ID Task Task Name Duration Start Finish Predecessors Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023

Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 Pekerjaan Pondasi 30 days 16 June 2022 22 July 2022
2 Galian Pondasi 12 days 16 June 2022 30 June 2022
3 Urugan pasir bawah 0,25 days 30 June 2022 30 June 2022 2
pondasi
4 Pasangan batu kosong1 day 30 June 2022 01 July 2022 3SS
5 Pasangan batu 14 days 30 June 2022 18 July 2022 4SS
gunung/kali
6 Timbunan 1/2 galian 3 days 19 July 2022 22 July 2022 5
7 Pekerjaan Sloof & Kolom23 days 24 June 2022 22 July 2022
8 Pasang besi sloof dan 7 days 14 July 2022 22 July 2022 6FF
kolom
9 Pasang bekisting sloof 7 days 24 June 2022 02 July 2022 8

10 Pengecoran sloof 7 days 24 June 2022 02 July 2022 9FF


11 Pasang Pipa Drainase 2 days 02 July 2022 05 July 2022 10
Dan KM
12 Timbunan & Urugan 14 days 05 July 2022 22 July 2022 11
Lantai
13 Pekerjaan Dinding 31 days 22 July 2022 31 August 2022
14 Pasangan dinding 1/2 24 days 22 July 2022 23 August 12
bata 2022
15 Pasang bekisking 7 days 23 August 31 August 14
kolom 2022 2022
16 Pengecoran kolom 3 days 27 August 202231 August 202215FF

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: ZAKHARIA BILLADEN P
Summary Manual Summary Rollup Critical
Date: 23 May 2022
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
17 Pekerjaan Dinding 25 days 13 August 13 September
(lanjutan) 2022 2022
18 Plesteran 14 days 13 August 202231 August 202216FF
19 Plesteran trastam 1 day 12 September 2022
13 September 2022
18
20 Pekerjaan Kusen Pintu 14 days 13 September 29 September
Dan Jendela 2022 2022
21 Pasang kusen pintu 7 days 13 September 2022
21 September 2022
19
22 Pasang kusen jendela 7 days 21 September 2022
29 September 2022
21
23 Pekerjaan Ringbalk 10 days 21 September 2022
03 October 2022
24 Pasang besi ringbalk 7 days 21 September 2022
29 September 2022
22
25 Pasang bekisting 3 days 29 September 03 October 24
ringbalk 2022 2022
26 Pengejoran ringbalk 2 days 01 October 202203 October 202225FF
27 Pekerjaan Kuda-Kuda 26 days 06 October 07 November
dan Atap 2022 2022
28 Pasang bata 4 days 06 October 12 October 26
bubungan 2022 2022
(gunung-gunung)
29 Pasang besi 3 days 12 October 15 October 28
bubungan 2022 2022
30 Pengecoran 3 days 15 October 19 October 29
bubungan 2022 2022

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: ZAKHARIA BILLADEN P
Summary Manual Summary Rollup Critical
Date: 23 May 2022
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 2
ID Task Task Name Duration Start Finish Predecessors Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
31 Pasang rangka 12 days 15 October 29 October 30
kuda-kuda dan 2022 2022
rangka atap
32 Pasang penutup atap 7 days 29 October 202207 November 2022
31
33 Pekerjaan Plafon 14 days 07 November 2022
23 November 2022
34 Pasang rangka plafon 7 days 07 November 2022
15 November 2022
32
35 Pasang penutup 7 days 15 November 23 November 34
plafon 2022 2022
36 Pekerjaan listplank 3 days 15 November 2022
18 November 2022
35
37 Pekerjaan Mekanikal 7 days 18 November 26 November
dan Elektrikal 2022 2022
38 Pasang Kabel 7 days 18 November 2022
26 November 2022
36
39 Pasang saklar dan 3 days 23 November 26 November 38FF
fitting 2022 2022
40 Pekerjaan Lantai dan 18 days 01 December 22 December
Keramik 2022 2022
41 Pemasangan kloset 1 day 01 December 01 December 39
KM 2022 2022
42 Pemasangan keramik 14 days 02 December 19 December 41
lantai 2022 2022
43 Pemasangan keramik 3 days 02 December 06 December 42SS
dinding KM 2022 2022
44 Pemasangan kran air 1 day 21 December 2022
22 December 2022
43
45 Pekerjaan Finishing 26 days 22 December 2022
21 January 2023

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: ZAKHARIA BILLADEN P
Summary Manual Summary Rollup Critical
Date: 23 May 2022
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 3
ID Task Task Name Duration Start Finish Predecessors Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
46 Pekerjaan acian 12 days 22 December 05 January 44
dinding 2022 2023
47 Pasang pintu dan 2 days 22 December 24 December 46SS
jendela 2022 2022
48 Pekerjaan 14 days 05 January 21 January 47SS
pengecetan 2023 2023

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: ZAKHARIA BILLADEN P
Summary Manual Summary Rollup Critical
Date: 23 May 2022
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress