Construction Project Plan

Task Status Start Date End Date

Pre-Construction Actitivities Completed 18/10/2022 26/10/2022

Site walk Completed 18/10/2022 18/10/2022

Blueprint review with owners Completed 18/10/2022 18/10/2022

Blueprint review with team Completed 19/10/2022 20/10/2022

Begin rental equipment procurement Completed 20/10/2022 24/10/2022

Set up project office Completed 20/10/2022 26/10/2022

Site Mobilization Delayed 26/10/2022 03/11/2022

Block off area and establish access points On Time 26/10/2022 31/10/2022

Set up on-site satellite office On Hold 01/11/2022 03/11/2022

Review construction plan with crew Delayed 03/11/2022 03/11/2022

Review safety procedures with crew Completed 03/11/2022 03/11/2022


Receive and store vehicle/equipment
rentals Completed 01/11/2022 02/11/2022

Scope 1: Concrete Foundation Delayed 08/11/2022 12/12/2022

Preliminary site preparation Completed 08/11/2022 14/11/2022

Foundation excavation Completed 15/11/2022 21/11/2022

Move steel into position On Time 22/11/2022 23/11/2022

Foundation pour Delayed 24/11/2022 24/11/2022

Foundation curing time On Hold 25/11/2022 09/12/2022

Foundation inspection Not Started 12/12/2022 12/12/2022


Scope 2: Structural Steel Erection &
Exterior Work Not Started 13/12/2022 28/02/2023

Move steel to job site Not Started 13/12/2022 13/12/2022


Preliminary material inspection Not Started 15/12/2022 15/12/2022

Erect structure (Floor 1) Not Started 16/12/2022 04/01/2023

Floor 1 inspection Not Started 05/01/2023 05/01/2023

Erect structure (Floor 2) Not Started 06/01/2023 20/01/2023

Floor 2 inspection Not Started 23/01/2023 23/01/2023

Exterior fill-in Not Started 24/01/2023 16/02/2023

Install windows, doors Not Started 13/02/2023 27/02/2023

Final structural inspection Not Started 28/02/2023 28/02/2023

Scope 3: Interior Work Not Started 23/02/2023 03/04/2023

Interior walls (Floor 1) Not Started 23/02/2023 02/03/2023

Interior walls (Floor 2) Not Started 03/03/2023 10/03/2023

Electrical work Not Started 07/03/2023 13/03/2023

Plumbing work Not Started 14/03/2023 20/03/2023

Finish interior walls Not Started 21/03/2023 27/03/2023

Flooring install Not Started 16/03/2023 30/03/2023

Painting Not Started 28/03/2023 03/04/2023

Project Closeout Not Started 03/04/2023 17/04/2023

Final inspection Not Started 04/04/2023 04/04/2023

Reconcile labor, materials budgeting Not Started 03/04/2023 10/04/2023

Demobilize on-site equipment and office Not Started 05/04/2023 12/04/2023

Handoff to owner Not Started 17/04/2023 17/04/2023


Duration % Completed Owner Predecessor

7d 100.00% Crystal Codebase

1d 100.00% Crystal Codebase

1d 100.00% Crystal Codebase

2d 100.00% Peter Perfcycle Site walk

3d 100.00% Crystal Codebase Site walk

5d 100.00% Crystal Codebase

7d 100.00% Peter Perfcycle

4d 100.00% Peter Perfcycle

3d 100.00% Peter Perfcycle

1d 100.00% Crystal Codebase

1d 100.00% Peter Perfcycle

2d 100.00% Peter Perfcycle Begin rental equipment p

25d 51.40% Beth Bigidea

5d 100.00% Peter Perfcycle Receive and store vehicle/

5d 100.00% Beth Bigidea Preliminary site preparatio

2d 100.00% Harry Helpsalot Foundation excavation

1d 30.00% Beth Bigidea Move steel into position

11d 5.00% Roger Reports Foundation pour

1d Beth Bigidea Foundation curing time

56d Beth Bigidea

1d Harry Helpsalot
1d Beth Bigidea Move steel to job site

14d Beth Bigidea Preliminary material inspection, Foundation inspection

1d Harry Helpsalot Erect structure (Floor 1)

11d Beth Bigidea Floor 1 inspection

1d Beth Bigidea Erect structure (Floor 2)

18d Harry Helpsalot Floor 2 inspection

11d

1d Install windows, doors

28d Beth Bigidea

6d Beth Bigidea Exterior fill-in

6d Beth Bigidea Interior walls (Floor 1)

5d Roger Reports

5d Beth Bigidea Interior walls (Floor 1), Int

5d Roger Reports Interior walls (Floor 2), Plumbing work, Electrical work

11d Crystal Codebase Electrical work

5d Beth Bigidea Electrical work, Finish interior walls

11d Crystal Codebase

1d Crystal Codebase Painting

6d Crystal Codebase

6d Crystal Codebase

1d Peter Perfcycle Final inspection, Demobiliz


Subcontractors & Vendors Files Notes

Li's Engineering, CM Consulting Inc Screen Shot 2021-11-23 at 11.38.36 AM.png

Screen Shot 2021-11-23 at 11.39.03 AM.png

Bright Electric , Plumbing with Combs,


Dwell Stones Inc Screen Shot 2021-11-23 at 11.39.41 AM.png

Equipment Rentals Inc Screen Shot 2021-11-23 at 11.40.31 AM.png

CM Consulting Inc Screen Shot 2021-11-23 at 11.40.52 AM.png

Screen Shot 2021-11-23 at 11.42.08 AM.png

Screen Shot 2021-11-23 at 11.43.43 AM.png

Bright Electric , Plumbing with Combs,


Dwell Stones Inc, CM Consulting Inc Screen Shot 2021-11-23 at 11.39.41 AM.png

Screen Shot 2021-11-23 at 11.44.33 AM.png

Equipment Rentals Inc Screen Shot 2021-11-23 at 11.46.13 AM.png

Li's Engineering Screen Shot 2021-11-23 at 11.48.09 AM.png

Equipment Rentals Inc Screen Shot 2021-11-23 at 11.48.51 AM.png

Screen Shot 2021-11-23 at 11.49.32 AM.png

Screen Shot 2021-11-23 at 11.51.57 AM.png

Screen Shot 2021-11-23 at 11.52.31 AM.png

Dwell Stones Inc Screen Shot 2021-11-23 at 11.54.07 AM.png

CM Consulting Inc

Equipment Rentals Inc Screen Shot 2021-11-23 at 11.54.48 AM.png


Dwell Stones Inc, Li's Engineering Screen Shot 2021-11-23 at 12.07.01 PM.png

aterial inspection, Foundation inspection Screen Shot 2021-11-23 at 12.09.12 PM.png

CM Consulting Inc Screen Shot 2021-11-23 at 12.07.40 PM.png

Screen Shot 2021-11-23 at 12.10.01 PM.png

Screen Shot 2021-11-23 at 12.08.05 PM.png

Screen Shot 2021-11-23 at 12.10.34 PM.png

Screen Shot 2021-11-23 at 12.11.13 PM.png

Dwell Stones Inc Screen Shot 2021-11-23 at 12.08.48 PM.png

Screen Shot 2021-11-23 at 12.12.09 PM.png

Screen Shot 2021-11-23 at 12.14.27 PM.png

Bright Electric Screen Shot 2021-11-23 at 12.14.57 PM.png

Plumbing with Combs Screen Shot 2021-11-23 at 12.15.16 PM.png

Floor 2), Plumbing work, Electrical work Screen Shot 2021-11-23 at 12.16.53 PM.png

Dwell Stones Inc Screen Shot 2021-11-23 at 12.18.07 PM.png

, Finish interior walls Screen Shot 2021-11-23 at 12.09.32 PM.png

Bright Electric , Plumbing with Combs, CM


Consulting Inc, Li's Engineering Screen Shot 2021-11-23 at 12.18.54 PM.png

Screen Shot 2021-11-23 at 12.21.44 PM.png

Screen Shot 2021-11-23 at 12.22.20 PM.png

Li's Engineering, CM Consulting Inc Screen Shot 2021-11-23 at 12.22.53 PM.png

You might also like