You are on page 1of 1

Shapoorji Pallonji & Co. Pvt.

Ltd
Lift Shaft Handing Over (Tower A & B)
Date: 04-Aug-2022

Lift Schedule Tower -A Tower -B


Sr. No Work Activities Fire lift Stretcher Lift Passenger Lift- 1 Passenger Lift- 2 Fire lift Stretcher Lift Passenger Lift- 1 Passenger Lift- 2

Completed till
1 RSP/ Scaffolding Installation Completed till Typ-27th 08-08-2022 12-08-2022 16-08-2022 10-08-2022 25-08-2022 01-09-2022
Typ-27th
2 Template Fixing Completed 13-08-2022 15-08-2022 21-08-2022 Completed 15-08-2022 30-08-2022 05-09-2022

3 Grinding 05-08-2022 20-08-2022 22-08-2022 10-09-2022 03-08-2022 20-08-2022 03-09-2022 10-09-2022

4 Cleaning 06-08-2022 22-08-2022 24-08-2022 12-09-2022 06-08-2022 22-08-2022 06-09-2022 12-09-2022

5 Tie rod Hole filling/Repairing 12-08-2022 24-08-2022 28-08-2022 15-09-2022 12-08-2022 24-08-2022 10-09-2022 15-09-2022

6 Block Work 19-08-2022 24-08-2022 01-09-2022 17-09-2022 19-08-2022 24-08-2022 10-09-2022 17-09-2022

7 Plastering 27-08-2022 30-08-2022 08-09-2022 25-09-2022 25-08-2022 30-08-2022 16-09-2022 25-09-2022

8 White wash 10-09-2022 15-09-2022 20-09-2022 30-09-2022 10-09-2022 16-09-2022 26-09-2022 30-09-2022