ID Task Name Start Finish 22 03 Apr '22 10 Apr '22 17 Apr '22 24 Apr '22 01 May '22 08 May

Apr '22 24 Apr '22 01 May '22 08 May '22 15 May '22 22 May '22 29 May '22 05 Jun '22 12 Jun '22 19 Jun '22 26 Jun '22 03 Jul '22 10 Jul '22 17 Jul '22 24 Jul '22 31 Jul '22 07 Aug '22 14 Aug '22 21 Aug '22 28 Aug '22 04 Sep '22 11 Sep '22 18 Sep '22 25 Sep '22 02 Oct '22 09 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22 06 Nov '22 1
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
1 Go Production ‐ 2023 01/04/22 10/11/22

2 Kick Of Meeting 19/04/22 19/04/22

3 Step 1 ‐ Manufacture Documentation 02/05/22 31/08/22

4 Standarization  02/05/22 01/06/22

5 Reference for Glass 02/05/22 01/06/22

6 Survey for Material 02/05/22 01/06/22

7 Data and Specification 30/05/22 12/07/22

8 CAD Design 30/05/22 14/06/22

9 Datasheet 01/07/22 12/07/22

10 Technical Calculation 13/07/22 01/08/22

11 Pressure Calculation 13/07/22 15/07/22

12 Glass Calculation 18/07/22 20/07/22

13 Body Design 21/07/22 22/07/22

14 Human Resource Calculation 25/07/22 27/07/22

15 Machining Cost 28/07/22 29/07/22

16 Tools Development Cost 28/07/22 29/07/22

17 Bereakdown Cost 01/08/22 01/08/22

18 Sales & Marketing 12/07/22 15/07/22

19 Resuming for Selling of Last Year 12/07/22 15/07/22

20 Listing Customer 16/06/22 12/07/22

21 Catalog for Sight Glass 27/05/22 16/06/22

22 Outline Project and Procedure  18/07/22 29/07/22

23 Production Procedure 18/07/22 29/07/22

24 Machining Procedure 18/07/22 29/07/22

25 Tagging Procedure 18/07/22 29/07/22

26 Safety Production Procedure 18/07/22 29/07/22

27 Testing Procedure 18/07/22 29/07/22

28 Template format 18/07/22 29/07/22

29 Step 2 ‐ Trial of Creating 07/06/22 21/09/22

30 Circular Flange Sight Glass 07/06/22 07/06/22 07/06

31 Wafer Sight Glass 02/08/22 10/08/22

32 Sight Glass Double Window 01/09/22 21/09/22

33 Step 3 General Calculation 01/08/22 17/08/22

34 Production Cost 01/08/22 03/08/22

35 Machining and Development tool co 04/08/22 09/08/22

36 Marketing Cost 10/08/22 12/08/22

37 Profit Calculation 15/08/22 17/08/22

38 Step 4 ‐ Evaluation and Presentation 27/05/22 22/09/22 22/09

39 Evaluation 27/05/22 22/09/22 22/09

40 Evaluation Production 1 27/05/22 27/05/22 27/05

41 Evaluation Production 2 07/06/22 07/06/22 07/06

42 Evaluation Production 3 12/07/22 12/07/22 12/07

43 Evaluation Production 4 19/08/22 19/08/22 19/08

44 Evaluation Production 5 22/09/22 22/09/22 22/09

45 Presentation to Bueno Indoensia 22/08/22 22/08/22 22/08

46 Sales Side 22/08/22 22/08/22 22/08

47 Enginering Side 22/08/22 22/08/22 22/08

48 Logistic and Purcashing Side 22/08/22 22/08/22 22/08

49 Marketing Side 22/08/22 22/08/22 22/08

50 Step 5 ‐ Launching and Selling 03/10/22 14/10/22

51 Marketing Strategic 03/10/22 14/10/22

52 Offering New Customer 03/10/22 07/10/22

53 Following Old Customer 10/10/22 14/10/22

54 Telemarketing 10/10/22 14/10/22

Project: Bueno Indonesia - Go Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress

Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Date: 08/07/22