ID Task Name Duration % Start Finish 2022

Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
0 EPC Schedule May.2021 549.63 days 19% 22-11-2020 30-12-2022
1 Engineering (In House) 179 days 99% 22-11-2020 10-06-2021
2 Gas Turbine Package 21 days 100% 22-11-2020 14-12-2020
3 Scope Of Work Prepration 12 days 100% 22-11-2020 03-12-2020
4 Scope of Work Review and Materials 8 days 100% 06-12-2020 14-12-2020
requisition Preparation.
5 Water Injection Pump 17 days 100% 22-11-2020 09-12-2020
6 Scope Of Work Prepration 9 days 100% 22-11-2020 01-12-2020
7 Scope of Work Review and Materials 7 days 100% 02-12-2020 09-12-2020
requisition Preparation.
8 Sipping & Recycle Pumps 49 days 100% 14-12-2020 07-02-2021
9 Scope Of Work Prepration 38 days 100% 14-12-2020 25-01-2021
10 Scope of Work Review and Materials 10 days 100% 26-01-2021 07-02-2021
requisition Preparation.
11 Transformers & Electrical Equipment Supply 57 days 100% 05-01-2021 10-03-2021

12 Scope Of Work Prepration 31 days 100% 05-01-2021 09-02-2021


13 Scope of Work Review and Materials 25 days 100% 10-02-2021 10-03-2021
requisition Preparation.
14 Air Compressors Units 93 days 100% 22-11-2020 04-03-2021
15 Scope Of Work Prepration 82 days 100% 22-11-2020 21-02-2021
16 Scope of Work Review and Materials 11 days 100% 21-02-2021 04-03-2021
requisition Preparation.

Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 1
ID Task Name Duration % Start Finish 2022
Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
17 Fire Water Pump 17 days 100% 22-11-2020 09-12-2020
18 Scope Of Work Prepration 9 days 100% 22-11-2020 01-12-2020
19 Scope of Work Review and Materials 7 days 100% 02-12-2020 09-12-2020
requisition Preparation.
20 Wells Tie-Ins 99 days 100% 10-12-2020 31-03-2021
21 Materials Requistion 99 days 100% 10-12-2020 31-03-2021
22 Line Pipes Materials Requisition. 10 days 100% 10-12-2020 22-12-2020
23 Scope of Work Prepation 10 days 100% 10-12-2020 22-12-2020
24 Fittings Requisition 71 days 100% 11-01-2021 31-03-2021
25 Scope of Work Prepation 71 days 100% 11-01-2021 31-03-2021
26 Electrical Well Head Materials Requisition 56 days 100% 11-01-2021 15-03-2021

27 Scope of Work Prepation 56 days 100% 11-01-2021 15-03-2021


28 Installation Package 43 days 100% 20-12-2020 04-02-2021
29 SOW & ITT Preparation 43 days 100% 20-12-2020 04-02-2021
30 Static Equipment (Tank & Degassing Boot at 54 days 100% 01-12-2020 31-01-2021
Zenad St.)
31 ITT Prepration 54 days 100% 01-12-2020 31-01-2021
32 Mechanical, Electrical, Instrument & Civil 67 days 100% 24-01-2021 08-04-2021
Packages for Zenad Station
33 Site Survey 42 days 100% 24-01-2021 11-03-2021
34 Scope of Work Prepation 53 days 100% 08-02-2021 08-04-2021

Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 2
ID Task Name Duration % Start Finish 2022
Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
35 Farrud Water Injection Surface Facilities 87 days 91% 03-03-2021 10-06-2021

36 Site Survey 7 days 100% 03-03-2021 11-03-2021


37 Indentfy the missing and required materials. 5 days 100% 14-03-2021 18-03-2021

38 Preparing EPC ITT and issuing for review. 72 days 90% 21-03-2021 10-06-2021

39 Tendering 247 days 45% 10-12-2020 15-09-2021


40 Gas Turbine Package 201 days 50% 15-12-2020 29-07-2021
41 Issue Materials Requisition to TC 15 days 100% 15-12-2020 31-12-2020
42 Tendering Stage. 165 days 45% 25-01-2021 29-07-2021
43 Water Injection Pump 165 days 56% 10-12-2020 15-06-2021
44 Issue Materials Requisition to TC 4 days 100% 10-12-2020 15-12-2020
45 Tendering Stage. 152 days 55% 24-12-2020 15-06-2021
46 Sipping & Recycle Pumps 132 days 55% 10-02-2021 11-07-2021
47 Issue Materials Requisition to TC 34 days 100% 10-02-2021 21-03-2021
48 Tendering Stage. 98 days 40% 21-03-2021 11-07-2021
49 Transformers & Electrical Equipment Supply 144 days 33% 11-03-2021 22-08-2021

50 Issue Materials Requisition to TC 24 days 100% 11-03-2021 07-04-2021


51 Tendering Stage. 119 days 20% 08-04-2021 22-08-2021
52 Air Compressors Units 131 days 37% 08-03-2021 02-08-2021
53 Issue Materials Requisition to TC 28 days 100% 08-03-2021 07-04-2021
Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 3
ID Task Name Duration % Start Finish 2022
Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
54 Tendering Stage. 102 days 20% 08-04-2021 02-08-2021
55 Fire Water Pump 126 days 100% 10-12-2020 03-05-2021
56 Issue Materials Requisition to TC 4 days 100% 10-12-2020 15-12-2020
57 Tendering Stage. 118 days 100% 20-12-2020 03-05-2021
58 Wells Tie-Ins 219 days 43% 10-12-2020 15-08-2021
59 Materials Requastion 212 days 43% 10-12-2020 08-08-2021
60 Line Pipes Materials Requisition. 165 days 63% 10-12-2020 15-06-2021
61 Review and issueing to TC 10 days 100% 10-12-2020 22-12-2020
62 Tendering Stage 134 days 60% 14-01-2021 15-06-2021
63 Fittings Requisition 112 days 28% 01-04-2021 08-08-2021
64 Review and issueing to TC 4 days 100% 01-04-2021 06-04-2021
65 Tendering Stage 106 days 25% 08-04-2021 08-08-2021
66 Electrical Well Head Materials Requisition 128 days 34% 15-03-2021 08-08-2021

67 Review and issueing to TC 15 days 100% 15-03-2021 31-03-2021


68 Tendering Stage 109 days 25% 05-04-2021 08-08-2021
69 Installation Package 169 days 42% 04-02-2021 15-08-2021
70 Review and issueing to TC 39 days 100% 04-02-2021 21-03-2021
71 Tendering Stage 129 days 25% 22-03-2021 15-08-2021
72 "Static Equipment (Tank & Degassing Boot at 147 days 38% 31-01-2021 15-07-2021
Zenad St.)
73 Review and issueing to TC 25 days 100% 31-01-2021 28-02-2021

Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 4
ID Task Name Duration % Start Finish 2022
Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
74 Tendering Stage 122 days 25% 28-02-2021 15-07-2021
75 Mechanical, Electrical, Instrument & Civil 137 days 35% 08-04-2021 09-09-2021
Packages for Zenad Station
76 Review Scope of work and prepare ITT 14 days 100% 08-04-2021 25-04-2021
Package
77 Issue ITT to TC 34 days 95% 27-04-2021 06-06-2021
78 Tendering stage and Award 85 days 0% 07-06-2021 09-09-2021
79 Farrud Water Injection Surface Facilities 86 days 0% 10-06-2021 15-09-2021

80 Issuing to TC 8 days 0% 10-06-2021 20-06-2021


81 Tendering stage and Award 75 days 0% 23-06-2021 15-09-2021
82 Procurement 405 days 0% 03-05-2021 31-07-2022
83 Gas Turbine Package 317 days 0% 05-08-2021 26-07-2022
84 Award / PO Issued 18 days 0% 05-08-2021 25-08-2021
85 Delivery Time 296 days 0% 30-08-2021 26-07-2022
86 Water Injection Pump 363 days 0% 17-06-2021 31-07-2022
87 Award / PO Issued 25 days 0% 17-06-2021 15-07-2021
88 Delivery Time 323 days 0% 02-08-2021 31-07-2022
89 Sipping & Recycle Pumps 328 days 0% 18-07-2021 20-07-2022
90 Award / PO Issued 25 days 0% 18-07-2021 15-08-2021
91 Delivery Time 301 days 0% 17-08-2021 20-07-2022
92 Transformers & Electrical Equipment Supply 302 days 0% 25-08-2021 31-07-2022

Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 5
ID Task Name Duration % Start Finish 2022
Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
93 Award / PO Issued 30 days 0% 25-08-2021 28-09-2021
94 Delivery Time 268 days 0% 03-10-2021 31-07-2022
95 Air Compressors Units 278 days 0% 08-09-2021 17-07-2022
96 Award / PO Issued 24 days 0% 08-09-2021 05-10-2021
97 Delivery Time 250 days 0% 10-10-2021 17-07-2022
98 Fire Water Pump 319 days 4% 03-05-2021 25-04-2022
99 Award / PO Issued 44 days 30% 03-05-2021 21-06-2021
100 Delivery Time 270 days 0% 27-06-2021 25-04-2022
101 Wells Tie-Ins 294 days 0% 30-06-2021 25-05-2022
102 Materials Requistion 294 days 0% 30-06-2021 25-05-2022
103 Line Pipes Materials Requisition. 290 days 0% 30-06-2021 22-05-2022
104 Award / PO Issued 13 days 0% 30-06-2021 15-07-2021
105 Delivery Time 264 days 0% 29-07-2021 22-05-2022
106 Fittings Requisition 229 days 0% 09-08-2021 21-04-2022
107 Award / PO Issued 37 days 0% 09-08-2021 20-09-2021
108 Delivery Time 189 days 0% 22-09-2021 21-04-2022
109 Electrical Well Head Materials Requisition 258 days 0% 10-08-2021 25-05-2022

110 Award / PO Issued 29 days 0% 10-08-2021 12-09-2021


111 Delivery Time 227 days 0% 14-09-2021 25-05-2022
112 Static Equipment (Tank & Degassing Boot at 275 days 0% 15-07-2021 19-05-2022
Zenad St.)

Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 6
ID Task Name Duration % Start Finish 2022
Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
113 Award / PO Issued 25 days 0% 15-07-2021 12-08-2021
114 Delivery Time 250 days 0% 12-08-2021 19-05-2022
115 Construction & Commissioning 625 days 0% 17-08-2021 30-12-2022
116 Gas Turbine Package 185 days 0% 30-05-2022 25-10-2022
117 Installation Activity 185 days 0% 30-05-2022 25-10-2022
118 Wells Tie-Ins 421 days 0% 17-08-2021 20-07-2022
119 Installation Package 421 days 0% 17-08-2021 20-07-2022
120 Award / Contract Sign 43 days 0% 17-08-2021 20-09-2021
121 Installation Activities 371 days 0% 26-09-2021 20-07-2022
122 Static Equipment (Tank & Degassing Boot at 512 days 0% 07-10-2021 20-11-2022
Zenad St.)
123 Contract Signature 26 days 0% 07-10-2021 27-10-2021
124 Installation Activities 486 days 0% 27-10-2021 20-11-2022
125 Mechanical, Electrical, Instrument & Civil 589.5 days 0% 14-09-2021 30-12-2022
Packages for Zenad Station
126 Contract Signature 38 days 0% 14-09-2021 15-10-2021
127 Engineering by Contractor 92 days 0% 17-10-2021 26-01-2022
128 Procurement by Contractor 223 days 0% 30-01-2022 06-10-2022
129 Installation & Commissioning by Contractor 303 days 0% 01-05-2022 30-12-2022

130 Farrud Water Injection Surface Facilities 586 days 0% 17-09-2021 30-12-2022

131 Contract Signature 39 days 0% 17-09-2021 18-10-2021


Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 7
ID Task Name Duration % Start Finish 2022
Complete Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
132 Engineering by Contractor 80 days 0% 19-10-2021 17-01-2022
133 Procurement by Contractor 220 days 0% 17-01-2022 20-09-2022
134 Project Implementation by Contractor 308 days 0% 28-04-2022 30-12-2022

Task Manual Task Deadline

Split Duration-only Critical

Milestone Manual Summary Rollup Critical Split

Project: EPC Schedule May.2021 Summary Manual Summary Baseline


Date: 30-05-2021 Project Summary Start-only Baseline Milestone

Inactive Task Finish-only Baseline Summary

Inactive Milestone External Tasks Progress

Inactive Summary External Milestone Manual Progress

Page 8

You might also like