PRELIMENARY SCHEDULE PROJECT CFPP BOILER 1 PT.

ANTAM
PT. ALBERTA MAKMUR UTAMA

JANUARI FEBRUARI
No JOB DESCRIPTION START DATE DURATION
2 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 Material & Tools To Site 20/12/2022 14
2 Manpower To Site 15/01/2023 1
3 Covid Cek & Safety Induction 16/01/2023 1
4 Prepare Material & Tools 17/01/2023 1
5 Marking Area With User 18/01/2023 1
Actual Marking Area With User
6 Start Fabrication Moulding 18/01/2023 9
Actual Fabrication Moulding
7 Dismantling Refractory 19/01/2023 12
Actual Dismantling Refractory
8 Gouging & Install Anchor 21/01/2023 11
Actual Gouging & Install Anchor
9 Install Insulation Castable 24/01/2023 10
Actual Install Insulation Castable
10 Install Moulding 27/01/2023 9
Actual Install Moulding
11 Casting Material Castable 29/01/2023 10
Actual Install Material Castable
12 Dismantling Moulding 02/02/2023 8
Actual Dismantling Moulding
13 Checking with User 10/02/2023 1
Actual Checking With User
14 Cleaning All Area 11/02/2023 3
Actual Cleaning
15 Finishing 10/02/2023 2