Project Planning Chart

Milestone Start Date End Date Day Count


Work order Recivied Monday, August 22, 2022 Monday, August 22, 2022 1
Project Start Thursday, September 15, 2022 Thursday, September 15, 2022 24
Pullout Test of Steel Track Friday, September 16, 2022 Tuesday, September 20, 2022 29
Grinding & Buffing of Existing track Friday, September 16, 2022 Monday, September 26, 2022 35
Coating of track with Zinc Rich Paint Tuesday, September 27, 2022 Friday, September 30, 2022 39
Manufacturing of New BMU Machine Monday, August 22, 2022 Friday, November 4, 2022 74
Supply Of New BMU Saturday, November 5, 2022 Saturday, November 5, 2022 75
Lifting Of BMU Sub Part (Small) with help of Service Lift Monday, November 7, 2022 Monday, November 7, 2022 77
Lifting Of BMU Sub Part with Existing BMU Tuesday, November 8, 2022 Wednesday, November 9, 2022 79
Assembly of New BMU Base & Spacer Thursday, November 10, 2022 Thursday, November 10, 2022 80
Assembly of New BMU Jib & Electric Trolley Friday, November 11, 2022 Saturday, November 12, 2022 82
Handover System to Client Monday, November 14, 2022 Monday, November 14, 2022 84
Dismantle of old BMU from Terrace to Scrap Yard Saturday, November 12, 2022 Monday, November 14, 2022 84
DAY & DATE COUNT

84 84
82
79 80
77
74 75
Day Count

39
35

29
24

Monday, Thursday, Tuesday, Monday, Friday, Friday, Saturday, Monday, Wednesday, Thursday, Saturday, Monday, Monday,
August 22, September September September September November 4, November 5, November 7, November 9, November November November November
2022 15, 2022 20, 2022 26, 2022 30, 2022 2022 2022 2022 2022 10, 2022 12, 2022 14, 2022 14, 2022
Monday, Thursday, Friday, Friday, Tuesday, Monday, Saturday, Monday, Tuesday, Thursday, Friday, Monday, Saturday,
August 22, September September September September August 22, November 5, November 7, November 8, November November November November
2022 15, 2022 16, 2022 16, 2022 27, 2022 2022 2022 2022 2022 10, 2022 11, 2022 14, 2022 12, 2022
Work order Project Start Pullout Test Grinding & Coating of Manufacturi Supply Of Lifting Of Lifting Of Assembly of Assembly of Handover Dismantle of
Recivied of Steel Track Buffing of track with ng of New New BMU BMU Sub BMU Sub New BMU New BMU Jib System to old BMU
Existing track Zinc Rich BMU Part (Small) Part with Base & & Electric Client from Terrace
Paint Machine with help of Existing BMU Spacer Trolley to Scrap Yard
Service Lift
Day Count 1 24 29 35 39 74 75 77 79 80 82 84 84