive 30 days 2022/11/26 2022/12/26
unit platform

Task External task Only duration Deadline


Split External milestones Manual abstract assembly Key
QASSIM CEMENT NEW CEMENT MILL Milestone Inactive Milestones Manual abstract Key split
Abstract Inactive abstract Only start time Progress
Project abstract Manual tasks Only finish time

- CDI Started working on 1st Feb, 2022, but CDI received advanced payment on 11th Mar, 2022
- This schedule consider the owner issue L/C according to contract condition.
1 /6
QCC PROJECT TIE-IN TIME SCHEDULE
标识号 Task Duration Time Start Complete 2023
11 12 1 2 3 4 5
23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28
35 QCC provide safe procedure for rod gates and vibration 30 days 2022/11/26 2022/12/26
feeder to CDI
36 CDI scope 11 days 2022/12/27 2023/1/6
37 512AC01 pan conveyor demolition 11 days 2022/12/27 2023/1/6
38 Site mobilization & preparation 2 days 2022/12/27 2022/12/28
39 Remove the bucket & chain & roller 2 days 2022/12/29 2022/12/30
40 Remove the grinding building side wall rain protection 2 days 2022/12/31 2023/1/1
sheet & steel bracing
41 Remove the drive unit,drive sprocket & conveyor head 2 days 2023/1/2 2023/1/3
hood
42 Remove rail & supporting legs 3 days 2023/1/4 2023/1/6
43 Rod gate & vabriating feeder demolition 4 days 2022/12/31 2023/1/3
44 Installation 47 days 2022/12/17 2023/2/1
45 512AC01 pan conveyor installation 47 days 2022/12/17 2023/2/1
46 Pre-assemble chain & roller & bucket(section) 20 days 2022/12/17 2023/1/6
47 Steel structure reforcement(Not sure, based on design 5 days 2023/1/7 2023/1/11
calculation)
48 Install drive sprocket and tail sprocket 3 days 2023/1/12 2023/1/14
49 Install supporting legs and rail 5 days 2023/1/15 2023/1/19
50 Install chain & roller & bucket(section) 3 days 2023/1/20 2023/1/22
51 Install drive unit & auxiliary unit & alignment 3 days 2023/1/23 2023/1/25
52 Install conveyor rain shield & safety protection net 3 days 2023/1/23 2023/1/25
53 Refix grinding building steel bracing & side wall rain 2 days 2023/1/26 2023/1/27
protection sheet
54 Electrical Installation 10 days 2023/1/23 2023/2/1
55 Chute & dedusting duct installation 7 days 2023/1/26 2023/2/1
56 New rod gate & vabriating feeder 5 days 2023/1/23 2023/1/27
57 Part 3_512AC02 pan conveyor demolition & installation 68 days 2023/1/4 2023/3/12
58 Demolition 42 days 2023/1/4 2023/2/14
59 QCC scope 30 days 2023/1/4 2023/2/3
60 Housekeeping for tunnel under clinker silo,stairs,drive 30 days 2023/1/4 2023/2/3
unit platform
61 QCC provide safe procedure for rod gates and vibration 30 days 2023/1/4 2023/2/3
feeder to CDI
62 CDI scope 11 days 2023/2/4 2023/2/14
63 512AC02 pan conveyor demolition 11 days 2023/2/4 2023/2/14
64 Site mobilization & preparation 2 days 2023/2/4 2023/2/5
65 Remove the bucket & chain & roller 2 days 2023/2/6 2023/2/7
66 Remove the grinding building side wall rain protection 2 days 2023/2/8 2023/2/9
sheet & steel bracing
67 Remove the drive unit,drive sprocket & conveyor head 2 days 2023/2/10 2023/2/11
hood

Task External task Only duration Deadline


Split External milestones Manual abstract assembly Key
QASSIM CEMENT NEW CEMENT MILL Milestone Inactive Milestones Manual abstract Key split
Abstract Inactive abstract Only start time Progress
Project abstract Manual tasks Only finish time

- CDI Started working on 1st Feb, 2022, but CDI received advanced payment on 11th Mar, 2022
- This schedule consider the owner issue L/C according to contract condition.
2 /6
QCC PROJECT TIE-IN TIME SCHEDULE
标识号 Task Duration Time Start Complete 2023
11 12 1 2 3 4 5
23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28
68 Remove rail & supporting legs 3 days 2023/2/12 2023/2/14
69 Rod gate & vabriating feeder demolition 4 days 2023/2/8 2023/2/11
70 Installation 47 days 2023/1/25 2023/3/12
71 512AC02 pan conveyor installation 47 days 2023/1/25 2023/3/12
72 Pre-assemble chain & roller & bucket(section) 20 days 2023/1/25 2023/2/14
73 Steel structure reforcement(Not sure, based on design 5 days 2023/2/15 2023/2/19
calculation)
74 Install drive sprocket and tail sprocket 3 days 2023/2/20 2023/2/22
75 Install supporting legs and rail 5 days 2023/2/23 2023/2/27
76 Install chain & roller & bucket(section) 3 days 2023/2/28 2023/3/2
77 Install drive unit & auxiliary unit & alignment 3 days 2023/3/3 2023/3/5
78 Install conveyor rain shield & safety protection net 3 days 2023/3/3 2023/3/5
79 Refix grinding building steel bracing & side wall rain 2 days 2023/3/6 2023/3/7
protection sheet
80 Electrical Installation 10 days 2023/3/3 2023/3/12
81 Chute & dedusting duct installation 7 days 2023/3/6 2023/3/12
82 New rod gate & vabriating feeder 5 days 2023/3/3 2023/3/7
83 Part 4_Tie in existing belt conveyor 522BC1 & 523BC9 158 days? 2022/12/5 2023/5/11
84 Demolition 82 days? 2022/12/5 2023/2/24
85 QCC scope 60 days? 2022/12/5 2023/2/3
86 Housekeeping for belt conveyor 522BC01 & 523BC09 60 days? 2022/12/5 2023/2/3

87 Remove circulating cooling water pipes and firefighting 60 days? 2022/12/5 2023/2/3
water pipes from 522BC1 belt conveyor truss

88 Remove the cable from 522BC1 belt conveyor truss 60 days? 2022/12/5 2023/2/3
89 Remove the compressed air pipe from 523BC9 belt 60 days? 2022/12/5 2023/2/3
conveyor truss
90 CDI scope 21 days 2023/2/4 2023/2/24
91 Site mobilization & preparation 2 days 2023/2/4 2023/2/5
92 Remove rain protection roof and steel bracing 3 days 2023/2/6 2023/2/8
93 Remove belt conveyor 522BC1 & 523BC9 belt 2 days 2023/2/9 2023/2/10
94 Remove bracket,roller,frame according to design 4 days 2023/2/11 2023/2/14
95 Remove part of belt conveyor 522-BC01 truss (dimension 5 days 2023/2/15 2023/2/19
according to design) & temporary support
96 Remove part of belt conveyor 523-BC9 truss (dimension 5 days 2023/2/20 2023/2/24
according to design) & temporary support
97 Civil 44 days 2023/1/11 2023/2/24
98 Foundation 40 days 2023/1/11 2023/2/20
99 Civil handover to mechanical 3 days 2023/2/21 2023/2/24
100 Installation 123 days? 2023/1/9 2023/5/11
101 Transfer building installation 87 days? 2023/1/9 2023/4/5

Task External task Only duration Deadline


Split External milestones Manual abstract assembly Key
QASSIM CEMENT NEW CEMENT MILL Milestone Inactive Milestones Manual abstract Key split
Abstract Inactive abstract Only start time Progress
Project abstract Manual tasks Only finish time

- CDI Started working on 1st Feb, 2022, but CDI received advanced payment on 11th Mar, 2022
- This schedule consider the owner issue L/C according to contract condition.
3 /6
QCC PROJECT TIE-IN TIME SCHEDULE
标识号 Task Duration Time Start Complete 2023
11 12 1 2 3 4 5
23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28
102 Steel Structure fabrication 30 days 2023/1/9 2023/2/8
103 Steel structure Pre-assemble 15 days? 2023/2/9 2023/2/24
104 Steel structure transfer building installation 40 days 2023/2/25 2023/4/5
105 Belt conveyor truss installation 39 days? 2023/3/6 2023/4/13
106 525BC04 Belt conveyor truss fabrication & assemble 30 days? 2023/3/6 2023/4/5
107 525BC04 Belt conveyor truss installation 2 days 2023/4/6 2023/4/7
108 525BC05 Belt conveyor new section truss fabrication & 25 days? 2023/3/13 2023/4/7
assemble
109 525BC05 Belt conveyor new section truss installation 2 days 2023/4/8 2023/4/9
110 515BC02 Belt conveyor new section truss fabrication & 25 days? 2023/3/15 2023/4/9
assemble
111 515BC02 Belt conveyor new section truss installation 2 days 2023/4/10 2023/4/11
112 515BC01 Belt conveyor new section truss modification 7 days 2023/4/4 2023/4/11

113 515BC01 Belt conveyor truss installation 2 days 2023/4/12 2023/4/13


114 525BC04 Belt conveyor truss & belt conveyor installation 10 days? 2023/4/14 2023/4/23

115 Bracket,roller,frame,drive drum,tail drum 6 days 2023/4/14 2023/4/19


116 Tail tension device 1 day? 2023/4/20 2023/4/20
117 Drive unit installation & alignment 3 days 2023/4/21 2023/4/23
118 525BC05 Belt conveyor truss & belt conveyor installation 8 days? 2023/4/14 2023/4/21

119 Bracket,roller,frame,tail drum 6 days 2023/4/14 2023/4/19


120 Tail tension device 1 day? 2023/4/20 2023/4/20
121 Belt middle tension device 1 day? 2023/4/21 2023/4/21
122 515BC02 conveyor truss & belt conveyor installation 10 days? 2023/4/24 2023/5/3
123 Bracket,roller,frame,drive drum,tail drum 6 days 2023/4/24 2023/4/29
124 Tail tension device 1 day? 2023/4/30 2023/4/30
125 Drive unit installation & alignment 3 days 2023/5/1 2023/5/3
126 515BC01 conveyor truss modification & belt conveyor 11 days 2023/4/24 2023/5/4
installation
127 Bracket,roller,frame,drive drum 6 days 2023/4/24 2023/4/29
128 Drive unit installation & alignment 3 days 2023/4/30 2023/5/2
129 Belt middle tension device 2 days 2023/5/3 2023/5/4
130 525BC04 & 5252BC05 & 515BC01 & 515BC02 Belt laying 4 days 2023/5/5 2023/5/8
and tension
131 525BC04 & 5252BC05 & 515BC01 & 515BC02 Belt 2 days 2023/5/9 2023/5/10
vulcanization
132 Remaining installation 12 days 2023/4/30 2023/5/11
133 525BC04 & 5252BC05 & 515BC02 Canopy installation 3 days 2023/5/9 2023/5/11

134 515BC01 conveyor truss rain protection roof 2 days 2023/5/9 2023/5/10
re-installation
Task External task Only duration Deadline
Split External milestones Manual abstract assembly Key
QASSIM CEMENT NEW CEMENT MILL Milestone Inactive Milestones Manual abstract Key split
Abstract Inactive abstract Only start time Progress
Project abstract Manual tasks Only finish time

- CDI Started working on 1st Feb, 2022, but CDI received advanced payment on 11th Mar, 2022
- This schedule consider the owner issue L/C according to contract condition.
4 /6
QCC PROJECT TIE-IN TIME SCHEDULE
标识号 Task Duration Time Start Complete 2023
11 12 1 2 3 4 5
23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28
135 No-standard chute & pipe installation 10 days 2023/4/30 2023/5/9
136 Electrical cable installation 10 days 2023/4/30 2023/5/9
137 Part 5_Tie in Line 2 transport cment belt 592BC01 79 days? 2023/2/12 2023/5/1
138 Task 1_592BC01 belt conveyor demolition & New 592BC01 74 days? 2023/2/12 2023/4/26
belt conveyor installation
139 Existing 592BC01 belt conveyor demolition 43 days? 2023/2/12 2023/3/26
140 QCC scope 30 days? 2023/2/12 2023/3/14
141 Housekeeping for belt conveyor 592BC01 & platform 30 days? 2023/2/12 2023/3/14
142 Ensure that the pneumatic conveying pipeline can 30 days? 2023/2/12 2023/3/14
transport the cement to cement silo
143 CDI scope 12 days? 2023/3/15 2023/3/26
144 Site mobilization & preparation 2 days 2023/3/15 2023/3/16
145 Remove rain protection roof and steel bracing 2 days 2023/3/17 2023/3/18
146 Remove belt 1 day? 2023/3/19 2023/3/19
147 Remove bracket,roller,frame,drive unit,tail tension 7 days 2023/3/20 2023/3/26
decice,etc.
148 New 592BC01 belt conveyor installation 31 days? 2023/3/27 2023/4/26
149 Steel structure reforcement(Not sure, based on design 7 days 2023/3/27 2023/4/2
calculation)
150 Bracket,roller,frame,drive drum,tail drum 10 days 2023/4/3 2023/4/12
151 Tail tension device 1 day? 2023/4/13 2023/4/13
152 Belt laying and tension 3 days 2023/4/14 2023/4/16
153 Drive unit installation & algnment 3 days 2023/4/17 2023/4/19
154 Belt vulcanization 1 day? 2023/4/20 2023/4/20
155 Re-install rain protection roof and steel bracing 3 days 2023/4/21 2023/4/23
156 Electrical installation 10 days 2023/4/17 2023/4/26
157 Task 2_592BE2 bucket elevator demolition & installation 55 days? 2023/2/27 2023/4/22

158 592BE2 bucket elevator demolition 29 days? 2023/2/27 2023/3/27


159 QCC scope 15 days 2023/2/27 2023/3/14
160 Housekeeping for 592BE02 bucket elevator 15 days 2023/2/27 2023/3/14
161 Empty the bucket before stoping the elevator 1 day 2023/3/13 2023/3/14
162 CDI scope 13 days? 2023/3/15 2023/3/27
163 Remove side wall rain protection sheet and steel 2 days 2023/3/15 2023/3/16
bracing
164 Remove bucket 3 days 2023/3/17 2023/3/19
165 Remove belt 1 day? 2023/3/20 2023/3/20
166 Remove brace frame,drive unit,drive head hood,casing, 7 days 2023/3/21 2023/3/27
tail unit,etc.
167 592BE2 bucket elevator installation 26 days 2023/3/28 2023/4/22
168 Foundation preparation and tail unit installation & 2 days 2023/3/28 2023/3/29
alignment

Task External task Only duration Deadline


Split External milestones Manual abstract assembly Key
QASSIM CEMENT NEW CEMENT MILL Milestone Inactive Milestones Manual abstract Key split
Abstract Inactive abstract Only start time Progress
Project abstract Manual tasks Only finish time

- CDI Started working on 1st Feb, 2022, but CDI received advanced payment on 11th Mar, 2022
- This schedule consider the owner issue L/C according to contract condition.
5 /6
QCC PROJECT TIE-IN TIME SCHEDULE
标识号 Task Duration Time Start Complete 2023
11 12 1 2 3 4 5
23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28
169 Install casing & brace frame 7 days 2023/3/30 2023/4/5
170 Install drive head hood,drum,paltform 3 days 2023/4/6 2023/4/8
171 Casing verticality alignment & inspection 3 days 2023/4/9 2023/4/11
172 Drive unit installation & algnment 2 days 2023/4/12 2023/4/13
173 Belt preparation & laying & tention 3 days 2023/4/14 2023/4/16
174 Weaving and vulcanization of steel wire rope with belt 2 days 2023/4/17 2023/4/18
joint
175 Bucket installation 4 days 2023/4/19 2023/4/22
176 Task 3_Air slide demolition & installation 12 days 2023/3/9 2023/3/20
177 Air slide demolition 5 days 2023/3/9 2023/3/13
178 Air slide installation 7 days 2023/3/14 2023/3/20
179 Chute,dedusting duct installation 20 days? 2023/4/12 2023/5/1
180 Electrical installation 20 days? 2023/4/12 2023/5/1
181 Part 6_493PN05 Pan conveyor midification 53 days? 2023/4/1 2023/5/23
182 QCC scope 30 days? 2023/4/1 2023/5/1
183 Housekeeping for Pan conveyor & paltform 30 days? 2023/4/1 2023/5/1
184 Count & Replace damaged and missing part of pan conveyor 30 days? 2023/4/1 2023/5/1

185 Do run test to prove pan conveyor in good condition before 30 days? 2023/4/1 2023/5/1
modification
186 CDI scope 22 days? 2023/5/2 2023/5/23
187 Site mobilization & preparation 2 days 2023/5/2 2023/5/3
188 Remove conveyor truss rain protection roof and bracing for 1 day? 2023/5/4 2023/5/4
modification preparation
189 Remove pan bucket & chain & roller 2 days 2023/5/5 2023/5/6
190 Exchange drive unit ,drive drum with tail tention device 3 days 2023/5/7 2023/5/9
191 Do reforcement & modification for drive sprocket bracket 5 days 2023/5/10 2023/5/14
frame and tail tention device bracket frame
192 Install drive unit & alignment 2 days 2023/5/15 2023/5/16
193 Install chain & supporting roller & bucket 5 days 2023/5/17 2023/5/21
194 Re-install rain protection roof and bracing 2 days 2023/5/22 2023/5/23
195 Chute,dedusting duct installation 9 days 2023/5/15 2023/5/23
196 Electrical installation 7 days 2023/5/17 2023/5/23

Task External task Only duration Deadline


Split External milestones Manual abstract assembly Key
QASSIM CEMENT NEW CEMENT MILL Milestone Inactive Milestones Manual abstract Key split
Abstract Inactive abstract Only start time Progress
Project abstract Manual tasks Only finish time

- CDI Started working on 1st Feb, 2022, but CDI received advanced payment on 11th Mar, 2022
- This schedule consider the owner issue L/C according to contract condition.
6 /6