UNO COMPLETIONS & DEFECTING

PROGRAMME
ID Task Name Duration Start Finish Predecessors Resource Names Aug '22 Sep '22 Oct '22 Nov '22
18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31
1 Completion and Commissioning Programme 112 days Sat 15/01/22 Wed 22/06/22
34 Builders works completion SP1 17 days Wed 14/09/22 Sat 8/10/22
35 Speedpanel to SP1 areas Complete 0 days Wed 14/09/22 Wed 14/09/22 36 14/09
36 Stair Doors Complete 0 days Wed 14/09/22 Wed 14/09/22 14/09
37 Apartment Entry Doors Complete 0 days Fri 30/09/22 Fri 30/09/22 30/09
38 Floor Finishes to Corridor 0 days Sat 8/10/22 Sat 8/10/22 8/10
39 FFFT Test Run 21 days Wed 14/09/22 Wed 12/10/22
40 Stair Press Commissioning 5 days Thu 15/09/22 Tue 20/09/22
41 Carpark Exhaust Commissioning 5 days Wed 21/09/22 Thu 29/09/22 40
42 Lobby Supply Commissioning 5 days Fri 30/09/22 Thu 6/10/22 41,37
43 Misc Essential Service Re-testing Commissioning 5 days Fri 7/10/22 Wed 12/10/22 42
44 Wet Fire Commissioning 5 days Wed 14/09/22 Mon 19/09/22
45 Dry Fire Commissioning 15 days Fri 16/09/22 Sat 8/10/22 86SS,321FF,38FF
46 Lift 1, 2, 5 & 6 0 days Tue 20/09/22 Tue 20/09/22 20/09
47 FFFT 0 days Thu 13/10/22 Thu 13/10/22 40FS+1 day,42FS+1 day,44FS+1 day,45FS+1 day,43FS+1 day,41FS+1 day 13/10
48 OP Application 1 day Fri 14/10/22 Fri 14/10/22 47
49 Reg 187 Application 1 day Sat 15/10/22 Sat 15/10/22 48
50 MFB Walk 0 days Wed 26/10/22 Wed 26/10/22 47FS+10 days 26/10
51 Certification of OP 0 days Wed 26/10/22 Wed 26/10/22 50 26/10
52 SP1 Handover 0 days Fri 28/10/22 Fri 28/10/22 51 28/10
53 Ground Common Area 51 days Wed 24/08/22 Fri 28/10/22
54 Hang Walls 3 days Wed 24/08/22 Fri 26/08/22 Express Express
55 Stop & Sand Walls 3 days Sat 27/08/22 Tue 30/08/22 54 Express Express
56 Hang Ceilings 3 days Wed 31/08/22 Fri 2/09/22 55 Express Express
57 Stop & Sand Ceilings 3 days Sat 3/09/22 Tue 6/09/22 56 Express Express
58 Partition Frames 2 days Tue 13/09/22 Wed 14/09/22 Insight Insight
59 Skirting & Cornices 2 days Tue 13/09/22 Wed 14/09/22 Insight Insight
60 First Paint 3 days Thu 15/09/22 Sat 17/09/22 57,55,58,59 DEC DEC
61 Tile & Grout 10 days Mon 19/09/22 Tue 4/10/22 60 Wetspot Wetspot
62 Doors, Skirting & Cornices 4 days Wed 5/10/22 Sat 8/10/22 61 Purple Hills & Express Purple Hills & Express
63 Joinery & Feature Steel 4 days Wed 5/10/22 Sat 8/10/22 61 IJF IJF
64 Services Fitoff 4 days Thu 6/10/22 Mon 10/10/22 63FS-3 days Services S/C Services S/C
65 Install Entry Door 3 days Thu 6/10/22 Sat 8/10/22 63FS-3 days Facadex Facadex
66 ENERGISATION 4 days Tue 11/10/22 Fri 14/10/22 64,65 Apps Apps
67 Partition Glazing 1 day Tue 18/10/22 Tue 18/10/22 58FS+6 days,59FS+6
Insight
days,62FS+6 days Insight
68 Services Commissioning 4 days Sat 15/10/22 Thu 20/10/22 66 Services S/C Services S/C
69 Final Patch & Paint to Walls 4 days Sat 15/10/22 Thu 20/10/22 66 Express / DEC Express / DEC
70 RCo Inspections & Rectification 3 days Fri 21/10/22 Mon 24/10/22 69 Roberts Co Roberts Co
71 First Clean / Caulking 2 days Fri 21/10/22 Sat 22/10/22 69 Construction Cleaning Construction Cleaning
72 FF&E Install 2 days Tue 25/10/22 Wed 26/10/22 70 Roberts Co Roberts Co
73 Final Clean 2 days Tue 25/10/22 Wed 26/10/22 70 CCG CCG
74 Architect Defects Inspection & Rectification 1 day Tue 25/10/22 Tue 25/10/22 70 Elenberg Fraser Elenberg Fraser
75 Client Defects Inspection & Rectification 3 days Wed 26/10/22 Fri 28/10/22 74 Setia Setia
76 Ground Gas Meter Room 69 days Wed 20/07/22 Tue 18/10/22
77 Blockwork to Gas Meter Room 3 days Wed 20/07/22 Fri 22/07/22 Brickon Brickon
78 Low Level Gas & Mechanical 4 days Tue 2/08/22 Fri 5/08/22 77 Ellis Air Ellis Air
79 Manifold Install 1 day Sat 6/08/22 Sat 6/08/22 78 Comdain Comdain
80 Electrical Fitoff 1 day Tue 9/08/22 Tue 9/08/22 79 Apps Apps
81 Door Frame, Door and Hardware Fitoff 1 day Wed 10/08/22 Wed 10/08/22 80 Purple Hills / DEC Purple Hills / DEC
82 Connection to manifold & regulators 2 days Tue 13/09/22 Wed 14/09/22 Ellis Air Ellis Air
83 Gas Meter Install (+10 days from application) 1 day Fri 30/09/22 Fri 30/09/22 82FS+10 days Comdain Comdain
84 Ground BOH Works 34 days Fri 2/09/22 Tue 18/10/22
85 Blockwork to MSSB cupboard and loading dock 3 days Fri 2/09/22 Mon 5/09/22 Brickon Brickon
86 FIP Energisation 1 day Mon 5/09/22 Mon 5/09/22 Apps / Leemark Apps / Leemark
87 MSSB Fitoff 5 days Tue 6/09/22 Sat 10/09/22 85 LJs / Ellis LJs / Ellis
88 Mech Board Energisation 2 days Tue 13/09/22 Wed 14/09/22 87 Apps Apps
89 ENERGISATION 3 days Tue 11/10/22 Thu 13/10/22 64 Apps Apps
90 Roller Shutter Steel 2 days Wed 7/09/22 Thu 8/09/22 CSS CSS
91 Fire Walls to Roller Shutter 4 days Fri 9/09/22 Wed 14/09/22 90 Express Express
92 Fire Shutter Install 1 day Thu 15/09/22 Thu 15/09/22 91 Mirage Mirage
93 Temporary Plaster Firewall and Door near Switchroom 4 days Thu 15/09/22 Mon 19/09/22 91 Express/Purple Hills Express/Purple Hills
94 Tilt Door to Loading Dock 2 days Sat 15/10/22 Tue 18/10/22 Mirage Mirage
95 Level 1 Common Area 47 days Tue 23/08/22 Sat 22/10/22
96 Hang Ceilings 4 days Tue 23/08/22 Fri 26/08/22 Express Express
97 Stop & Sand Ceiling 6 days Sat 27/08/22 Fri 2/09/22 96 Express Express
98 First Paint 2 days Sat 3/09/22 Mon 5/09/22 97 DEC DEC
99 Partition Glazing & Doors 2 days Tue 13/09/22 Wed 14/09/22 Insight Insight
100 Flooring, Tile & Grout 6 days Thu 15/09/22 Wed 21/09/22 99 Wetspot / Aywon Wetspot / Aywon
101 Joinery & Feature Steel 4 days Thu 22/09/22 Thu 29/09/22 100 IJF IJF
102 Services Fitoff / Skirting / Doors 8 days Fri 30/09/22 Mon 10/10/22 101 Services S/C Services S/C
103 Partition Glazing 1 day Fri 30/09/22 Fri 30/09/22 99FS+10 days Insight Insight
104 Energise Permanent Power 4 days Tue 11/10/22 Fri 14/10/22 102 Apps Apps
105 Services Commissioning 3 days Sat 15/10/22 Wed 19/10/22 104 Services S/C Services S/C
106 Final Patch & Paint to Walls, 3 days Tue 11/10/22 Thu 13/10/22 102 Express / DEC Express / DEC
107 First Clean / Caulking 1 day Fri 14/10/22 Fri 14/10/22 106 Construction Cleaning Construction Cleaning
108 RCo Inspections & Rectification 2 days Sat 15/10/22 Tue 18/10/22 107 Roberts Co Roberts Co
109 FF&E Install 2 days Tue 18/10/22 Wed 19/10/22 108FS-1 day Roberts Co Roberts Co
110 Final Clean 2 days Tue 18/10/22 Wed 19/10/22 108FS-1 day CCG CCG
111 Architect Defects Inspection & Rectification 1 day Wed 19/10/22 Wed 19/10/22 108 Elenberg Fraser Elenberg Fraser
112 Client Defects Inspection & Rectification 3 days Thu 20/10/22 Sat 22/10/22 111 Setia Setia

Page 1
UNO COMPLETIONS & DEFECTING
PROGRAMME
ID Task Name Duration Start Finish Predecessors Resource Names Aug '22 Sep '22 Oct '22 Nov '22
18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31
113 LEVEL 03 53.5 days Thu 26/05/22 Wed 3/08/22
123 LEVEL 04 54 days Thu 26/05/22 Wed 3/08/22
131 LEVEL 05 50.5 days Tue 31/05/22 Thu 4/08/22
139 LEVEL 06 51 days Tue 31/05/22 Thu 4/08/22
147 LEVEL 07 47.5 days Sat 4/06/22 Fri 5/08/22
155 LEVEL 08 29 days Fri 2/09/22 Tue 11/10/22
156 Energise Mech Boards 1 day Fri 2/09/22 Fri 2/09/22 Apps / LJ Apps / LJ
157 Fitoff and Energise Permanent Power 4 days Sat 3/09/22 Wed 7/09/22 140,156 Apps Apps
158 Commissioning Carpark Exhaust 5 days Wed 21/09/22 Thu 29/09/22 157,41SS Ellis Air Ellis Air
159 Scaffold Install 3 days Fri 30/09/22 Tue 4/10/22 158 RCo/Gravity RCo/Gravity
160 Louver Install Carpark Exhaust 4 days Wed 5/10/22 Sat 8/10/22 159 Colab Colab
161 Final Balance Carpark Exhaust 2 days Mon 10/10/22 Tue 11/10/22 160 Ellis Air Ellis Air
162 LEVEL 09 104 days Fri 10/06/22 Tue 25/10/22
163 Temp Plant Area 103 days Fri 10/06/22 Mon 24/10/22
164 Temp Mech Install Level 9 Landscape Area 40 days Fri 10/06/22 Tue 2/08/22 Ellis Air Ellis Air
165 Energise Permanent Power 4 days Wed 7/09/22 Sat 10/09/22 164,187 Apps Apps
166 Commissioning Temp Plant Level 9 8 days Tue 27/09/22 Thu 6/10/22 165,83FS-4 days Ellis Air Ellis Air
167 LG Commissioning L3-17 8 days Fri 7/10/22 Sat 15/10/22 166
168 LG Commissioning L18-27 6 days Tue 18/10/22 Mon 24/10/22 167
169 Level 9 Common Area 47 days Thu 25/08/22 Tue 25/10/22
170 First Paint 2 days Thu 25/08/22 Fri 26/08/22 DEC DEC
171 Partition Doorss 3 days Sat 27/08/22 Tue 30/08/22 170 Insight Insight
172 Tile & Grout 6 days Wed 31/08/22 Tue 6/09/22 171 Wetspot Wetspot
173 Joinery 3 days Wed 7/09/22 Fri 9/09/22 172 IJF IJF
174 Services Fitoff 6 days Fri 30/09/22 Fri 7/10/22 173,101 Services S/C Services S/C
175 ENERGISATION 4 days Sat 8/10/22 Wed 12/10/22 174 Apps Apps
176 Services Commissioning (Noting Pool will not be filled) 6 days Thu 13/10/22 Thu 20/10/22 175 Services S/C Services S/C
177 Fill Pool 0 days Sat 22/10/22 Sat 22/10/22 Fill Pool 22/10
178 Final Patch & Paint to Walls, Skirting & Doors 3 days Thu 13/10/22 Sat 15/10/22 175 Express / DEC Express / DEC
179 First Clean / Caulking 2 days Tue 18/10/22 Wed 19/10/22 178 Construction Cleaning Construction Cleaning
180 RCo Inspections & Rectification 3 days Thu 20/10/22 Sat 22/10/22 179 Roberts Co Roberts Co
181 FF&E Install 2 days Mon 24/10/22 Tue 25/10/22 180,191 Roberts Co Roberts Co
182 Final Clean 2 days Mon 24/10/22 Tue 25/10/22 180 CCG CCG
183 Architect Defects Inspection & Rectification 1 day Mon 24/10/22 Mon 24/10/22 180,191 Elenberg Fraser Elenberg Fraser
184 Client Defects Inspection & Rectification 1 day Tue 25/10/22 Tue 25/10/22 183 Setia Setia
185 LEVEL 09M 35 days Thu 1/09/22 Tue 18/10/22
186 ENERGISATION 4 days Thu 1/09/22 Mon 5/09/22 Apps Apps
187 Energise Mech Boards 1 day Tue 6/09/22 Tue 6/09/22 186 Apps / LJ Apps / LJ
188 Stair Press Commissioning 5 days Thu 15/09/22 Tue 20/09/22 187,156,40FF,36 Ellis/CDC Ellis/CDC
189 HWP Commissioning 5 days Sat 1/10/22 Fri 7/10/22 188,83 Construction Cleaning Construction Cleaning
190 1st Clean/Caulking 4 days Sat 8/10/22 Wed 12/10/22 189 Express / DEC Express / DEC
191 RCo Inspections & Rectification 4 days Thu 13/10/22 Tue 18/10/22 190 Roberts Co Roberts Co
192 LEVEL 10 418.9 days Fri 19/03/21 Mon 10/10/22
200 LEVEL 11 419.4 days Fri 19/03/21 Tue 11/10/22
208 LEVEL 12 19.2 days Fri 19/03/21 Sat 10/04/21
209 Apartments 21 days Tue 9/08/22 Fri 2/09/22
210 ENERGISATION 3 days Tue 9/08/22 Thu 11/08/22 Apps Apps
211 Patch & Sand 3 days Fri 12/08/22 Mon 15/08/22 210 Express Express
212 Paint 3 days Tue 16/08/22 Thu 18/08/22 211 DEC group DEC group
213 Carpet 3 days Fri 19/08/22 Tue 23/08/22 212 Aywon Aywon
214 First Clean 2 days Wed 24/08/22 Thu 25/08/22 213 CCG CCG
215 Caulk 2 days Thu 25/08/22 Fri 26/08/22 214FS-1 day All trades All trades
216 Rco Inspection 4 days Thu 25/08/22 Mon 29/08/22 215SS RCo RCo
217 2nd Clean 1 day Tue 30/08/22 Tue 30/08/22 216 CCG CCG
218 Client Inspection 3 days Wed 31/08/22 Fri 2/09/22 217 Setia Setia
219 Corridor 408.9 days Fri 19/03/21 Tue 27/09/22
220 ENERGISATION 1 day Sat 10/09/22 Sat 10/09/22 Apps Apps
221 Patch & Sand 2 days Tue 13/09/22 Wed 14/09/22 220 Express Express
222 Carpet 1 day Fri 19/03/21 Sat 20/03/21 Aywon
223 Rco Inspection 3 days Thu 15/09/22 Sat 17/09/22 222,221 RCo RCo
224 1st Clean 1 day Mon 19/09/22 Mon 19/09/22 223 CCG CCG
225 Client Inspection 2 days Tue 20/09/22 Wed 21/09/22 224 All trades All trades
226 Signage 1 day Thu 22/09/22 Thu 22/09/22 225 Signage Signage
227 2nd Clean 1 day Tue 27/09/22 Tue 27/09/22 226 CCG CCG
228 LEVEL 13 19.2 days Fri 19/03/21 Sat 10/04/21
229 Apartments 21 days Fri 12/08/22 Tue 6/09/22
230 ENERGISATION 3 days Fri 12/08/22 Mon 15/08/22 210 Apps Apps
231 Patch & Sand 3 days Tue 16/08/22 Thu 18/08/22 230 Express Express
232 Paint 3 days Fri 19/08/22 Tue 23/08/22 231 DEC group DEC group
233 Carpet 3 days Wed 24/08/22 Fri 26/08/22 232 Aywon Aywon
234 First Clean 2 days Sat 27/08/22 Mon 29/08/22 233 CCG CCG
235 Caulk 2 days Mon 29/08/22 Tue 30/08/22 234FS-1 day All trades All trades
236 Rco Inspection 4 days Mon 29/08/22 Thu 1/09/22 235SS RCo RCo
237 2nd Clean 1 day Fri 2/09/22 Fri 2/09/22 236 CCG CCG
238 Client Inspection 3 days Sat 3/09/22 Tue 6/09/22 237 Setia Setia
239 Corridor 15 days Thu 8/09/22 Thu 29/09/22
240 ENERGISATION 1 day Thu 8/09/22 Thu 8/09/22 Apps Apps
241 Patch, Sand & Paint 2 days Fri 9/09/22 Sat 10/09/22 240 Express Express
242 Carpet 1 day Fri 16/09/22 Fri 16/09/22 Aywon Aywon
243 Rco Inspection 3 days Sat 17/09/22 Tue 20/09/22 242 RCo RCo

Page 2
UNO COMPLETIONS & DEFECTING
PROGRAMME
ID Task Name Duration Start Finish Predecessors Resource Names Aug '22 Sep '22 Oct '22 Nov '22
18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31
244 1st Clean 1 day Wed 21/09/22 Wed 21/09/22 243 CCG CCG
245 Client Inspection 2 days Thu 22/09/22 Tue 27/09/22 244 All trades All trades
246 Signage 1 day Wed 28/09/22 Wed 28/09/22 245 Signage Signage
247 2nd Clean 1 day Thu 29/09/22 Thu 29/09/22 246 CCG CCG
248 LEVEL 14 19.2 days Fri 19/03/21 Sat 10/04/21
249 Apartments 27 days Tue 16/08/22 Sat 17/09/22
250 ENERGISATION 3 days Tue 16/08/22 Thu 18/08/22 230 Apps Apps
251 Patch & Sand 3 days Fri 19/08/22 Tue 23/08/22 250 Express Express
252 Paint 3 days Wed 24/08/22 Fri 26/08/22 251 DEC group DEC group
253 Carpet 2 days Mon 5/09/22 Tue 6/09/22 Aywon Aywon
254 First Clean 2 days Wed 7/09/22 Thu 8/09/22 253 CCG CCG
255 Caulk 2 days Thu 8/09/22 Fri 9/09/22 254FS-1 day All trades All trades
256 Rco Inspection 4 days Thu 8/09/22 Tue 13/09/22 255SS RCo RCo
257 2nd Clean 1 day Wed 14/09/22 Wed 14/09/22 256 CCG CCG
258 Client Inspection 3 days Thu 15/09/22 Sat 17/09/22 257 Setia Setia
259 Corridor 14 days Sat 10/09/22 Fri 30/09/22
260 ENERGISATION 1 day Sat 10/09/22 Sat 10/09/22 240 Apps Apps
261 Patch, Sand & Paint 2 days Tue 13/09/22 Wed 14/09/22 260 Express Express
262 Carpet 1 day Sat 17/09/22 Sat 17/09/22 242 Aywon Aywon
263 Rco Inspection 3 days Mon 19/09/22 Wed 21/09/22 262 RCo RCo
264 1st Clean 1 day Thu 22/09/22 Thu 22/09/22 263 CCG CCG
265 Client Inspection 2 days Tue 27/09/22 Wed 28/09/22 264 All trades All trades
266 Signage 1 day Thu 29/09/22 Thu 29/09/22 265 Signage Signage
267 2nd Clean 1 day Fri 30/09/22 Fri 30/09/22 266 CCG CCG
268 LEVEL 15 19.2 days Fri 19/03/21 Sat 10/04/21
269 Apartments 25 days Fri 19/08/22 Mon 19/09/22
270 ENERGISATION 3 days Fri 19/08/22 Tue 23/08/22 250 Apps Apps
271 Patch & Sand 3 days Wed 24/08/22 Fri 26/08/22 270 Express Express
272 Paint 3 days Sat 27/08/22 Tue 30/08/22 271 DEC group DEC group
273 Carpet 2 days Wed 7/09/22 Thu 8/09/22 253 Aywon Aywon
274 First Clean 2 days Fri 9/09/22 Sat 10/09/22 273 CCG CCG
275 Caulk 2 days Sat 10/09/22 Tue 13/09/22 274FS-1 day All trades All trades
276 Rco Inspection 4 days Sat 10/09/22 Thu 15/09/22 275SS RCo RCo
277 2nd Clean 1 day Fri 16/09/22 Fri 16/09/22 276 CCG CCG
278 Client Inspection 3 days Fri 16/09/22 Mon 19/09/22 277SS Setia Setia
279 Corridor 15 days Sat 10/09/22 Sat 1/10/22
280 ENERGISATION 1 day Sat 10/09/22 Sat 10/09/22 240 Apps Apps
281 Patch, Sand & Paint 2 days Tue 13/09/22 Wed 14/09/22 280 Express Express
282 Carpet 1 day Mon 19/09/22 Mon 19/09/22 262 Aywon Aywon
283 Rco Inspection 3 days Tue 20/09/22 Thu 22/09/22 282 RCo RCo
284 1st Clean 1 day Tue 27/09/22 Tue 27/09/22 283 CCG CCG
285 Client Inspection 2 days Wed 28/09/22 Thu 29/09/22 284 All trades All trades
286 Signage 1 day Fri 30/09/22 Fri 30/09/22 285 Signage Signage
287 2nd Clean 1 day Sat 1/10/22 Sat 1/10/22 286 CCG CCG
288 LEVEL 16 19.2 days Fri 19/03/21 Sat 10/04/21
289 Apartments 24 days Wed 24/08/22 Wed 21/09/22
290 ENERGISATION 3 days Wed 24/08/22 Fri 26/08/22 270 Apps Apps
291 Patch & Sand 3 days Sat 27/08/22 Tue 30/08/22 290 Express Express
292 Paint 3 days Wed 31/08/22 Fri 2/09/22 291 DEC group DEC group
293 Carpet 2 days Fri 9/09/22 Sat 10/09/22 273 Aywon Aywon
294 First Clean 2 days Tue 13/09/22 Wed 14/09/22 293 CCG CCG
295 Caulk 2 days Wed 14/09/22 Thu 15/09/22 294FS-1 day All trades All trades
296 Rco Inspection 4 days Wed 14/09/22 Sat 17/09/22 295SS RCo RCo
297 2nd Clean 1 day Mon 19/09/22 Mon 19/09/22 296 CCG CCG
298 Client Inspection 3 days Mon 19/09/22 Wed 21/09/22 297SS Setia Setia
299 Corridor 15 days Tue 13/09/22 Tue 4/10/22
300 ENERGISATION 1 day Tue 13/09/22 Tue 13/09/22 260 Apps Apps
301 Patch, Sand & Paint 2 days Wed 14/09/22 Thu 15/09/22 300 Express Express
302 Carpet 1 day Tue 20/09/22 Tue 20/09/22 282 Aywon Aywon
303 Rco Inspection 3 days Wed 21/09/22 Tue 27/09/22 302 RCo RCo
304 1st Clean 1 day Wed 28/09/22 Wed 28/09/22 303 CCG CCG
305 Client Inspection 2 days Thu 29/09/22 Fri 30/09/22 304 All trades All trades
306 Signage 1 day Sat 1/10/22 Sat 1/10/22 305 Signage Signage
307 2nd Clean 1 day Tue 4/10/22 Tue 4/10/22 306 CCG CCG
308 LEVEL 17 19.2 days Fri 19/03/21 Sat 10/04/21
309 Apartments 23 days Sat 27/08/22 Tue 27/09/22
310 ENERGISATION 3 days Sat 27/08/22 Tue 30/08/22 290 Apps Apps
311 Patch & Sand 3 days Wed 31/08/22 Fri 2/09/22 310 Express Express
312 Paint 3 days Sat 3/09/22 Tue 6/09/22 311 DEC group DEC group
313 Carpet 2 days Tue 13/09/22 Wed 14/09/22 293 Aywon Aywon
314 First Clean 2 days Thu 15/09/22 Fri 16/09/22 313 CCG CCG
315 Caulk 2 days Fri 16/09/22 Sat 17/09/22 314FS-1 day All trades All trades
316 Rco Inspection 4 days Fri 16/09/22 Tue 20/09/22 315SS RCo RCo
317 2nd Clean 1 day Wed 21/09/22 Wed 21/09/22 316 CCG CCG
318 Client Inspection 3 days Wed 21/09/22 Tue 27/09/22 317SS Setia Setia
319 Corridor 16 days Tue 13/09/22 Wed 5/10/22
320 ENERGISATION 1 day Tue 13/09/22 Tue 13/09/22 260 Apps Apps
321 Connection of Leemark DGP 1 day Thu 15/09/22 Thu 15/09/22 320FS+1 day Leemark / Apps Leemark / Apps
322 Patch, Sand & Paint 2 days Wed 14/09/22 Thu 15/09/22 320 Express Express
323 Carpet 1 day Wed 21/09/22 Wed 21/09/22 302 Aywon Aywon

Page 3
UNO COMPLETIONS & DEFECTING
PROGRAMME
ID Task Name Duration Start Finish Predecessors Resource Names Aug '22 Sep '22 Oct '22 Nov '22
18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31
324 Rco Inspection 3 days Thu 22/09/22 Wed 28/09/22 323 RCo RCo
325 1st Clean 1 day Thu 29/09/22 Thu 29/09/22 324 CCG CCG
326 Client Inspection 2 days Fri 30/09/22 Sat 1/10/22 325 All trades All trades
327 Signage 1 day Tue 4/10/22 Tue 4/10/22 326 Signage Signage
328 2nd Clean 1 day Wed 5/10/22 Wed 5/10/22 327 CCG CCG
329 LEVEL 18 19.2 days Fri 19/03/21 Sat 10/04/21
330 Apartments 17 days Tue 6/09/22 Thu 29/09/22
331 ENERGISATION 3 days Tue 6/09/22 Thu 8/09/22 310 Apps Apps
332 Patch & Sand 3 days Fri 9/09/22 Tue 13/09/22 331 Express Express
333 Paint 3 days Wed 14/09/22 Fri 16/09/22 332 DEC group DEC group
334 Carpet 2 days Thu 15/09/22 Fri 16/09/22 313 Aywon Aywon
335 First Clean 2 days Sat 17/09/22 Mon 19/09/22 333 CCG CCG
336 Caulk 2 days Mon 19/09/22 Tue 20/09/22 335FS-1 day All trades All trades
337 Rco Inspection 4 days Mon 19/09/22 Thu 22/09/22 336SS RCo RCo
338 2nd Clean 1 day Tue 27/09/22 Tue 27/09/22 337 CCG CCG
339 Client Inspection 3 days Tue 27/09/22 Thu 29/09/22 338SS Setia Setia
340 Corridor 16 days Wed 14/09/22 Thu 6/10/22
341 ENERGISATION 1 day Wed 14/09/22 Wed 14/09/22 320 Apps Apps
342 Patch, Sand & Paint 2 days Thu 15/09/22 Fri 16/09/22 341 Express Express
343 Carpet 1 day Thu 22/09/22 Thu 22/09/22 323 Aywon Aywon
344 Rco Inspection 3 days Tue 27/09/22 Thu 29/09/22 343 RCo RCo
345 1st Clean 1 day Fri 30/09/22 Fri 30/09/22 344 CCG CCG
346 Client Inspection 2 days Sat 1/10/22 Tue 4/10/22 345 All trades All trades
347 Signage 1 day Wed 5/10/22 Wed 5/10/22 346 Signage Signage
348 2nd Clean 1 day Thu 6/10/22 Thu 6/10/22 347 CCG CCG
349 LEVEL 19 19.2 days Fri 19/03/21 Sat 10/04/21
350 Apartments 17 days Fri 9/09/22 Tue 4/10/22
351 ENERGISATION 3 days Fri 9/09/22 Tue 13/09/22 331 Apps Apps
352 Patch & Sand 3 days Wed 14/09/22 Fri 16/09/22 351 Express Express
353 Paint 3 days Sat 17/09/22 Tue 20/09/22 352 DEC group DEC group
354 Carpet 2 days Sat 17/09/22 Mon 19/09/22 334 Aywon Aywon
355 First Clean 2 days Wed 21/09/22 Thu 22/09/22 353 CCG CCG
356 Caulk 2 days Thu 22/09/22 Tue 27/09/22 355FS-1 day All trades All trades
357 Rco Inspection 4 days Thu 22/09/22 Thu 29/09/22 356SS RCo RCo
358 2nd Clean 1 day Fri 30/09/22 Fri 30/09/22 357 CCG CCG
359 Client Inspection 3 days Fri 30/09/22 Tue 4/10/22 358SS Setia Setia
360 Corridor 16 days Thu 15/09/22 Fri 7/10/22
361 ENERGISATION 1 day Thu 15/09/22 Thu 15/09/22 341 Apps Apps
362 Patch, Sand & Paint 2 days Fri 16/09/22 Sat 17/09/22 361 Express Express
363 Carpet 1 day Tue 27/09/22 Tue 27/09/22 343 Aywon Aywon
364 Rco Inspection 3 days Wed 28/09/22 Fri 30/09/22 363 RCo RCo
365 1st Clean 1 day Sat 1/10/22 Sat 1/10/22 364 CCG CCG
366 Client Inspection 2 days Tue 4/10/22 Wed 5/10/22 365 All trades All trades
367 Signage 1 day Thu 6/10/22 Thu 6/10/22 366 Signage Signage
368 2nd Clean 1 day Fri 7/10/22 Fri 7/10/22 367 CCG CCG
369 LEVEL 20 19.2 days Fri 19/03/21 Sat 10/04/21
370 Apartments 17 days Wed 14/09/22 Fri 7/10/22
371 ENERGISATION 3 days Wed 14/09/22 Fri 16/09/22 351 Apps Apps
372 Patch & Sand 3 days Sat 17/09/22 Tue 20/09/22 371 Express Express
373 Paint 3 days Wed 21/09/22 Tue 27/09/22 372 DEC group DEC group
374 Carpet 2 days Tue 20/09/22 Wed 21/09/22 354 Aywon Aywon
375 First Clean 2 days Wed 28/09/22 Thu 29/09/22 373 CCG CCG
376 Caulk 2 days Thu 29/09/22 Fri 30/09/22 375FS-1 day All trades All trades
377 Rco Inspection 4 days Thu 29/09/22 Tue 4/10/22 376SS RCo RCo
378 2nd Clean 1 day Wed 5/10/22 Wed 5/10/22 377 CCG CCG
379 Client Inspection 3 days Wed 5/10/22 Fri 7/10/22 378SS Setia Setia
380 Corridor 9 days Wed 28/09/22 Sat 8/10/22
381 ENERGISATION 1 day Fri 30/09/22 Fri 30/09/22 Apps Apps
382 Patch, Sand & Paint 2 days Sat 1/10/22 Tue 4/10/22 381 Express Express
383 Carpet 1 day Wed 28/09/22 Wed 28/09/22 363 Aywon Aywon
384 Rco Inspection 3 days Thu 29/09/22 Sat 1/10/22 383 RCo RCo
385 1st Clean 1 day Tue 4/10/22 Tue 4/10/22 384 CCG CCG
386 Client Inspection 2 days Wed 5/10/22 Thu 6/10/22 385 All trades All trades
387 Signage 1 day Fri 7/10/22 Fri 7/10/22 386 Signage Signage
388 2nd Clean 1 day Sat 8/10/22 Sat 8/10/22 387 CCG CCG
389 LEVEL 21 19.2 days Fri 19/03/21 Sat 10/04/21
390 Apartments 17 days Sat 17/09/22 Tue 11/10/22
391 ENERGISATION 3 days Sat 17/09/22 Tue 20/09/22 371 Apps Apps
392 Patch & Sand 3 days Wed 21/09/22 Tue 27/09/22 391 Express Express
393 Paint 3 days Wed 28/09/22 Fri 30/09/22 392 DEC group DEC group
394 Carpet 2 days Thu 22/09/22 Tue 27/09/22 374 Aywon Aywon
395 First Clean 2 days Sat 1/10/22 Tue 4/10/22 393 CCG CCG
396 Caulk 2 days Tue 4/10/22 Wed 5/10/22 395FS-1 day All trades All trades
397 Rco Inspection 4 days Tue 4/10/22 Fri 7/10/22 396SS RCo RCo
398 2nd Clean 1 day Sat 8/10/22 Sat 8/10/22 397 CCG CCG
399 Client Inspection 3 days Sat 8/10/22 Tue 11/10/22 398SS Setia Setia
400 Corridor 9 days Thu 29/09/22 Mon 10/10/22
401 ENERGISATION 1 day Sat 1/10/22 Sat 1/10/22 381 Apps Apps
402 Patch, Sand & Paint 2 days Tue 4/10/22 Wed 5/10/22 401 Express Express
403 Carpet 1 day Thu 29/09/22 Thu 29/09/22 383 Aywon Aywon

Page 4
UNO COMPLETIONS & DEFECTING
PROGRAMME
ID Task Name Duration Start Finish Predecessors Resource Names Aug '22 Sep '22 Oct '22 Nov '22
18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31
404 Rco Inspection 3 days Fri 30/09/22 Tue 4/10/22 403 RCo RCo
405 1st Clean 1 day Wed 5/10/22 Wed 5/10/22 404 CCG CCG
406 Client Inspection 2 days Thu 6/10/22 Fri 7/10/22 405 All trades All trades
407 Signage 1 day Sat 8/10/22 Sat 8/10/22 406 Signage Signage
408 2nd Clean 1 day Mon 10/10/22 Mon 10/10/22 407 CCG CCG
409 LEVEL 22 19.2 days Fri 19/03/21 Sat 10/04/21
410 Apartments 17 days Wed 21/09/22 Fri 14/10/22
411 ENERGISATION 3 days Wed 21/09/22 Tue 27/09/22 391 Apps Apps
412 Patch & Sand 3 days Wed 28/09/22 Fri 30/09/22 411 Express Express
413 Paint 3 days Sat 1/10/22 Wed 5/10/22 412 DEC group DEC group
414 Carpet 2 days Wed 28/09/22 Thu 29/09/22 394 Aywon Aywon
415 First Clean 2 days Thu 6/10/22 Fri 7/10/22 413 CCG CCG
416 Caulk 2 days Fri 7/10/22 Sat 8/10/22 415FS-1 day All trades All trades
417 Rco Inspection 4 days Fri 7/10/22 Tue 11/10/22 416SS RCo RCo
418 2nd Clean 1 day Wed 12/10/22 Wed 12/10/22 417 CCG CCG
419 Client Inspection 3 days Wed 12/10/22 Fri 14/10/22 418SS Setia Setia
420 Corridor 9 days Fri 30/09/22 Tue 11/10/22
421 ENERGISATION 1 day Sat 1/10/22 Sat 1/10/22 381 Apps Apps
422 Patch, Sand & Paint 2 days Tue 4/10/22 Wed 5/10/22 421 Express Express
423 Carpet 1 day Fri 30/09/22 Fri 30/09/22 403 Aywon Aywon
424 Rco Inspection 3 days Sat 1/10/22 Wed 5/10/22 423 RCo RCo
425 1st Clean 1 day Thu 6/10/22 Thu 6/10/22 424 CCG CCG
426 Client Inspection 2 days Fri 7/10/22 Sat 8/10/22 425 All trades All trades
427 Signage 1 day Mon 10/10/22 Mon 10/10/22 426 Signage Signage
428 2nd Clean 1 day Tue 11/10/22 Tue 11/10/22 427 CCG CCG
429 LEVEL 23 19.2 days Fri 19/03/21 Sat 10/04/21
430 Apartments 17 days Wed 28/09/22 Wed 19/10/22
431 ENERGISATION 3 days Wed 28/09/22 Fri 30/09/22 411 Apps Apps
432 Patch & Sand 3 days Sat 1/10/22 Wed 5/10/22 431 Express Express
433 Paint 3 days Thu 6/10/22 Sat 8/10/22 432 DEC group DEC group
434 Carpet 2 days Fri 30/09/22 Sat 1/10/22 414 Aywon Aywon
435 First Clean 2 days Mon 10/10/22 Tue 11/10/22 433 CCG CCG
436 Caulk 2 days Tue 11/10/22 Wed 12/10/22 435FS-1 day All trades All trades
437 Rco Inspection 4 days Tue 11/10/22 Fri 14/10/22 436SS RCo RCo
438 2nd Clean 1 day Sat 15/10/22 Sat 15/10/22 437 CCG CCG
439 Client Inspection 3 days Sat 15/10/22 Wed 19/10/22 438SS Setia Setia
440 Corridor 9 days Sat 1/10/22 Wed 12/10/22
441 ENERGISATION 1 day Tue 4/10/22 Tue 4/10/22 401 Apps Apps
442 Patch, Sand & Paint 2 days Wed 5/10/22 Thu 6/10/22 441 Express Express
443 Carpet 1 day Sat 1/10/22 Sat 1/10/22 423 Aywon Aywon
444 Rco Inspection 3 days Tue 4/10/22 Thu 6/10/22 443 RCo RCo
445 1st Clean 1 day Fri 7/10/22 Fri 7/10/22 444 CCG CCG
446 Client Inspection 2 days Sat 8/10/22 Mon 10/10/22 445 All trades All trades
447 Signage 1 day Tue 11/10/22 Tue 11/10/22 446 Signage Signage
448 2nd Clean 1 day Wed 12/10/22 Wed 12/10/22 447 CCG CCG
449 LEVEL 24 19.2 days Fri 19/03/21 Sat 10/04/21
450 Apartments 20 days Tue 4/10/22 Thu 27/10/22
451 ENERGISATION 3 days Fri 7/10/22 Mon 10/10/22 431FS+4 days Apps Apps
452 Patch & Sand 3 days Tue 11/10/22 Thu 13/10/22 451 Express Express
453 Paint 3 days Fri 14/10/22 Tue 18/10/22 452 DEC group DEC group
454 Carpet 2 days Tue 4/10/22 Wed 5/10/22 434 Aywon Aywon
455 First Clean 2 days Wed 19/10/22 Thu 20/10/22 453 CCG CCG
456 Caulk 2 days Thu 20/10/22 Fri 21/10/22 455FS-1 day All trades All trades
457 Rco Inspection 4 days Thu 20/10/22 Mon 24/10/22 456SS RCo RCo
458 2nd Clean 1 day Tue 25/10/22 Tue 25/10/22 457 CCG CCG
459 Client Inspection 3 days Tue 25/10/22 Thu 27/10/22 458SS Setia Setia
460 Corridor 9 days Tue 4/10/22 Thu 13/10/22
461 ENERGISATION 1 day Tue 4/10/22 Tue 4/10/22 401 Apps Apps
462 Patch, Sand & Paint 2 days Wed 5/10/22 Thu 6/10/22 461 Express Express
463 Carpet 1 day Tue 4/10/22 Tue 4/10/22 443 Aywon Aywon
464 Rco Inspection 3 days Wed 5/10/22 Fri 7/10/22 463 RCo RCo
465 1st Clean 1 day Sat 8/10/22 Sat 8/10/22 464 CCG CCG
466 Client Inspection 2 days Mon 10/10/22 Tue 11/10/22 465 All trades All trades
467 Signage 1 day Wed 12/10/22 Wed 12/10/22 466 Signage Signage
468 2nd Clean 1 day Thu 13/10/22 Thu 13/10/22 467 CCG CCG
469 LEVEL 25 19.2 days Fri 19/03/21 Sat 10/04/21
470 Apartments 21 days Thu 6/10/22 Fri 4/11/22
471 ENERGISATION 3 days Tue 11/10/22 Thu 13/10/22 451 Apps Apps
472 Patch & Sand 3 days Fri 14/10/22 Tue 18/10/22 471 Express Express
473 Paint 3 days Wed 19/10/22 Fri 21/10/22 472 DEC group DEC group
474 Carpet 2 days Thu 6/10/22 Fri 7/10/22 454 Aywon Aywon
475 First Clean 2 days Sat 22/10/22 Mon 24/10/22 473 CCG CCG
476 Caulk 2 days Mon 24/10/22 Tue 25/10/22 475FS-1 day All trades All trades
477 Rco Inspection 4 days Mon 24/10/22 Thu 27/10/22 476SS RCo RCo
478 2nd Clean 1 day Fri 28/10/22 Fri 28/10/22 477 CCG CCG
479 Client Inspection 3 days Fri 28/10/22 Fri 4/11/22 478SS Setia Setia
480 Corridor 9 days Wed 5/10/22 Fri 14/10/22
481 ENERGISATION 1 day Wed 5/10/22 Wed 5/10/22 461 Apps Apps
482 Patch, Sand & Paint 2 days Thu 6/10/22 Fri 7/10/22 481 Express Express
483 Carpet 1 day Wed 5/10/22 Wed 5/10/22 463 Aywon Aywon

Page 5
UNO COMPLETIONS & DEFECTING
PROGRAMME
ID Task Name Duration Start Finish Predecessors Resource Names Aug '22 Sep '22 Oct '22 Nov '22
18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31
484 Rco Inspection 3 days Thu 6/10/22 Sat 8/10/22 483 RCo RCo
485 1st Clean 1 day Mon 10/10/22 Mon 10/10/22 484 CCG CCG
486 Client Inspection 2 days Tue 11/10/22 Wed 12/10/22 485 All trades All trades
487 Signage 1 day Thu 13/10/22 Thu 13/10/22 486 Signage Signage
488 2nd Clean 1 day Fri 14/10/22 Fri 14/10/22 487 CCG CCG
489 LEVEL 26 19.2 days Fri 19/03/21 Sat 10/04/21
490 Apartments 19 days Sat 8/10/22 Fri 4/11/22
491 ENERGISATION 3 days Fri 14/10/22 Tue 18/10/22 471 Apps Apps
492 Patch & Sand 2 days Wed 19/10/22 Thu 20/10/22 491 Express Express
493 Paint 2 days Fri 21/10/22 Sat 22/10/22 492 DEC group DEC group
494 Carpet 2 days Sat 8/10/22 Mon 10/10/22 474 Aywon Aywon
495 First Clean 2 days Mon 24/10/22 Tue 25/10/22 493 CCG CCG
496 Caulk 2 days Tue 25/10/22 Wed 26/10/22 495FS-1 day All trades All trades
497 Rco Inspection 3 days Tue 25/10/22 Thu 27/10/22 496SS RCo RCo
498 2nd Clean 1 day Tue 25/10/22 Tue 25/10/22 496SS CCG CCG
499 Client Inspection 3 days Fri 28/10/22 Fri 4/11/22 497 Setia Setia
500 Corridor 10 days Wed 5/10/22 Sat 15/10/22
501 ENERGISATION 1 day Wed 5/10/22 Wed 5/10/22 461 Apps Apps
502 Patch, Sand & Paint 2 days Thu 6/10/22 Fri 7/10/22 501 Express Express
503 Carpet 1 day Thu 6/10/22 Thu 6/10/22 483 Aywon Aywon
504 Rco Inspection 3 days Fri 7/10/22 Mon 10/10/22 503 RCo RCo
505 1st Clean 1 day Tue 11/10/22 Tue 11/10/22 504 CCG CCG
506 Client Inspection 2 days Wed 12/10/22 Thu 13/10/22 505 All trades All trades
507 Signage 1 day Fri 14/10/22 Fri 14/10/22 506 Signage Signage
508 2nd Clean 1 day Sat 15/10/22 Sat 15/10/22 507 CCG CCG
509 LEVEL 27 19.2 days Fri 19/03/21 Sat 10/04/21
510 Apartments 18 days Tue 11/10/22 Sat 5/11/22
511 ENERGISATION 3 days Wed 19/10/22 Fri 21/10/22 491 Apps Apps
512 Patch & Sand 2 days Sat 22/10/22 Mon 24/10/22 511 Express Express
513 Paint 2 days Tue 25/10/22 Wed 26/10/22 512 DEC group DEC group
514 Carpet 2 days Tue 11/10/22 Wed 12/10/22 494 Aywon Aywon
515 First Clean 2 days Thu 27/10/22 Fri 28/10/22 513 CCG CCG
516 Caulk 2 days Fri 28/10/22 Thu 3/11/22 515FS-1 day All trades All trades
517 Rco Inspection 4 days Fri 28/10/22 Sat 5/11/22 516SS RCo
518 2nd Clean 1 day Fri 28/10/22 Fri 28/10/22 516SS CCG CCG
519 Client Inspection 3 days Fri 28/10/22 Fri 4/11/22 516SS Setia Setia
520 Corridor 10 days Thu 6/10/22 Tue 18/10/22
521 ENERGISATION 1 day Thu 6/10/22 Thu 6/10/22 481 Apps Apps
522 Patch, Sand & Paint 2 days Fri 7/10/22 Sat 8/10/22 521 Express Express
523 Carpet 1 day Fri 7/10/22 Fri 7/10/22 503 Aywon Aywon
524 Rco Inspection 3 days Sat 8/10/22 Tue 11/10/22 523 RCo RCo
525 1st Clean 1 day Wed 12/10/22 Wed 12/10/22 524 CCG CCG
526 Client Inspection 2 days Thu 13/10/22 Fri 14/10/22 525 All trades All trades
527 Signage 1 day Sat 15/10/22 Sat 15/10/22 526 Signage Signage
528 2nd Clean 1 day Tue 18/10/22 Tue 18/10/22 527 CCG CCG
529 LEVEL 28 & LMR & LIFTS 3, 4, 5 & 6 404.9 days Fri 19/03/21 Tue 20/09/22
530 Energise Lift Board 1 day Fri 19/03/21 Sat 20/03/21 Apps
531 Commission Temp Mech to LMR 1 day Fri 19/03/21 Sat 20/03/21 Ellis Air / Apps
532 Lifts 3, 4, 5 & 6 Commissioned 0 days Tue 20/09/22 Tue 20/09/22 20/09
533 Client Defects Inspection & Rectification 4 days Sat 20/03/21 Thu 25/03/21 531 Setia
534 LEVEL 39 9 days Tue 19/07/22 Fri 29/07/22
535 Level 39 Façade Install 1 day Tue 19/07/22 Tue 19/07/22 Colab Colab
536 High Level Fire/Elec/Mech Rough incl. Hot Water Plant to Temp Tank 4 days Wed 20/07/22 Sat 23/07/22 535 Services S/C Services S/C

537 Speedpanel to Gas Riser and Lobby Supply Riser 4 days Tue 26/07/22 Fri 29/07/22 536 Express Express
538 LEVEL 40 77 days Wed 29/06/22 Thu 6/10/22
539 Pour Level 40 4 days Wed 29/06/22 Sat 2/07/22 I&D
540 Stripping level 40 12 days Mon 4/07/22 Mon 18/07/22 539 I&D I&D
541 Install Loading Bay 4 days Tue 19/07/22 Fri 22/07/22 540 I&D I&D
542 Level 40 Façade Load 4 days Sat 23/07/22 Thu 28/07/22 541 Colab Colab
543 Level 40 Façade Install 4 days Fri 29/07/22 Tue 2/08/22 542 Colab Colab
544 High Level Fire/Elec/Mech Rough In To Plantrooms 4 days Wed 3/08/22 Sat 6/08/22 543 Services S/C Services S/C
545 Duct, Fans & Hot Water Plant Loaded outside of Plantrooms 3 days Tue 9/08/22 Thu 11/08/22 544 Ellis Air Ellis Air
546 Plinths & Hobs Poured 4 days Tue 9/08/22 Fri 12/08/22 544 I&D I&D
547 Tanking of Plant Room 4 days Sat 13/08/22 Wed 17/08/22 546 Polyseal Polyseal
548 Mech Plantroom Install 10 days Thu 18/08/22 Tue 30/08/22 547 Ellis Air Ellis Air
549 Hot Water Plant Room Install 6 days Thu 18/08/22 Thu 25/08/22 547 CDC/Energy Australia CDC/Energy Australia
550 Temp Tank Install 4 days Wed 31/08/22 Sat 3/09/22 548 CDC CDC
551 Speedpanel to Plantrooms, Gas Riser and Lobby Supply Riser 4 days Mon 5/09/22 Thu 8/09/22 550 Express Express
552 Hot Water Commissioning 12 days Mon 19/09/22 Thu 6/10/22 550,549,83FS-8 days
CDC/Energy Australia CDC/Energy Australia
553 Lobby Supply Commissioning 5 days Fri 30/09/22 Thu 6/10/22 37 Ellis Air Ellis Air
554 LEVEL 41 3 days Tue 9/08/22 Thu 11/08/22
555 Fire Rated Lid Installed to the Gas Riser and Lobby Supply Riser 1 day Tue 9/08/22 Tue 9/08/22 544 Express Express
556 Gas capped off/separated & Fire Sealed 2 days Wed 10/08/22 Thu 11/08/22 555 Ellis Air Ellis Air