ID Task Name Duration Start Finish 022 April 2022 May 2022 June 2022 July 2022 August

Finish 022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06
1 NTI IMAM BONJOL BP‐AKR 90 days Wed 06/04/22 Sat 09/07/22 NTI IMAM BONJOL BP-AKR
2  MILESTONES 90 days Wed 06/04/22 Sat 09/07/22 MILESTONES
3 KOM 0 days Wed 06/04/22 Wed 06/04/22 KOM 06/04
4 Pilling Work Completed 0 days Wed 27/04/22 Wed 27/04/22 Pilling Work Completed 27/04
5 UST Piling Completed 0 days Mon 18/04/22 Mon 18/04/22 UST Piling Completed 18/04
6 Tank Sinking 0 days Mon 09/05/22 Mon 09/05/22 Tank Sinking 09/05
7 Fore Court completed 0 days Fri 17/06/22 Fri 17/06/22 Fore Court completed 17/06
8 Office& Shop Building Completed 0 days Mon 04/07/22 Mon 04/07/22 Office& Shop Building Completed 04/07
9 Fuel System& IT System Completed  0 days Wed 15/06/22 Wed 15/06/22 Fuel System& IT System Completed 15/06
10 RVIe 0 days Wed 29/06/22 Wed 29/06/22 RVIe 29/06
11 Monolith Completed 0 days Tue 05/07/22 Tue 05/07/22 Monolith Completed 05/07
12 Virgin Delivery 0 days Sun 26/06/22 Sun 26/06/22 Virgin Delivery 26/06
13 COI 0 days Tue 05/07/22 Tue 05/07/22 COI 05/07
14 Pre‐ Handover 0 days Fri 08/07/22 Fri 08/07/22 Pre- Handover 08/07
15 Handover/OTP 0 days Sat 09/07/22 Sat 09/07/22 Handover/OTP 09/07
16 CONSTRUCTION WORK 90 days Wed 06/04/22 Sat 09/07/22 CONSTRUCTION WORK
17 E2E PROCESS EXECUTION 90 days Wed 06/04/22 Sat 09/07/22 E2E PROCESS EXECUTION
18 CONSTRUCTION WORK 86 days Wed 06/04/22 Tue 05/07/22 CONSTRUCTION WORK
19 Land Development 3 days Wed 06/04/22 Fri 08/04/22 Land Development
20 Remove debris 1 day Wed 06/04/22 Wed 06/04/22 Remove debris 06/04
21 Survey and Topografi 2 days Thu 07/04/22 Fri 08/04/22 Survey and Topografi 07/04
22 Temporary Facilities 4 days Wed 06/04/22 Sat 09/04/22 Temporary Facilities
23 Mobilization 2 days Wed 06/04/22 Thu 07/04/22 Mobilization 06/04
24 Site preliminaries set up 2 days Fri 08/04/22 Sat 09/04/22 Site preliminaries set up 08/04
25 Pilling Work 18 days Sat 09/04/22 Wed 27/04/22 Pilling Work
26 Pilling Machine Inspection Checlist 1 day Sat 09/04/22 Sun 10/04/22 Pilling Machine Inspection Checlist 09/04
27 Pilling Machine Mobilization and  1 day Sun 10/04/22 Mon 11/04/22 Pilling Machine Mobilization and Instalation 10/04
Instalation
28 Pilling Material Mobilization 2 days Mon 11/04/22 Wed 13/04/22 Pilling Material Mobilization 11/04
29 Pilling Tank Farm Foundation 5 days Wed 13/04/22 Mon 18/04/22 Pilling Tank Farm Foundation 13/04
30 Pilling Building Fundation 5 days Mon 18/04/22 Sat 23/04/22 Pilling Building Fundation 18/04
31 Pilling Forecourt Foundation 3 days Sat 23/04/22 Tue 26/04/22 Pilling Forecourt Foundation 23/04
32 Pilling Monolith foundation 1 day Tue 26/04/22 Wed 27/04/22 Pilling Monolith foundation 26/04
33 Tankfarm Construction  13 days Mon 18/04/22 Sun 08/05/22 Tankfarm Construction
34 Capping Beam 4 days Mon 18/04/22 Fri 22/04/22 Capping Beam 18/04
35 Excavation Soil 3 days Fri 22/04/22 Mon 25/04/22 Excavation Soil 22/04
36 Slab Below and Anchor 5 days Mon 25/04/22 Sun 08/05/22 Slab Below and Anchor 25/04
37 Screening 1st filling 1 day Sun 08/05/22 Sun 08/05/22 Screening 1st filling 08/05
38 Tanks Instalation 11 days Mon 25/04/22 Fri 13/05/22 Tanks Instalation
39 Crane 25 Ton Checklist 1 day Mon 25/04/22 Tue 26/04/22 Crane 25 Ton Checklist 25/04
40 Tanks Instalation 1 day Mon 09/05/22 Mon 09/05/22 Tanks Instalation 09/05
41 Observation Well Instalation 1 day Tue 10/05/22 Tue 10/05/22 Observation Well Instalation 10/05
42 2nd Back Filling Screening 3 days Wed 11/05/22 Fri 13/05/22 2nd Back Filling Screening 11/05
43 Office& Shop Building Construction 67 days Sat 23/04/22 Mon 04/07/22 Office& Shop Building Construction
44 Foundation 5 days Sat 23/04/22 Fri 06/05/22 Foundation 23/04
45 Curring time 1 day Fri 06/05/22 Sat 07/05/22 Curring time 06/05
46 Structure and roof 14 days Sat 07/05/22 Fri 20/05/22 Structure and roof 07/05
47 Wall and rendering 25 days Fri 20/05/22 Mon 13/06/22 Wall and rendering 20/05
48 Mechanical‐electrical installation 30 days Fri 06/05/22 Sat 04/06/22 Mechanical-electrical installation 06/05
49 Ceiling Work 8 days Mon 30/05/22 Mon 06/06/22 Ceiling Work 30/05
50 Flooring work 12 days Mon 13/06/22 Sat 25/06/22 Flooring work 13/06
51 Door& Window 10 days Sat 25/06/22 Mon 04/07/22 Door& Window 25/06
52 Forecourt Structure Construction 32 days Tue 26/04/22 Sat 04/06/22 Forecourt Structure Construction
53 Forecourt Foundation 4 days Tue 26/04/22 Sun 08/05/22 Forecourt Foundation 26/04
54 Structure and roof Canopy 15 days Fri 20/05/22 Sat 04/06/22 Structure and roof Canopy 20/05
55 FSY ‐ Tanks Equipment Instalation 7 days Sat 14/05/22 Fri 20/05/22 FSY - Tanks Equipment Instalation
56 Pipe Material Mobilization 2 days Sat 14/05/22 Sun 15/05/22 Pipe Material Mobilization 14/05

Task Summary Inactive Task Duration-only Finish-only Critical Baseline Summary

Split Project Summary Inactive Milestone Manual Summary Rollup External Tasks Critical Split Progress

Milestone Rolled Up Critical Inactive Summary Manual Summary External Milestone Baseline

Slippage Rolled Up Critical Split Manual Task Start-only Deadline Baseline Milestone
ID Task Name Duration Start Finish 022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06
57 Collar modification & pneumatic test2 days Sun 15/05/22 Tue 17/05/22 Collar modification & pneumatic test 15/05
58 QC 1.12 Install Tank Chamber&   1 day Tue 17/05/22 Wed 18/05/22 QC 1.12 Install Tank Chamber& Vacum test for tank chamber 17/05
Vacum test for tank chamber
59 QC 1.17 Tank Equipment Instalation 2 days Wed 18/05/22 Fri 20/05/22 QC 1.17 Tank Equipment Instalation 18/05
60 FSY Work KPS PIPE Lines Instalation 21 days Mon 16/05/22 Sun 05/06/22 FSY Work KPS PIPE Lines Instalation
61 Pipe 11 days Mon 16/05/22 Fri 27/05/22 Pipe
62 Tank Testing (After 80 % backfill  1 day Mon 16/05/22 Tue 17/05/22 Tank Testing (After 80 % backfill tank) 16/05
tank)
63 Install pipe line fill 3 days Fri 20/05/22 Mon 23/05/22 Install pipe line fill 20/05
64 Install pipe line product 2 days Mon 23/05/22 Wed 25/05/22 Install pipe line product 23/05
65 Install pipe vent 2 days Wed 25/05/22 Fri 27/05/22 Install pipe vent 25/05
66 Instalation easy riser and all jointing 3 days Fri 27/05/22 Mon 30/05/22 Instalation easy riser and all jointing (Before and Backfill) 27/05
(Before and Backfill)
67 Filling point area (discharge point) 2 days Mon 30/05/22 Wed 01/06/22 Filling point area (discharge point) 30/05
68 QC 1.14 Fill Point 1 day Wed 01/06/22 Thu 02/06/22 QC 1.14 Fill Point 01/06
69 Setting spill contaiment (Before or  2 days Mon 30/05/22 Wed 01/06/22 Setting spill contaiment (Before or After Pouring Concrete) 30/05
After Pouring Concrete)
70 Instalation and all jointing fill point  1 day Mon 30/05/22 Tue 31/05/22 Instalation and all jointing fill point (Before concrete fill point) 30/05
(Before concrete fill point)
71 Install and joint pipe line vapor  1 day Tue 31/05/22 Wed 01/06/22 Install and joint pipe line vapor recovery 31/05
recovery
72 Pump Island area Canopy 7 days Fri 27/05/22 Fri 03/06/22 Pump Island area Canopy
73 QC 1.13 Under Dispenser Sump 2 days Fri 27/05/22 Sun 29/05/22 QC 1.13 Under Dispenser Sump 27/05
74 Setting entry boots electrofusion  1 day Sun 29/05/22 Mon 30/05/22 Setting entry boots electrofusion in UDC (After Tank Farm) 29/05
in UDC (After Tank Farm)
75 Assembling Share valve and  1 day Mon 30/05/22 Tue 31/05/22 Assembling Share valve and accessoris 30/05
accessoris
76 Welding electrofusion accessoris  1 day Tue 31/05/22 Wed 01/06/22 Welding electrofusion accessoris UDC 31/05
UDC
77 Setting and install pipe line produc1 day Wed 01/06/22 Thu 02/06/22 Setting and install pipe line product 01/06
78 Instal electrical detector tape 1 day Thu 02/06/22 Fri 03/06/22 Instal electrical detector tape 02/06
79 Testing Pipe Line 1 day Wed 25/05/22 Thu 26/05/22 Testing Pipe Line 25/05
80 Pressure test Pre Burried test 4 days Thu 02/06/22 Sun 05/06/22 Pressure test Pre Burried test 02/06
81 Tankfarm Floor Concreting 8 days Mon 06/06/22 Mon 13/06/22 Tankfarm Floor Concreting
82 3rd Screening Backfill 2 days Mon 06/06/22 Tue 07/06/22 3rd Screening Backfill 06/06
83 Top Slab Tank 6 days Wed 08/06/22 Mon 13/06/22 Top Slab Tank 08/06
84 Drainage and Soak Well Work 13 days Sat 23/04/22 Fri 13/05/22 Drainage and Soak Well Work
85 Drainage and Soak well material  3 days Sat 23/04/22 Tue 26/04/22 Drainage and Soak well material mobilization 23/04
mobilization
86 Drainage and Soak well excavation  10 days Tue 26/04/22 Fri 13/05/22 Drainage and Soak well excavation and approval for tanks 26/04
and approval for tanks
87 Forecourt Floor Concreting (LTP)  46 days Sun 08/05/22 Tue 21/06/22 Forecourt Floor Concreting (LTP) Including Bollard
Including Bollard
88 Sub Base, Compaction and CBR Test 9 days Sun 08/05/22 Mon 16/05/22 Sub Base, Compaction and CBR Test 08/05
89 Forecourt, Floor & Concreting  6 days Wed 08/06/22 Mon 13/06/22 Forecourt, Floor & Concreting including bollards 08/06
including bollards
90 Pressure Post Burried Test 2 days Mon 13/06/22 Wed 15/06/22 Pressure Post Burried Test 13/06
91 Ceiling Forecourt (Luxalon) 8 days Mon 13/06/22 Tue 21/06/22 Ceiling Forecourt (Luxalon) 13/06
92 Pump Island (Finishing) 4 days Mon 13/06/22 Fri 17/06/22 Pump Island (Finishing) 13/06
93 Vent Area (Easy Riser mode) 1 day Mon 13/06/22 Tue 14/06/22 Vent Area (Easy Riser mode)
94 Install easy riser and accessories  1 day Mon 13/06/22 Tue 14/06/22 Install easy riser and accessories (After Backfill) 13/06
(After Backfill)
95 Discharge Point construction and  7 days Wed 08/06/22 Tue 14/06/22 Discharge Point construction and finishing 08/06
finishing
96 Drive Way Pavement 44 days Mon 16/05/22 Tue 28/06/22 Drive Way Pavement
97 Paving & cansteen material  1 day Sat 11/06/22 Sun 12/06/22 Paving & cansteen material mobilization 11/06
mobilization
98 Forecourt Pavement Installation  10 days Sun 12/06/22 Wed 22/06/22 Forecourt Pavement Installation (paving and canstein) 12/06
(paving and canstein)
99 Ingress Construction 4 days Mon 16/05/22 Fri 20/05/22 Ingress Construction 16/05

Task Summary Inactive Task Duration-only Finish-only Critical Baseline Summary

Split Project Summary Inactive Milestone Manual Summary Rollup External Tasks Critical Split Progress

Milestone Rolled Up Critical Inactive Summary Manual Summary External Milestone Baseline

Slippage Rolled Up Critical Split Manual Task Start-only Deadline Baseline Milestone
ID Task Name Duration Start Finish 022 April 2022 May 2022 June 2022 July 2022 August 2022
Mode 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06
100 Egress Consruction 7 days Mon 16/05/22 Mon 23/05/22 Egress Consruction 16/05
101 Egress Consruction 2nd 6 days Wed 08/06/22 Mon 13/06/22 Egress Consruction 2nd 08/06
102 Road covers 1 day Wed 22/06/22 Thu 23/06/22 Road covers 22/06
103 Air & water facility 5 days Thu 23/06/22 Tue 28/06/22 Air & water facility 23/06
104 RVIE AND MONOLITH WORK  15 days Tue 21/06/22 Tue 05/07/22 RVIE AND MONOLITH WORK (HEKSAGON)
(HEKSAGON)
105 CANOPY RIGHT SIDE 1 day Tue 21/06/22 Wed 22/06/22 CANOPY RIGHT SIDE 21/06
106 CANOPY LEFT SIDE 1 day Wed 22/06/22 Thu 23/06/22 CANOPY LEFT SIDE 22/06
107 CANOPY BACK SIDE 2 days Thu 23/06/22 Sat 25/06/22 CANOPY BACK SIDE 23/06
108 CANOPY FRONT SIDE 2 days Sat 25/06/22 Mon 27/06/22 CANOPY FRONT SIDE 25/06
109 CANOPY FASCIA INSTALLATION 1 day Mon 27/06/22 Tue 28/06/22 CANOPY FASCIA INSTALLATION 27/06
110 CANOPY RED BAR INSTALLATION 1 day Tue 28/06/22 Wed 29/06/22 CANOPY RED BAR INSTALLATION 28/06
111 SPREADER PUMP NUMBER  2 days Wed 29/06/22 Fri 01/07/22 SPREADER PUMP NUMBER INSTALLATION 29/06
INSTALLATION
112 HSSE POSTER INSTALLATION 2 days Fri 01/07/22 Sun 03/07/22 HSSE POSTER INSTALLATION 01/07
113 CSU INSTALLATION 1 day Sun 03/07/22 Sun 03/07/22 CSU INSTALLATION 03/07
114 LEADER BOARD INSTALLATION 1 day Mon 04/07/22 Mon 04/07/22 LEADER BOARD INSTALLATION 04/07
115 SIGN IN/OUT INSTALLATION 1 day Mon 04/07/22 Mon 04/07/22 SIGN IN/OUT INSTALLATION 04/07
116 SIGN AIR WATER FACILITY  1 day Mon 04/07/22 Mon 04/07/22 SIGN AIR WATER FACILITY INSTALLATION 04/07
INSTALLATION
117 MONOLITH INSTALLATION 1 day Tue 05/07/22 Tue 05/07/22 MONOLITH INSTALLATION 05/07
118 Drainage and Soak Well Work 11 days Sat 14/05/22 Tue 24/05/22 Drainage and Soak Well Work
119 Drainage and OWS installation 4 days Sat 14/05/22 Tue 17/05/22 Drainage and OWS installation 14/05
120 QC 1.11 Installation of Oil Water  7 days Tue 17/05/22 Tue 24/05/22 QC 1.11 Installation of Oil Water Separator 17/05
Separator
121 ELECTRICAL 24 days Fri 20/05/22 Sun 12/06/22 ELECTRICAL
122 Wirring Cable Installation & IT Cable 14 days Fri 20/05/22 Fri 03/06/22 Wirring Cable Installation & IT Cable 20/05
123 Panel Electrical Instalation 10 days Fri 03/06/22 Sun 12/06/22 Panel Electrical Instalation 03/06
124 Lighting Installation (In/Out) 4 days Fri 20/05/22 Tue 24/05/22 Lighting Installation (In/Out) 20/05
125 Perimeter lamp material delivery 5 days Tue 24/05/22 Sun 29/05/22 Perimeter lamp material delivery 24/05
126 Perimeter lamp Installation 1 day Sun 29/05/22 Mon 30/05/22 Perimeter lamp Installation 29/05
127 CCTV Internal delivery 1 day Fri 03/06/22 Sat 04/06/22 CCTV Internal delivery 03/06
128 CCTV Installation 4 days Fri 03/06/22 Mon 06/06/22 CCTV Installation 03/06
129 Dispenser Installation  2 days Sun 12/06/22 Tue 14/06/22 Dispenser Installation
130 Dispensers delivery 1 day Sun 12/06/22 Mon 13/06/22 Dispensers delivery 12/06
131 Dispenser Installation work (After  1 day Mon 13/06/22 Tue 14/06/22 Dispenser Installation work (After Canopy Civil) Work Complete & Pouring Concrete Island 13/06
Canopy Civil) Work Complete & 
Pouring Concrete Island
132 Genset Work 1 day Sat 07/05/22 Sun 08/05/22 Genset Work
133 Genset Equipment Installation 1 day Sat 07/05/22 Sun 08/05/22 Genset Equipment Installation 07/05
134 FSY Readiness Commissioning 13 days Thu 23/06/22 Tue 05/07/22 FSY Readiness Commissioning
135 ESB and Electrical Commisioning 1 day Thu 23/06/22 Fri 24/06/22 ESB and Electrical Commisioning 23/06
136 Virgin delivery 1 day Sat 25/06/22 Sun 26/06/22 Virgin delivery 25/06
137 Circullation 2 days Sun 26/06/22 Tue 28/06/22 Circullation 26/06
138 Terra 1 day Tue 28/06/22 Wed 29/06/22 Terra 28/06
139 Dry run 1 day Wed 29/06/22 Thu 30/06/22 Dry run 29/06
140 Pre COI 1 day Thu 30/06/22 Fri 01/07/22 Pre COI 30/06
141 COI 1 day Tue 05/07/22 Tue 05/07/22 COI 05/07
142 Landscaping 7 days Fri 01/07/22 Thu 07/07/22 Landscaping 01/07
143 General Cleaning 1 day Fri 08/07/22 Fri 08/07/22 General Cleaning 08/07
144 E2E Process‐Handover 4 days Wed 06/07/22 Sat 09/07/22 E2E Process-Handover
145 Equipment register submission to APR 3 days Wed 06/07/22 Fri 08/07/22 Equipment register submission to APR 06/07
146 Pre‐Handover 1 day Fri 08/07/22 Fri 08/07/22 Pre-Handover 08/07
147 Traininng to blueteam 1 day Fri 08/07/22 Fri 08/07/22 Traininng to blueteam 08/07
148 Handover 1 day Sat 09/07/22 Sat 09/07/22

Task Summary Inactive Task Duration-only Finish-only Critical Baseline Summary

Split Project Summary Inactive Milestone Manual Summary Rollup External Tasks Critical Split Progress

Milestone Rolled Up Critical Inactive Summary Manual Summary External Milestone Baseline

Slippage Rolled Up Critical Split Manual Task Start-only Deadline Baseline Milestone