Date BH Drilling Total Depth, m BH Drilling

18/07/2022 3 12 12 - -
19/07/2022 3 8 20 - -
20/07/2022 3 5 25 - -
21/07/2022 3 4 29 - -
22/07/2022 Friday
23/07/2022 3 4 33 - -
24/07/2022 3 3 36 - -
25/07/2022 3 4 40 - -
26/07/2022 4 10 10 - -
27/07/2022 4 11 21 - -
28/07/2022 4 5 26 - -
29/07/2022 Friday
30/07/2022 Islamic New Year Holiday
31/07/2022 4 4 30 2 10
1/8/2022 - - - 2 10
2/8/2022 1 12.5 12.5 2 4
3/8/2022 1 8 20.5 2 6
4/8/2022 1 8 28.5 5 10.5
5/8/2022 Friday

NOTE:
1- Second rig was deployed on the request of client to speed up the work as underlying strata is hard

2- On 01/08/2022 just one rig was working as second rig was stoped and was waiting for client to verify
the depth
3- Borehole-3 was finished on 25/07/2022
4- Borehole-4 was finished on 31/07/2022
5- Borehole-2 was finished on 03/08/2022
6- We are working on Borehole-1 & Borehole-5
7- The future progress will depend on underlying strata
Total Depth, m
-
-
-
-

-
-
-
-
-
-

day
10
20
24
30
10.5

as underlying strata is hard

was waiting for client to verify