PROJECT SCHEDULE

ROKAN TANK CLEANING & REPAIR (Contract No. SPHR00256A)


REMAINING WORK WASH TANK A CLEANING & REPAIR CGS 3 HO
ID Task Name Qty Unit Duration Start Finish 2024
Qtr 4, 2023 Qtr 1, 2024
Sep Oct Nov Dec Jan
1 WASH TANK-A CLEANING & REPAIR CGS-3 (Dia. 140 72 days Mon 18/09/23 Fri 29/12/23
FT, Hi. 24 FT)
2 Welding Roof Plate 784 Meter 15 days Mon 18/09/23 Mon 09/10/23
3 Fit-up & Welding Roof Nozzle 42 Meter 2 days Tue 10/10/23 Wed 11/10/23
4 Welding Roof Platform 2 Lot 3 days Thu 12/10/23 Mon 16/10/23
5 Modify Stairway 2 Lot 5 days Tue 17/10/23 Mon 23/10/23
6 Coating Internal Blasting-Primer "Top Shell, Rafter, 2224 M2 5 days Tue 24/10/23 Mon 30/10/23
Column"
7 Coating Internal Top Coat "Top Shell, Rafter, Column 2224 M2 2 days Tue 31/10/23 Wed 01/11/23
8 Coating Internal Blasting-Primer "Upper Shell, 1757 M2 3 days Thu 02/11/23 Mon 06/11/23
Bottom, Spreader Box"
9 Coating Internal Top Coat "Upper Shell, Bottom, 1757 M2 2 days Tue 07/11/23 Wed 08/11/23
Spreader Box"
10 Coating External Blasting-Primer "Roof & Shell" 2412 M2 7 days Thu 09/11/23 Fri 17/11/23
11 Coating External Top Coat "Roof & Shell" 2412 M2 3 days Mon 20/11/23 Wed 22/11/23
12 Install Sand Pan & Sand Jetting 72 Spool 5 days Thu 23/11/23 Wed 29/11/23
13 Install Shell Doorsheet 1 Lot 2 days Thu 30/11/23 Fri 01/12/23
14 Blasting & Coating Shell Doorsheet 1 Lot 2 days Mon 04/12/23 Tue 05/12/23
15 Filling Water Hydrotest 65860 Bbls 10 days Wed 06/12/23 Tue 19/12/23
16 Water Release 65860 Bbls 5 days Wed 20/12/23 Thu 28/12/23
17 Housekeeping & Finish 1 Lot 1 day Fri 29/12/23 Fri 29/12/23