Monthly Progress Report

PT. SMELTING – GRESIK


NEW SULPHURIC ACID PLANT 1,350 TPD
09. 2022

VENDOR: BUENO TECHNOLOGY INDONESIA

Equipment Name: PTFE LINING PIPES, FITTINGS


Delivery date:

a. Contractual delivery date: Dec 2022, FCA Project Site

b. Current forecasted delivery date: Dec 2022, FCA Project Site

Engineering status: 20%

Procurement status: 11%

Production status: 18%

Test & Inspection status: 0%

Package & Transport status: 0%

Description and photos of progress completed during this reported period:

a. Engineering: Bill of Material is completed 27%.

b. Material Procurement:

Major components

- Under Progressing production fitting


- ready to process production (spool)
- some item has hold to lining, waiting for dimension approve from IKPT’s Licensors
- PTFE Lining parallel from approved fitting and spool
c. Material Delivery:

The delivery will be slippage cause there some changes pipe length. Estimated on 21 Dec 2022

d. Fabrication:

- Start production on 01 Aug 2022 for (PTFE Lining Spool)


- Most of the items are still waiting for approval, the rest are already in production. there is a
spool that has been produced but the lining process is still waiting for approval because
there is a change in length
- Fitting and other product will be produce after revised drawing approved
- On 15 August 2022, we have returned GA Drawing with document number 4EXP-V-500-
139-01-003 Revision 2. Those are some hold item to produce and changed dimension. We
need to extend time for following the comment within manufacturing

e. Inspection & testing:

- Will be process after Production step finished for all

f. Painting & Final Packaging:

Outstanding issues:

a. Waiting more drawing revision approval


b. Fitting and another component waiting approval to started production
c. The manufacture is under produce Pipe Spool
d. The spool production process was delayed for several days while waiting for approval for the
spool length. Some of the spools that have been approved will be processed further. For spools
that have previously been approved but there are long changes, they will be implemented
immediately but require additional time.
e. The fitting production is under progressing
f. Half quantity of the spool has been lined

Planned activities for the next month:

a. Engineering: Ensure product dimension and inspect welding process

b. Material Procurement: -

c. Material Delivery: -
d. Fabrication: Production process and parallel by drawing revision review and approvals
DESCRIPTION / PICTURES START AND FINISH
Material ready to
production process
29/07/2022

Spool Material
Material ready to
production process
29/07/2022

Flange Material
On Hold Lining
Process and waiting
some fix length
05/08/2022

Spool–
Fitting Producing
90° Elbow and Tee
15/09/2022

Spool Pipe
Prepared for liing
process
27/09/2022
e. Inspection & testing:

- Inspection and testing will be start after production phase finished

f. Painting & Final Packaging: -


ID Task Name Duration Start Finish % Complete Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12
1 IKPT ‐ New Sulfuric Acid Plant 1.350 TPD Pro116 days 13/07/22 21/12/22 33%
2 Pre Production 5 days 05/07/22 11/07/22 67%
3 Technical Approval 5 days 05/07/22 11/07/22 35% Engineering

4 Technical Datasheet 5 days 05/07/22 11/07/22 90% Engineering

5 Approval Drawing 5 days 05/07/22 11/07/22 75% Engineering

6 Inventory Management 3 days 11/07/22 13/07/22 45%


7 Inventory Process Non Stock 1 day 11/07/22 11/07/22 45% Manufacturing;Purchasing

8 Incomming Material 1 day 12/07/22 12/07/22 45% Manufacturing;Purchasing

9 Inspection Material & Dimension 1 day 13/07/22 13/07/22 45% 13/07

10 Production Process 78 days 13/07/22 28/10/22 11%


11 Pipe & Fitting Production 78 days 13/07/22 28/10/22 19%
12 Pipe Production Process 10 days 13/07/22 26/07/22 25% Manufacturing

13 Fitting Production Process 10 days 21/07/22 03/08/22 20% Manufacturing

14 PTFE Solid Material Production Process 10 days 27/07/22 09/08/22 15% Manufacturing

15 Surface & Visual Inspection 4 days 10/08/22 15/08/22 15% 15/08

16 Lining Process 10 days 16/08/22 29/08/22 4%


17 Material Processing 4 days 16/08/22 19/08/22 5% Manufacturing

18 Measure Length, Dia Inner and Outer 3 days 18/08/22 22/08/22 5% Manufacturing

19 Mold Making Process 3 days 23/08/22 25/08/22 3% Manufacturing

20 Mold Filling 3 days 24/08/22 26/08/22 3% Manufacturing

21 Finishing 2 days 27/08/22 29/08/22 1% 29/08

22 Inspection & Testing 7 days 30/08/22 07/09/22 0%


23 Hydro Pressure Test 2 days 30/08/22 31/08/22 0% Manufacturing;Quality Control

24 Positive Material Identification 2 days 31/08/22 01/09/22 0% Manufacturing;Quality Control

25 Spark Test 2 days 01/09/22 02/09/22 0% Manufacturing;Quality Control

26 Penetrant Test 2 days 02/09/22 05/09/22 0% Manufacturing;Quality Control

27 Temperature Test 2 days 06/09/22 07/09/22 0% Manufacturing;Quality Control

28 Finishing and Final Inspection 4 days 08/09/22 13/09/22 0%


29 Cleaning Surface Preparation 2 days 08/09/22 09/09/22 0% Manufacturing;Quality Control

30 Checking Quantity & Final Inspection 2 days 08/09/22 09/09/22 0% 09/09

31 Packing Process 2 days 08/09/22 09/09/22 0% Manufacturing;Quality Control

32 Estimated Delivery to Port 3 days 09/09/22 13/09/22 0% Forwarder Service;Manufacturing

33 Prevaration & Shipping 17 days 30/10/22 21/11/22 0%


34 Estimated Arrived Jakarta 17 days 30/10/22 21/11/22 0% Forwarder Service

35 Clearance Shipping 5 days 22/11/22 28/11/22 0%


36 Customs Duty 5 days 22/11/22 28/11/22 0% Externals Resource

37 Fabrication Acceptance 10 days 29/11/22 12/12/22 0%


38 Visual & Dimension Check 1 day 29/11/22 29/11/22 0% Warehouse;Quality Control;Engineering

39 Document Check 1 day 30/11/22 30/11/22 0% Warehouse;Quality Control;Engineering

40 Pressure Test On Bueno Indonesia WS 2 days 01/12/22 02/12/22 0% 02/12

41 Preparation Product 2 days 05/12/22 06/12/22 0% Warehouse;Logistic

42 Packing and Marking 2 days 07/12/22 08/12/22 0% Warehouse;Logistic

43 Input Delivery Document 1 day 09/12/22 09/12/22 0% Warehouse;Logistic

44 Scheduling to Delivery 1 day 12/12/22 12/12/22 0% Warehouse;Logistic

45 Delivery Process 7 days 13/12/22 21/12/22 0%


46 Delivery to Site 7 days 13/12/22 21/12/22 0% Warehouse;Logistic

Task Project Summary Manual Task Start-only Deadline Progress


Project: IKPT - New Sulpuric Ac Split Inactive Task Duration-only Finish-only Baseline Manual Progress
Date: 30/09/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Baseline Milestone Slippage

Summary Inactive Summary Manual Summary External Milestone Baseline Summary

Page 1
CLIENT IKPT
DATE PRINT 29/09/2022
PERIODE 29‐Sep‐22

DESCRIPTION AUGUST SEPTEMBER


Task Name DurationStart Finish 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
   Technical Approval 5 05/07/2022 11/07/2022 90,0
   Technical Datasheet 5 05/07/2022 11/07/2022
   Approval Drawing 5 05/07/2022 11/07/2022
   Inventory Process Non Stock 1 11/07/2022 11/07/2022
80,0
   Incomming Material 1 12/07/2022 12/07/2022
   Inspection Material & Dimension 1 13/07/2022 13/07/2022
      Pipe Production Process 10 13/07/2022 26/07/2022
      Fitting Production Process 10 21/07/2022 03/08/2022 70,0

      PTFE Solid Material Production Process 10 27/07/2022 09/08/2022


      Surface & Visual Inspection 4 10/08/2022 15/08/2022
      Material Processing 4 16/08/2022 19/08/2022 60,0
      Measure Length, Dia Inner and Outer 3 18/08/2022 22/08/2022
      Mold Making Process 3 23/08/2022 25/08/2022
      Mold Filling 3 24/08/2022 26/08/2022
50,0
      Finishing 2 27/08/2022 29/08/2022 0,83
      Hydro Pressure Test 2 30/08/2022 31/08/2022 0,83 0,83
      Positive Material Identification 2 31/08/2022 01/09/2022 0,83 0,83
      Spark Test 2 01/09/2022 02/09/2022 40,0 0,83 0,83
      Penetrant Test 2 02/09/2022 05/09/2022 0,83 0,83
      Temperature Test 2 06/09/2022 07/09/2022 0,83 0,83
      Cleaning Surface Preparation 2 08/09/2022 09/09/2022 30,0
0,83 0,83
      Checking Quantity & Final Inspection 2 08/09/2022 09/09/2022 0,83 0,83
      Packing Process 2 08/09/2022 09/09/2022 0,83 0,83
      Estimated Delivery to Port 3 09/09/2022 13/09/2022 0,83 0,83 0,83
20,0
   Estimated Arrived Jakarta 17 13/09/2022 05/10/2022 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83 0,83
   Customs Duty 5 05/10/2022 11/10/2022
   Visual & Dimension Check 1 11/10/2022 11/10/2022
   Document Check 1 11/10/2022 11/10/2022 10,0

   Pressure Test On Bueno Indonesia WS 2 12/10/2022 13/10/2022


   Preparation Product 2 14/10/2022 17/10/2022
   Packing and Marking 2 15/10/2022 17/10/2022 0,0
   Input Delivery Document 1 16/10/2022 16/10/2022 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

   Scheduling to Delivery 1 17/10/2022 17/10/2022 Plan Actual

   Delivery to Site 3 18/10/2022 20/10/2022

PLAN 0,00 0,83 0,83 1,65 1,65 1,65 0,00 0,00 0,83 0,83 0,83 2,48 3,31 0,00 0,00 0,83 1,65 0,83 0,83 0,83 0,00 0,00 0,83 0,83 0,83 0,83 0,83 0,00 0,00 0,83 0,83 0,83 0,83 0,83
ACCUMULATION 54,5 55,4 56,2 57,9 59,5 61,2 61,2 61,2 62,0 62,8 63,6 66,1 69,4 69,4 69,4 70,2 71,9 72,7 73,6 74,4 74,4 74,4 75,2 76,0 76,9 77,7 78,5 78,5 78,5 79,3 80,2 81,0 81,8 82,6

ACTUAL 0,2 0,2 0,2 0,2 0,2 0,2 0,3 0,3 0,3 0,5 0,5 0,3 0,5 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1 0,1
ACCUMULATION 44,9 45,1 45,3 45,5 45,7 45,9 45,9 45,9 46,2 46,5 46,8 47,3 47,8 47,8 47,8 48,1 48,6 48,7 48,8 48,9 48,9 48,9 49,0 49,1 49,2 49,3 49,4 49,4 49,4 49,5 49,6 49,7 49,8

* the date is posible to change according manufacturing process and approval the dimension
* the actual is lower than planned because some of the items are retained both
in dimensions and in the lining process. this is because it is still waiting
for approval from the licensor