no Project name Client Information Scope of the Project Project Estimated cost

1 JAAZ BUILDERS ALI E FIRE INSTALLATION 508000


PROJECT PLAN SUMMURY REPORT

Total Budget of the Project Assigned Site Manager Contractor/Vendor Start Date End Date

500000 RAHUL NIL 11/30/2023 12/7/2023


mercur

firewin

mercur

vineesh
vineesh

12/13/2023
N SUMMURY REPORT

Project Phases Status Responsible Dept/Division/Person

Material Delivery 80% completed Site supervisor


Piping on going Anil
Painting completed Helper - sijil
Equipment Fixing on going Anil
Raiser work Work in progress Anil
FBI connection Work in progress Anil
Pump Setting Anil
fire alarm
Commissioning Vineeshthambi
Work duration(in days) Planned date of Completion Fund Rquired Date of Required

2days 2days ₹ 222,275.00


6days
2days 2days ₹ 5,960.00
4hrs ₹ 4,000.00
1day
2 hr
1 day

4hrs
4
Material Required Equipment Required Manpower Required

yes

Not purchased Not purchased


Any other Requirements or Remarks

causing electrical issue so,work delay


core cutting team delay c/o anil