Culture Documents
2 Phase-2
Excavation 8/25/2022 9/5/2022 11days
Structure 9/6/2022 9/30/2022 24days
PCC 9/6/2022 9/10/2022 4days
Footings 9/10/2022 9/17/2022 7days
Columns & RT Wall upto Roof slab 9/17/2022 9/30/2022 13days
7 Finshing Works
A) GF Masonry 11/11/2022 11/21/2022 10days
B) GF Plastering 11/30/2022 12/10/2022 10days
C) FF Masonry 12/6/2022 12/16/2022 10days
D) FF Plastering 12/26/2022 1/5/2023 10days
E) SF Masonry 12/30/2022 1/10/2023 11days
F) SF Plastering 1/20/2023 1/30/2023 10days
11 External Works
A) Equipment Foundation 10/15/2022 11/15/2022 31days
B) UG Sump 11/1/2022 11/30/2022 29days
C) Trenches 11/1/2022 12/15/2022 44days
D) Road 11/15/2022 1/1/2023 47days
E) Compound Wall 12/17/2022 1/2/2023 16days
F) Gates 1/13/2023 1/28/2023 15days
Note: 1. schedule given on the assumption of clearance will be given for 2/3rd of foudation work on 25/08/2022
2.Clarance & Drawings to be give on time in advance for activities.
3. Please inform any Sequnce of work missed like, Plinth beam, trenches in the basement floor.