Name Assigned to Start Finish % Complete

1 Investigation 10/18/2022 11/15/2022 0

2 Hot oil PID development 10/18/2022 11/15/2022 0

3 Temperature survey 10/18/2022 10/24/2022 0

4 Pressure survey 10/18/2022 10/24/2022 0

5 Report 10/18/2022 10/24/2022 0

6 Process PID updates 10/18/2022 11/11/2022 0

7 Engineering 10/25/2022 2/16/2023 0

8 Disucss poject with engineering contractor 10/26/2022 10/26/2022 100

9 Field Visit 10/25/2022 10/25/2022 0

10 Review documents 10/26/2022 11/2/2022 0

11 Determine heat trace options 11/3/2022 11/9/2022 0

12 Priority Updates 11/2/2022 2/16/2023 0

13 G to H tank 11/10/2022 12/29/2022 0

14 Piping 11/10/2022 12/29/2022 0

15 Isometric 11/10/2022 11/28/2022 0

16 Fabrication 11/29/2022 12/12/2022 0

17 Installation 12/13/2022 12/29/2022 0

18 4" Siefer Mill 11/2/2022 11/23/2022 0

19 Mill Insulation 11/2/2022 11/23/2022 0

20 Insulation design 11/2/2022 11/8/2022 0

21 Insulation procurement 11/9/2022 11/22/2022 0

22 Insulation installation 11/23/2022 11/23/2022 0

23 Piping 0

24 Isometric 0

25 Fabrication 0

Exported from Microsoft Project on 10/18/2022 Page 1 of 6


Simple Project
Name

1 Investigation

2 Hot oil PID development

3 Temperature survey

4 Pressure survey

5 Report

6 Process PID updates

7 Engineering

8 Disucss poject with engineering contractor

9 Field Visit

10 Review documents

11 Determine heat trace options

12 Priority Updates

13 G to H tank

14 Piping

15 Isometric

16 Fabrication

17 Installation

18 4" Siefer Mill

19 Mill Insulation

20 Insulation design

21 Insulation procurement

22 Insulation installation

23 Piping

24 Isometric

25 Fabrication

Exported from Microsoft Project on 10/18/2022 Page 2 of 6


Simple Project
Name Assigned to Start Finish % Complete

26 Installation 0

27 Asphalt Loading 11/2/2022 12/26/2022 0

28 Pump Insulation 11/2/2022 12/26/2022 0

29 Insulation design 11/2/2022 11/4/2022 0

30 Insulation procurement 11/7/2022 11/25/2022 0

31 Insulation installation 11/28/2022 11/28/2022 0

32 Piping 11/14/2022 12/26/2022 0

33 Isometric 11/14/2022 11/25/2022 0

34 Fabrication 11/28/2022 12/16/2022 0

35 Installation 12/23/2022 12/26/2022 0

36 Line 1 Impregnation Tank 11/2/2022 1/13/2023 0

37 Pump Insulation 11/2/2022 11/23/2022 0

38 Insulation design 11/2/2022 11/8/2022 0

39 Insulation procurement 11/9/2022 11/22/2022 0

40 Insulation installation 11/23/2022 11/23/2022 0

41 Piping 11/28/2022 1/13/2023 0

42 Isometric 11/28/2022 12/16/2022 0

43 Fabrication 12/19/2022 1/6/2023 0

44 Installation 1/9/2023 1/13/2023 0

45 Line 1 Coating Section 2 11/29/2022 1/27/2023 0

46 Pump Insulation 11/29/2022 1/27/2023 0

47 Insulation design 11/29/2022 12/5/2022 0

48 Insulation procurement 12/6/2022 12/19/2022 0

49 Insulation installation 12/20/2022 12/20/2022 0

50 Piping 12/19/2022 1/27/2023 0

Exported from Microsoft Project on 10/18/2022 Page 3 of 6


Simple Project
Name

26 Installation

27 Asphalt Loading

28 Pump Insulation

29 Insulation design

30 Insulation procurement

31 Insulation installation

32 Piping

33 Isometric

34 Fabrication

35 Installation

36 Line 1 Impregnation Tank

37 Pump Insulation

38 Insulation design

39 Insulation procurement

40 Insulation installation

41 Piping

42 Isometric

43 Fabrication

44 Installation

45 Line 1 Coating Section 2

46 Pump Insulation

47 Insulation design

48 Insulation procurement

49 Insulation installation

50 Piping

Exported from Microsoft Project on 10/18/2022 Page 4 of 6


Simple Project
Name Assigned to Start Finish % Complete

51 Isometric 12/19/2022 1/6/2023 0

52 Fabrication 1/9/2023 1/20/2023 0

53 Installation 1/23/2023 1/27/2023 0

54 Line 1 Coating Section 1 1/9/2023 2/16/2023 0

55 Insulation 1/9/2023 2/16/2023 0

56 Insulation design 0

57 Insulation procurement 0

58 Insulation installation 0

59 Piping 1/9/2023 2/16/2023 0

60 Isometric 1/9/2023 1/27/2023 0

61 Fabrication 1/30/2023 2/10/2023 0

62 Installation 2/13/2023 2/16/2023 0

Exported from Microsoft Project on 10/18/2022 Page 5 of 6


Simple Project
Name

51 Isometric

52 Fabrication

53 Installation

54 Line 1 Coating Section 1

55 Insulation

56 Insulation design

57 Insulation procurement

58 Insulation installation

59 Piping

60 Isometric

61 Fabrication

62 Installation

Exported from Microsoft Project on 10/18/2022 Page 6 of 6