Title Start End Duration Prerequisites
Mar 27 – Apr 2 Apr 3 – Apr 9 Apr 10 – Apr 16 Apr 17 – Apr 23 Apr 24 – Apr 30 May 1 – May 7 May 8 – May 14 May 15 – May 21 May 22 – May 28 May 29 – Jun 4 Jun 5 – Jun 11 Jun 12 – J
1) Design and Administrative Tasks 2023-04-03 2023-06-05 9w 1d Design and Administrative Tasks
1.1) Conceptual design 2023-04-03 2023-04-07 1w Conceptual design
1.2) Final design 2023-04-10 2023-04-12 3d 1.1 Final design
1.3) Building permit application 2023-04-13 2023-04-21 1w 2d 1.2 Building permit application
1.4) Building permit received 2023-04-21 2023-04-21 1.3 Building permit received
1.5) As build design 2023-06-02 2023-06-05 2d 5.5FF As build design