You are on page 1of 3

CHAPTER-1: Basic of construction planning and management

 Key Players in Construction


 The Client: Who is the initiator and owner of the project (public or private)
 The Consultant: transfers the wish of the owner into realizable form and
makes the study, design and possibly the supervision.
 The Contractor: is the one who performs the work.
 Insurance Companies: they Provides bonds such as Bid bond, Performance
bond, Payment bonds…
 Banks: provide the working capital for contractors
 Suppliers: Provide equipment, materials or machineries.
 Permitting agency: Check the construction project with respect to the law.

 Introduction to PMBOK (Project Management Body of Knowledge)  Section III: The Project Management Knowledge Areas (9)
 The Project Management Body of Knowledge is the sum of knowledge 1. Project Integration Management
within the profession of project management.  Describes the processes and activities that integrate the various elements of
 The complete PMBOK includes proven traditional practices as well as project management
innovative practices that are emerging in the profession. 2. Project Scope Management
 The PMBOK has three distinct sections.  Describes the processes involved in ascertaining that the project includes all
 Section I: The Project Management Framework the work required, and only the work required, to complete the project
 It provides a basic structure for understanding project management successfully
by defining key terms and describing the project life cycle and 3. Project Time Management
organization.  Describes the processes concerning the timely completion of the project.
 Section II: The Standard for Project management  It consists of the Activity Resource and Duration Estimating, Schedule
 It specifies all the project management processes that are used by the Development, and Schedule Control project management processes
project team to manage a project and; 4. Project Cost Management
 It describes the five required Project Management Process Groups for  Describes the processes involved in planning, estimating, budgeting, and
any project which are: controlling costs so that the project is completed within the approved
o Initiating, Planning, Executing, Monitoring + controlling and budget
Closing processes group. 5. Project Quality Management
 Describes processes involved in assuring the project will satisfy the
objectives it was undertaken.

6. Project Human Resource Management


 Describes the processes that organize and manage the project team
7. Project Communications Management e. Negotiation and conflict management: Consulting with others and
 Describes the processes concerning the timely and appropriate generation, reaching 0n mutual agreement.
collection, dissemination, storage and ultimate disposition of project f. Problem solving: The combination of problem definition, alternatives
information identification and analysis, and decision making
8. Project Risk Management  Construction Project Phases
 Describes the processes concerned with conducting risk management on a 1. Pre-Project Phase
project.  At this stage the owner will decide:
9. Project Procurement Management  What sort of project delivery system will be used?
 Describes the processes that purchase or acquire products, services or  How will the various parties be related?
results, as well as contract management processes  Will the owner engage a design professional to prepare plans and
 Effective Project Management (EPM) specifications and then contract separately with a construction
 EPM requires that the project management team understand and use contractor? Or, will a single entity be responsible for the entire
knowledge and skills from at least five areas of expertise. project?
1. The Project Management Body of Knowledge  The type of contract to be used with the contractor.
 Describes knowledge unique to the project management field and 2. Planning and Design Phase
that overlaps other management disciplines  At this stage:
2. Application area knowledge, Standards, and Regulations  Feasibility study of the project will be conducted.
 Application areas: categories having common elements significant in  Complete design for the construction will be made.
projects, but are not needed or present in all projects.  Contract documents necessary for the project will be prepared.
 A standard: is a “document established by consensus and approved 3. Project Mobilization Phase
by a recognized body.  At this stage:
 A regulation: is a government-imposed requirement, which specifies  Bonds, licenses and insurances must be secured and a detailed
product, process or service characteristics program/schedule must be prepared.
3. Understanding the project Environment  The worksite must be organized, with provisions for access and
 The project team should consider the project in its cultural, social, delivery, storage areas and site security.
international, political, and physical environmental contexts  The process of obtaining materials and equipment to be incorporated
4. General management knowledge and skills into the project must be initiated and arrangements for labor, the
 General management encompasses planning, organizing, staffing, other essential resource, must be organized.
executing, and controlling the operations of an ongoing enterprise. 4. Project Operation Phase
5. Interpersonal Skills  At this stage:
a. Effective communication: The exchange of information  Monitoring and control, Resource management and Documentation
b. Influencing the organization: Ability to “get things done” and communication will take place.
c. Leadership: Developing a vision and strategy, and motivating people  Assigning and supervising personnel and assuring that the labor effort
to achieve that vision and strategy is sufficiently productive to meet schedule, cost and quality goals.
d. Motivation: Energizing people to achieve high levels of performance  In addition, materials and plant must be managed so that these same
and to overcome barriers to change. goals are met.
5. Project Closeout and Termination Phase
 At this stage:
 Testing and startup tasks,
 Various inspections and remedial work,
 Closing the construction office and terminating temporary staff’s
employment.
 Approvals and certifications that allow the contractor to receive final
payment, a set of as built drawings that include all changes made to
the original design, operating manuals, warranties and a final report.
 Transferring and archiving project records and conducting some sort
of project critique and evaluation.
 Operator training may also be part of the contractor’s contractual
responsibilities if needed.

You might also like