PRELIMINARY SCHEDULE

PEKERJAAN JASA ENGINEERING PROCUREMENT CONSTRUCTION (EPC)


PEMIPAAN DARI CIPAKU KE POND J DILAPANGAN PANAS BUMI PATUHA

ID Task Name Duration Start Finish October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021
300306091215182124273002050811141720232629020508111417202326290104071013161922252831030609121518212427020508111417202326290104071013161922252801040710
1 PEKERJAAN JASA ENGINEERING PROCUREMENT 200 days 08/10/2020 25/04/2021
CONSTRUCTION (EPC) PEMIPAAN DARI CIPAKU KE POND J
DILAPANGAN PANAS BUMI PATUHA

2 CONTRACT AWARD 0 days 08/10/2020 08/10/2020 08/10

3 KICK OF MEETING 1 day 12/10/2020 12/10/2020

4 PROCUREMENT 87 days 09/11/2020 03/02/2021

5 Material On Site 49 days 09/11/2020 27/12/2020

6 Pipa 8 CS sch.40 ASTM A 53 Grade B, ERW, Length : 6m


39 days 09/11/2020 17/12/2020

7 Flange 8-300#, WN, RF, SCH.40, A105N 10 days 18/12/2020 27/12/2020

8 Spiral Wound Gasket 8 -300#, INNER & OUTER RING: SS304


10 days 18/12/2020 27/12/2020

9 Gate Valve 8 -300# CS A216 gr WCB, Flange 10 days 18/12/2020 27/12/2020

10 Stud Bolt W/2 Nut 7/8x 5-3/4, ASTM A193, Gr.B7 10 days 18/12/2020 27/12/2020

11 Sock O-let 1/2 x 8 A105 #3000 10 days 18/12/2020 27/12/2020

12 Pipe Niple 1/2 x 100mm, Sch.40, SW x NPT, A106 Gr.B 10 days 18/12/2020 27/12/2020

13 Gate Valve 1/2 -800# A105, NPT 10 days 18/12/2020 27/12/2020

14 Pressure Gauge, Range 0-40 bar, 1/2 NPT male connect


10 days 18/12/2020 27/12/2020

15 Elbow 45°, 8, BW, LR, SCH.40, A234, SMLS 10 days 18/12/2020 27/12/2020

16 Elbow 90°, 8, BW, LR, SCH.40, A234, SMLS 10 days 18/12/2020 27/12/2020

17 Material For Construction 80 days 16/11/2020 03/02/2021

18 Pipa 8 CS sch.40 ASTM A 53 Grade B, ERW, Length : 6m


59 days 16/11/2020 13/01/2021

19 Flange 8-300#, WN, RF, SCH.40, A105N 38 days 28/12/2020 03/02/2021

20 Spiral Wound Gasket 8 -300#, INNER & OUTER RING: SS304


38 days 28/12/2020 03/02/2021

21 Gate Valve 8 -300# CS A216 gr WCB, Flange 38 days 28/12/2020 03/02/2021

22 Stud Bolt W/2 Nut 7/8x 5-3/4, ASTM A193, Gr.B7 38 days 28/12/2020 03/02/2021

23 Sock O-let 1/2 x 8 A105 #3000 38 days 28/12/2020 03/02/2021

24 Pipe Niple 1/2 x 100mm, Sch.40, SW x NPT, A106 Gr.B 38 days 28/12/2020 03/02/2021

25 Gate Valve 1/2 -800# A105, NPT 38 days 28/12/2020 03/02/2021

26 Pressure Gauge, Range 0-40 bar, 1/2 NPT male connect


38 days 28/12/2020 03/02/2021

27 Elbow 45°, 8, BW, LR, SCH.40, A234, SMLS 38 days 28/12/2020 03/02/2021

28 Elbow 90°, 8, BW, LR, SCH.40, A234, SMLS 38 days 28/12/2020 03/02/2021

29 CONSTRUCTION 196 days 12/10/2020 25/04/2021

30 Mobilization Personnel & Equipment 20 days 20/10/2020 08/11/2020

31 Personnel 10 days 20/10/2020 29/10/2020

32 Equipment 10 days 30/10/2020 08/11/2020

33 Demobilization Personnel & Equipment 20 days 06/04/2021 25/04/2021

34 Personnel 20 days 06/04/2021 25/04/2021

35 Equipment 20 days 06/04/2021 25/04/2021

36 Preparation 28 days 12/10/2020 08/11/2020

37 Location Survey 1 day 12/10/2020 12/10/2020

38 Direksi Kit 10 days 20/10/2020 29/10/2020

39 ROW Survey & Preparation 10 days 30/10/2020 08/11/2020

40 Pembuatan as built drawing dan dokumentasi 142 days 05/12/2020 25/04/2021

41 Sewa truck mounted crane kapasitas minimal 8 ton. 58 days 09/11/2020 05/01/2021

42 Jasa Pengelasan Minimal 3 layer, Pipa 8” sch 40 148 days 23/11/2020 19/04/2021
(GTAW - SMAW) dan pemasangan jaringan pipa

43 Pipe Stringing 80 days 23/11/2020 10/02/2021

44 Welding Work 129 days 28/11/2020 05/04/2021

45 Road Crossing 25 days 12/03/2021 05/04/2021

46 Wrapping 25 days 12/03/2021 05/04/2021

47 Hydrotest 14 days 06/04/2021 19/04/2021

48 PROJECT COMPLETED 0 days 25/04/2021 25/04/2021 25/04

Rev-0 Task Split Milestone Summary Progress Baseline Manual Progress