Project: Spinning Unit CONSTRUCTION WORK SCHEDULE

Client: Zaman Textile Mills FOR


Consultant: A.A. Associates
ZAMAN TEXTILE MILLS, SPINNING UNIT, KOTRI
Contractor: Shahab & Co.
PHASE -iii EB-4 GROUND FLOOR GRID 26 - 33 / A - F (AREA 36432 Sft)

ID Task Name Duration Start Finish Qtr 3, 2022 Qtr 4, 2022


Jul Aug Sep Oct Nov Dec
1 GRID 26 ~ 33 / A ~ F 141 days Sat 23-07-22 Sat 10-12-22 23-07 10-12

2 STRUCTURE WORKS 31 days Sat 23-07-22 Mon 22-08-22

13 Slab Concrete (Grid 30 ~ 33 / A - D) Area 15614 sft 98 days Sun 04-09-22 Sat 10-12-22

14 Drop Beam Buttum + Steel 8 days Mon 12-09-22 Mon 19-09-22

15 Drop Beam Formwork 6 days Tue 20-09-22 Sun 25-09-22

16 Drop Beam Concrete 5 days Mon 26-09-22 Fri 30-09-22

17 Slab formwork 8 days Sat 01-10-22 Sat 08-10-22

18 Slab Steel 5 days Sun 09-10-22 Thu 13-10-22

19 Slab Concrete 1 day Sat 15-10-22 Sat 15-10-22

20 Removing of Formwork 2 days Sun 23-10-22 Mon 24-10-22

21 Flooring work 18 days Mon 24-10-22 Thu 10-11-22

22 Earthfilling 7 days Mon 24-10-22 Sun 30-10-22

23 Hardcore 14 days Wed 26-10-22 Tue 08-11-22

24 Lean Underfloor 2 days Wed 09-11-22 Thu 10-11-22

25 FINISHING WORKS 98 days Sun 04-09-22 Sat 10-12-22

26 Block Masonry 80 days Wed 07-09-22 Fri 25-11-22

27 Plaster 82 days Sat 10-09-22 Wed 30-11-22

1/2

Note: This Schedule is subject to timely provision of materials & finalization of Drawings / details.
Project: Spinning Unit CONSTRUCTION WORK SCHEDULE
Client: Zaman Textile Mills FOR
Consultant: A.A. Associates
ZAMAN TEXTILE MILLS, SPINNING UNIT, KOTRI
Contractor: Shahab & Co.
PHASE -iii EB-4 GROUND FLOOR GRID 26 - 33 / A - F (AREA 36432 Sft)

ID Task Name Duration Start Finish Qtr 3, 2022 Qtr 4, 2022


Jul Aug Sep Oct Nov Dec
28 Grano floor 83 days Sun 04-09-22 Fri 25-11-22

29 Floor Griding 66 days Sat 01-10-22 Mon 05-12-22

30 Paint 87 days Thu 15-09-22 Sat 10-12-22

31 Mazznine Floor Slab 18 days Tue 15-11-22 Fri 02-12-22

32 Formwork of Slab 6 days Tue 15-11-22 Sun 20-11-22

33 Steel work of slab 3 days Mon 21-11-22 Wed 23-11-22

34 Concrete work of slab 1 day Thu 24-11-22 Thu 24-11-22

35 Removing of Formwork 2 days Thu 01-12-22 Fri 02-12-22

2/2

Note: This Schedule is subject to timely provision of materials & finalization of Drawings / details.