FUNNEL DECK PORT SIDE STEEL RENEWALFOR FPSO KIKEH

CONTRACT REFERENCE: SO 10590-20 (FUNNEL DECK PORT SIDE STEEL RENEWAL FOR FPSO KIKEH) LOCATION : FPSO KIKEH

PROGRESS DETAIL
DAYS
NO TASK DESCRIPTION PLANNING DATE ACTUAL DATE PROGRESS REMARKS
PLAN
Weightage Actual
A FUNNEL DECK PORT SIDE STEEL RENEWAL FOR FPSO KIKEH 7/10/2021 2/24/2022 7/10/2021 1.000 67.69%
1 OFFSHORE PREPARATION 7/10/2021 8/10/2021 7/10/2021 8/12/2021 0.004 100.00%
Equipment Set-up at Site 2 days 8/9/2021 8/10/2021 8/9/2021 8/12/2021 0.004 100.00%
2 EXECUTION SCOPE PHASE 1 (FAN#1) 8/11/2021 12/8/2021 8/11/2021 0.334 100.00%
a NO 2 HORIZONTAL GIRDER AREA 8/11/2021 12/8/2021 8/11/2021 0.127 100.00%
Preparation for Hot Work Task Outside Ducting Hood 2 days 8/11/2021 8/12/2021 8/11/2021 8/13/2021 0.004 100.00% Done by Empada
Removal Mesh at Ducting Hood Outside to Eliminate Confine Space 1 days 8/13/2021 8/13/2021 8/14/2021 8/17/2021 0.002 100.00% Done by Empada

Scaffolding Erection for Working Platform Inside Ducting Hood 2 days 8/14/2021 8/15/2021 7/16/2021 8/17/2021 0.004 100.00% Done by Empada

Preparation for Hot Work Task / Lay down Ducting Ventilation Fan 1 days 8/16/2021 8/16/2021 8/11/2021 8/12/2021 0.002 100.00% Done by Empada
Cutting and Removal Existing Plate at Horizontal Girder 6 days 8/17/2021 8/22/2021 8/27/2021 9/13/2021 0.013 100.00% Done by Empada

Transfer Scrap Material From No Hor Girder 6 days 8/17/2021 8/22/2021 8/30/2021 9/14/2021 0.013 100.00% Done by Empada

Scaffolding Erection at No.2 Hor Girder Area 6 days 8/18/2021 8/23/2021 8/19/2021 8/28/2021 0.013 100.00% Done by Empada

Cutting & Removal Ducting Hood Top (Material Transfer) 3 days 8/21/2021 8/22/2021 8/18/2021 8/20/2021 0.007 100.00% Done by Empada
Cutting & Removal Ducting Hood Wall 2 days 8/21/2021 8/23/2021 8/23/2021 8/24/2021 0.004 100.00% Done by Empada
Dismantling Air Intake Cone Fan #1 Cover at No.2 Hor Girder Area 2 days 8/23/2021 8/24/2021 8/25/2021 8/26/2021 0.004 100.00% Done by Empada

Transfer Air Intake Cone Fan #1 Cover / Scrap Material From No.2
1 days 8/25/2021 8/25/2021 8/26/2021 8/27/2021 0.002 100.00% Done by Empada
Hor Girder Area
2ai Transfer Fabrication Material to No.2 Hor Girder Area 5 days 4/30/2022 5/2/2022 TBA TBA 0.011 100.00% Done by HHA
Preparation Fabrication Material For Installation 5 days 5/1/2022 5/3/2022 TBA TBA 0.011 100.00% Done by HHA
Fit-up New Angle Bar & Plate 5 days 5/2/2022 5/4/2022 TBA TBA 0.011 100.00% Done by HHA
ABS Fit-up Inspection 1 days 5/5/2022 5/5/2022 TBA TBA 0.002 100.00% Done by HHA
Welding New Frame & Plate at Hor Girder No 2 5 days 5/6/2022 5/10/2022 TBA TBA 0.011 100.00% Done by HHA
Welding Inspection & NDT 1 days TBA TBA TBA TBA 0.002 100.00% Done by HHA
Touch up Painting at No.2 Hor Girder Area 3 days TBA TBA TBA TBA 0.007 100.00% Done by HHA
Dismantling Scaffolding at Horizontal Girder 1 days TBA TBA TBA TBA 0.002 100.00% Done by HHA
b DEAERATOR FLATE AREA 8/25/2021 11/14/2021 8/26/2021 0.111 100.00%
Preparation for Hot Work Task/Lay Down Ducting Ventilation Fan 2 days 8/25/2021 8/26/2021 8/26/2021 8/26/2021 0.004 100.00% Done by Empada
Transfer Scaffolding Material & Erection at Deaerator Flat Area 2 days 8/26/2021 8/27/2021 8/26/2021 8/26/2021 0.004 100.00% Done by Empada

2bi Cutting and Removal Plate & Angle at Daerator Flat Area 7 days 8/27/2021 9/2/2021 TBA TBA 0.015 100.00% Done by HHA

Dismantling of Damper & Seating #1 at Daerator Flat Area 4 days 8/31/2021 9/3/2021 TBA TBA 0.009 100.00% Done by HHA

Transfer Scrap Material From Daerator Flat 4 days 9/1/2021 9/4/2021 TBA TBA 0.009 100.00% Done by HHA
Transfer Fabrication Material to Daerator Flat 4 days 10/20/2021 10/23/2021 TBA TBA 0.009 100.00% Done by HHA
Preparation Fabrication Material For Installation 4 days 10/21/2021 10/24/2021 TBA TBA 0.009 100.00% Done by HHA
Fit-up New Angle Bar & Plate 5 days 10/22/2021 10/26/2021 TBA TBA 0.011 100.00% Done by HHA
ABS Fit-up Inspection 1 days 10/27/2021 10/27/2021 TBA TBA 0.002 100.00% Done by HHA
Welding New Frame & Plate at Deaerator Flate Area 5 days 10/28/2021 11/1/2021 TBA TBA 0.011 100.00% Done by HHA
Welding Fan Seating & Installation Damper at Deaerator Flat Area 7 days 11/2/2021 11/8/2021 TBA TBA 0.015 100.00% Done by HHA
Welding Inspection & NDT 1 days 11/9/2021 11/9/2021 TBA TBA 0.002 100.00% Done by HHA
Touch up Painting at Deaerator Flat Area 3 days 11/10/2021 11/12/2021 TBA TBA 0.007 100.00% Done by HHA
Dismantling Scaffolding at Deaerator Flate Area 2 days 11/13/2021 11/14/2021 TBA TBA 0.004 100.00% Done by HHA
c SUPPLY FAN 1# TRUNKING 12/9/2021 1/4/2021 0.096 100.00%
Scaffolding Erection Inside Confine Space Area 3 days 12/9/2021 12/11/2021 TBA TBA 0.007 100.00% Done by HHA
Preparation for Hot Work Inside Confine Space Area 2 days 12/12/2021 12/13/2021 TBA TBA 0.004 100.00% Done by HHA
Cutting and Removal Angle Bar & Plate Inside Confined Space Area 5 days 12/14/2021 12/18/2021 TBA TBA 0.011 100.00% Done by HHA
Transfer Scrap Material From Confined Space 5 days 12/15/2021 12/19/2021 TBA TBA 0.011 100.00% Done by HHA
Transfer Fabrication Material to Confined Space 5 days 12/16/2021 12/20/2021 TBA TBA 0.011 100.00% Done by HHA
Preparation New Angle & Plate for Supply Fan 1# 5 days 12/17/2021 12/21/2021 TBA TBA 0.011 100.00% Done by HHA
Fit-up New Angle & Plate Inside Confined Space Area 5 days 12/18/2021 12/22/2021 TBA TBA 0.011 100.00% Done by HHA
ABS Fit-up Inspection 1 days 12/23/2021 12/23/2021 TBA TBA 0.002 100.00% Done by HHA
Welding New Angle & Plate Inside Confined Space Area 5 days 12/24/2021 12/28/2021 TBA TBA 0.011 100.00% Done by HHA
Welding Inspection & NDT 2 days 12/29/2021 12/30/2021 TBA TBA 0.004 100.00% Done by HHA
Touch up Painting at Confined Space Area 3 days 12/31/2021 1/2/2022 TBA TBA 0.007 100.00% Done by HHA
Dismantling Scaffolding at Confined Space 3 days 1/3/2022 1/4/2022 TBA TBA 0.007 100.00% Done by HHA
3 EXECUTION SCOPE PHASE 2 (FAN#3) 9/2/2021 2/23/2022 8/11/2021 TBA 0.317 94.83%
a NO 2 HORIZONTAL GIRDER AREA 9/2/2021 2/23/2022 11/82021 TBA 0.111 85.29%
Preparation for Hot Work Task at Horizontal Girder Fan#3 2 days 9/2/2021 9/3/2021 9/6/2021 9/6/2021 0.004 100.00% Done by Empada
Cutting and Removal Existing Plate at Horizontal Girder 6 days 9/3/2021 9/8/2021 9/6/2021 9/16/2021 0.013 100.00% Done by Empada

Transfer Scrap Material From No Hor Girder 6 days 9/4/2021 9/9/2021 9/7/2021 9/17/2021 0.013 100.00% Done by Empada
Scaffolding Erection at No.2 Hor Girder Area 6 days 9/5/2021 9/10/2021 9/4/2021 9/5/2021 0.013 100.00% Done by Empada
Cutting & Removal Ducting Hood Top (Material Transfer) 2 days 9/8/2021 9/9/2021 8/18/2021 8/20/2021 0.004 100.00% Done by Empada
Dismantling Air Intake Cone Fan #3 Cover at No.2 Hor Girder Area 2 days 9/10/2021 9/11/2021 9/6/2021 9/6/2021 0.004 100.00% Done by Empada
Transfer Air Intake Cone Fan #3 Cover / Scrap Material From No.2
1 days 9/12/2021 9/12/2021 9/7/2021 9/7/2021 0.002 100.00% Done by Empada
Hor Girder area
3ai Transfer Fabrication Material to No.2 Hor Girder Area 5 days 1/31/2022 2/4/2022 TBA TBA 0.011 100.00% Done by HHA
Preparation Fabrication Material For Installation 5 days 2/1/2022 2/5/2022 TBA TBA 0.011 100.00% Done by HHA
Fit-up New Angle Bar & Plate 5 days 2/2/2022 2/6/2022 TBA TBA 0.011 100.00% Done by HHA
ABS Fit-up Inspection 1 days 2/7/2022 2/7/2022 TBA TBA 0.002 100.00% Done by HHA
Welding New Frame & Plate at Hor Girder No 2 5 days 2/8/2022 2/12/2022 TBA 0.011 50.00%
3aii Welding Inspection & NDT 1 days 0.002
Touch up Painting at No.2 Hor Girder Area 3 days 0.007
Dismantling Scaffolding at Horizontal Girder 1 days 0.002
b DEAERATOR FLATE AREA 9/12/2021 1/30/2022 8/26/2021 TBA 0.111 100.00%
Preparation for Hot Work Task/Lay Down Ducting Ventilation Fan 2 days 9/12/2021 9/13/2021 8/26/2021 8/26/2021 0.004 100.00% Done by Empada
Transfer Scaffolding Material & Erection at Deaerator Flat Area 2 days 9/13/2021 9/14/2021 8/26/2021 8/26/2021 0.004 100.00% Done by Empada
9/27/2021
Cutting and Removal Plate & Angle at Daerator Flat Area 7 days 9/14/2021 9/20/2021 9/25/2021 0.015 100.00% Done by Empada

Dismantling of Damper & Seating #3 at Daerator Flat Area 4 days 9/17/2021 9/20/2021 9/3/2021 9/9/2021 0.009 100.00% Done by Empada
Transfer Scrap Material From Daerator Flat 4 days 9/18/2021 9/21/2021 9/9/2021 10/2/2021 0.009 100.00% Done by Empada
Transfer Fabrication Material to Daerator Flat 4 days 4/13/2022 4/14/2022 4/19/2022 4/26/2022 0.009 100.00% Done by Empada
Preparation Fabrication Material For Installation 4 days 4/14/2022 4/15/2022 4/19/2022 4/26/2022 0.009 100.00% Done by Empada
Fit-up New Angle Bar & Plate 5 days 4/15/2022 4/16/2022 4/18/2022 4/26/2022 0.011 100.00% Done by Empada
ABS Fit-up Inspection 1 days 4/17/2022 4/17/2022 4/18/2022 4/27/2022 0.002 100.00% Done by Empada
Welding New Frame & Plate at Deaerator Flate Area 5 days 4/18/2022 4/21/2022 4/19/2022 TBA 0.011 100.00% Done by Empada
Welding Fan Seating & Installation Damper at Deaerator Flat Area 7 days 4/22/2022 4/23/2022 4/27/2022 TBA 0.015 100.00% Done by Empada
Welding Inspection & NDT 1 days 4/24/2022 4/24/2022 TBA TBA 0.002 100.00% Done by Empada
Touch up Painting at Deaerator Flat Area 3 days 4/25/2022 4/27/2022 TBA TBA 0.007 100.00% Done by Empada
Dismantling Scaffolding at Deaerator Flate Area 2 days 4/28/2022 4/29/2022 TBA TBA 0.004 100.00% Done by Empada
c SUPPLY FAN 3# TRUNKING 9/22/2021 10/19/2021 9/25/2021 4/25/2022 0.094 100.00%

Scaffolding Erection Inside Confine Space Area 3 days 9/22/2021 9/24/2021 9/25/2021 10/8/2021 0.007 100.00% Done by Empada

Preparation for Hot Work Inside Confine Space Area 2 days 9/25/2021 9/26/2021 9/29/2021 10/15/2021 0.004 100.00% Done by Empada

Cutting and Removal Angle Bar & Plate Inside Confined Space Area 5 days 9/27/2021 10/1/2021 9/29/2021 10/15/2021 0.011 100.00% Done by Empada

Transfer Scrap Material From Confined Space 5 days 9/28/2021 10/2/2021 10/1/2021 10/15/2021 0.011 100.00% Done by Empada
Transfer Fabrication Material to Confined Space 5 days 9/29/2021 10/3/2021 10/9/2021 10/30/2021 0.011 100.00% Done by Empada
Preparation New Angle & Plate for Supply Fan 1# 5 days 9/30/2021 10/4/2021 10/11/2021 11/1/2021 0.011 100.00% Done by Empada
Fit-up New Angle & Plate Inside Confined Space Area 5 days 10/1/2021 10/5/2021 10/13/2021 11/4/2021 0.011 100.00% Done by Empada
ABS Fit-up Inspection 1 days 10/6/2021 10/6/2021 10/14/2021 11/12/2021 0.002 100.00% Done by Empada
Welding New Angle & Plate Inside Confined Space Area 5 days 4/4/2022 4/6/2022 4/4/2022 4/23/2022 0.011 100.00% Done by Empada
Welding Inspection & NDT 2 days 4/6/2022 4/7/2022 4/23/2022 4/23/2022 0.004 100.00% Done by Empada
Touch up Painting at Confined Space Area 3 days 4/8/2022 4/10/2022 4/23/2022 4/24/2022 0.007 100.00% Done by Empada
Dismantling Scaffolding at Confined Space 2 days 4/11/2022 4/12/2022 4/25/2022 4/25/2022 0.004 100.00% Done by Empada
4 BULKHEAD FRAME TBA TBA TBA TBA 0.114 33.65%
a 5640 OFF CL AREA TBA TBA TBA TBA 0.033 83.33%
Preparation for Hot Work Task 1 days TBA TBA TBA TBA 0.002 100.00% Done by HHA
Cutting and Removal of Corroded Bulkhead Part 2 days TBA TBA TBA TBA 0.004 100.00% Done by HHA
Transfer Scrap Material 2 days TBA TBA TBA TBA 0.004 100.00% Done by HHA
Transfer Fabrication Material to 5640 Off CL Area 1 days TBA TBA TBA TBA 0.002 100.00% Done by HHA
Preparation Material for Bulkhead Installation 2 days TBA TBA TBA TBA 0.004 100.00% Done by HHA
Fit-up New Bulkhead Frame & Plate 2 days TBA TBA TBA TBA 0.004 100.00% Done by HHA
ABS Fit-up Inspection 1 days TBA TBA TBA TBA 0.002 100.00% Done by HHA
Welding New Frame & Plate Bulkhead 3 days TBA TBA 0.007 50.00%
Welding Inspection & NDT 1 days TBA TBA 0.002
b 8460 OFF CL AREA TBA TBA TBA TBA 0.041 26.32%
Preparation for Hot Work Task 1 days TBA TBA TBA TBA 0.002 100.00% Done by HHA
Cutting and Removal of Corroded Bulkhead Part 2 days TBA TBA TBA TBA 0.004 100.00% Done by HHA
Transfer Scrap Material 2 days TBA TBA TBA TBA 0.004 100.00% Done by HHA
Transfer Fabrication Material to 8460 Off CL Area 2 days 0.004
Preparation Material for Bulkhead Installation 2 days 0.004
Fit-up New Bulkhead Frame & Plate 2 days 0.004
ABS Fit-up Inspection 1 days 0.002
Welding New Frame & Plate Bulkhead 4 days 0.009
Welding Inspection & NDT 1 days 0.002
Touch up Painting 2 days 0.004
c FRAME 36 0.039 0.00%
Preparation for Hot Work Task 1 days 0.002
Cutting and Removal of Corroded Part Frame 36 2 days 0.004
Transfer Scrap Material 2 days 0.004
Transfer Fabrication Material to Frame 36 Area 2 days 0.004
Preparation Material for Bulkhead Installation 2 days 0.004
Fit-up New Bulkhead Frame & Plate 2 days 0.004
ABS Fit-up Inspection 1 days 0.002
Welding New Frame & Plate Bulkhead 3 days 0.007
Welding Inspection & NDT 1 days 0.002
Touch up Painting 2 days 0.004
5 DUCTING HOOD AREA 0.218 0.00%
a FRAME 29 (DUCTING WALL) AREA 0.035 0.00%
Preparation for Hot Work Task 1 days 0.002
Cutting and Removal Corroded Part at Frame 29 Area 2 days 0.004
Transfer Scrap Material & Fabrication Material 2 days 0.004
Preparation New Material for Installation 2 days 0.004
Fit-Up New Angle Bar/Plate 2 days 0.004
ABS Fit-up Inspection 1 days 0.002
Welding New Angle & Plate at Frame 29 3 days 0.007
Welding Inspection & NDT 1 days 0.002
Touch up Painting 2 days 0.004
b FRAME 36 (DUCTING WALL) AREA 0.035 0.00%
Preparation for Hot Work Task 1 days 0.002
Cutting and Removal Corroded Part at Frame 36 Area 2 days 0.004
Transfer Scrap Material & Fabrication Material 2 days 0.004
Preparation New Material for Installation 2 days 0.004
Fit-Up New Angle Bar/Plate 2 days 0.004
ABS Fit-up Inspection 1 days 0.002
Welding New Angle & Plate at Frame 36 3 days 0.007
Welding Inspection & NDT 1 days 0.002
Touch up Painting 2 days 0.004
c FRAME 33 AREA 0.028 0.00%
Preparation for Hot Work Task 1 days 0.002
Cutting and Removal Corroded Part at Frame 33 Area 1 days 0.002
Transfer Scrap Material & Fabrication Material 2 days 0.004
Preparation New Material for Installation 2 days 0.004
Fit-Up New Angle Bar/Plate 1 days 0.002
ABS Fit-up Inspection 1 days 0.002
Welding New Angle & Plate at Frame 33 2 days 0.004
Welding Inspection & NDT 1 days 0.002
Touch up Painting 2 days 0.004
d TOP DUCTING HOOD 0.037 0.00%
Preparation for Hot Work Task 3 days 0.007
New Plate and Bulkhead Preparation 3 days 0.007
Fit-Up New Angle Bar/Plate 3 days 0.007
ABS Fit-up Inspection 1 days 0.002
New Plate Welding 4 days 0.009
Welding Inspection & NDT 1 days 0.002
Touch up Painting 2 days 0.004
e LOWER CASING TOP AREA 0.083 0.00%
Site Preparation / Clear Working Area 3 days 0.007
Hard Barrier and Scaffold Erection at Area Lower Casing Top 2 days 0.004
Transfer Material/Equipment to Lower Casing Top 3 days 0.007
Marking & Removal Corroded Part at Lower Casing Top 5 days 0.011
Preparation New Material for Installation 5 days 0.011
Fit-up New Angle Bar & Plate 5 days 0.011
ABS Fit-up Inspection 2 days 0.004
Welding New Frame & Plate at Lower Casing Top 6 days 0.013
Welding Inspection & NDT 2 days 0.004
Dismantle Hard Barrier & Scaffolding at Lower Casing Top 2 days 0.004
Touch up Painting 3 days 0.007
6 HOUSEKEEPING & FINAL TOUCH UP 0.013 0.00%
Final Touch Up & Reinstatement Activities 3 days 0.007
Housekeeping MTEC Prior to Demobilization 3 days 0.007