PFC Customer :HAROUGE OIL OPERATIONS

1 off GSG B2B 100-300/14


Project: WIP for Ghani
Cstomer PO -No.:Frame Agreement No. P1-2021
Sulzer No.: 100442772 -10

ID Task Name Duration Start Finish Half 1, 2022 Half 2, 2022


O N D J F M A M J J A S O N
1 Start of order 1 dy Fri 03.12.21 Fri 03.12.21 03.12
2 Internal prod. Paper / OED Rev.0 3 dys Mon 06.12.21 Wed 08.12.21 100%
3 Design pump 10 dys Thu 09.12.21 Wed 22.12.21 100%
4 Design packaging / GA/PPI/PIL back/approved 80 dys Thu 09.12.21 Tue 19.04.22 59%
5 Part list pump- 3 dys Mon 10.01.22 Wed 12.01.22 100%
6 Part list packaging 30 dys Wed 20.04.22 Wed 01.06.22 0%
7
8 Procurement pump parts 139 dys Fri 03.12.21 Fri 08.07.22
9 Pressure retaining parts / ordered 120 dys Thu 13.01.22 Wed 06.07.22 28%
10 Rotor parts / ordered 105 dys Thu 13.01.22 Tue 14.06.22 32%
11 Mech. Seal EagleBurgmann Germany / ordered 139 dys Fri 03.12.21 Fri 08.07.22 37%
12 Procurement ACC 162 dys Fri 03.12.21 Wed 10.08.22
13 Motor + Softstarter Nidec ASI S.p.A. / ordered 162 dys Fri 03.12.21 Wed 10.08.22 31%
14 Baseplate 80 dys Thu 14.04.22 Wed 10.08.22 0%
15 Coupling 75 dys Mon 25.04.22 Wed 10.08.22 0%
16 Seal System EagleBurgmann Germany / ordered 162 dys Fri 03.12.21 Wed 10.08.22 31%
17 Unit Control Panel (Eldatex) / / ordered 143 dys Mon 17.01.22 Wed 10.08.22 22%
18
19 Machining 15 dys Wed 15.06.22 Wed 06.07.22
20 Rotor parts @ SPDE Bruchsal 15 dys Wed 15.06.22 Wed 06.07.22 0%
21
22 Bareshaft pumps 25 dys Thu 07.07.22 Wed 10.08.22
23 Preparation for Hydrotest / balancing 5 dys Thu 07.07.22 Wed 13.07.22 0%
24 Hydrotest witness 2 dys Thu 14.07.22 Fri 15.07.22 0%
25 Rotor balancing 2 dys Thu 14.07.22 Fri 15.07.22
26 Assembly Pump for Testbed 6 dys Mon 18.07.22 Mon 25.07.22 0%
27 Assembly on Testbed 5 dys Tue 26.07.22 Mon 01.08.22 0%
28 Performance Test / witness 5 dys Tue 02.08.22 Mon 08.08.22 0%
29 Disassembly, Cleaning, Assembly 2 dys Tue 09.08.22 Wed 10.08.22 0%
30 Packaging 13 dys Thu 11.08.22 Mon 29.08.22
31 Assembly 2 dys Thu 11.08.22 Fri 12.08.22 0%
32 Pipework / painting / install wiring 10 dys Mon 15.08.22 Fri 26.08.22 0%
33 Final inspection / witness 1 dy Mon 29.08.22 Mon 29.08.22 29.08
34
35 Packing & Dispach 43 dys Tue 30.08.22 Fri 28.10.22
36 Packing sea worthy / preparation shipping doc 12 dys Tue 30.08.22 Wed 14.09.22 0%
37 FCA packing company ( 41 weeks after 03-12-2021) 1 dy Thu 15.09.22 Thu 15.09.22 15.09
38 Shipment to Ras Lanuf / Libya 30 dys Fri 16.09.22 Fri 28.10.22 0%

Task Project Summary Inactive Task Duration-only Finish-only


Start date : 03-12-2021
Delivery date FCA : 15-09-2022 / CIF Ras Lanuf Split External Tasks Inactive Milestone Manual Summary Rollup Progress
Milestone External Milestone Inactive Summary Manual Summary Deadline
Summary Inactive Task Manual Task Start-only

Project Manager: Kasim Patel 1/1 Date:01-03-2022


Coordinator Order Processing : Hans Gaibler Rev.02