TIME SCHEDULE

BTR PROJECT

2023
NO. URAIAN / DESCRIPTION Duration units Start Finish

FEB MARET APRIL


a b c d c d W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13
Site Installation and Test Commissioing
1 Manpower On Site
1.1 Mechanical 2 days 3 Feb 2023 5 Feb 2023
1.2 Electrical 2 days 16 Feb 2023 18 Feb 2023
2 Mechanical
2.1 Preparation Site Work 3 days 6 Feb 2023 9 Feb 2023
2.2 Equipment Positioning 6 days 10 Feb 2023 16 Feb 2023
2.3 Clarifier Chemical Dosing System 8 days 17 Feb 2023 25 Feb 2023
2.4 Lamella Clarifier 15 days 17 Feb 2023 4 Mar 2023
2.5 Filter Feed Pump 7 days 25 Feb 2023 4 Mar 2023
2.6 Multimedia Filter 15 days 17 Feb 2023 4 Mar 2023
2.7 RO Feed Pump & CIP Pump 7 days 17 Feb 2023 24 Feb 2023
2.8 Activated Carbon Filter 15 days 5 Mar 2023 20 Mar 2023
2.9 Softener 15 days 5 Mar 2023 20 Mar 2023
2.10 BWRO Chemical Dosing System 6 days 21 Mar 2023 27 Mar 2023
2.11 BWRO Skid & CIP 15 days 21 Mar 2023 5 Apr 2023
2.12 RO Product Tank 15 days 21 Mar 2023 5 Apr 2023
2.13 Instrument Air 5 days 21 Mar 2023 26 Mar 2023
2.14 Regeneration Pump 5 days 21 Mar 2023 26 Mar 2023
3 Electrical
3.1 Panel Positioning 6 days 19 Feb 2023 25 Feb 2023
3.2 Support Installation 10 days 26 Feb 2023 8 Mar 2023
3.3 Jinction Box Installation 10 days 9 Mar 2023 19 Mar 2023
3.4 Cable Pulling 6 days 20 Mar 2023 26 Mar 2023
3.5 Cable Termination 9 days 27 Mar 2023 5 Apr 2023
4 Commissioning and Hand Over
4.1 Function Test & Rotation 5 days 6 Apr 2023 11 Apr 2023
4.2 Commissioning and Performance Monitoring 1 days 12 Apr 2023 13 Apr 2023
4.3 Operation Training 1 days 19 Apr 2023 20 Apr 2023
4.4 Hand Over 1 days 19 Apr 2023 20 Apr 2023