Swimming Pool
Title Start End Duration Prerequisites
Mar 27 – Apr 2 Apr 3 – Apr 9 Apr 10 – Apr 16 Apr 17 – Apr 23 Apr 24 – Apr 30 May 1 – May 7 May 8 – May 14 May 15 – May 21 May 22 – May 28 May 29 – Jun 4 Jun 5 – Jun 11 Jun 12 – J
1) Design and Administrative Tasks 2023-04-03 2023-06-05 9w 1d Design and Administrative Tasks
1.1) Conceptual design 2023-04-03 2023-04-07 1w Conceptual design
1.2) Final design 2023-04-10 2023-04-12 3d 1.1 Final design
1.3) Building permit application 2023-04-13 2023-04-21 1w 2d 1.2 Building permit application
1.4) Building permit received 2023-04-21 2023-04-21 1.3 Building permit received
1.5) As build design 2023-06-02 2023-06-05 2d 5.5FF As build design

2) Construction Works 2023-04-24 2023-05-26 5w Construction Works


2.1) Earthworks 2023-04-24 2023-04-25 2d 1.4 Earthworks
2.2) Rebar installation 2023-04-27 2023-04-27 1d 2.1, 3.1, 3.2 Rebar installation
2.3) Shotcrete application 2023-04-28 2023-04-28 1d 2.2, 3.1, 3.2 Shotcrete application
2.4) Concrete tasks completion 2023-04-28 2023-04-28 2.3 Concrete tasks completion
2.5) Curing 2023-05-01 2023-05-26 4w 2.3 Curing

3) MEP 2023-04-03 2023-04-26 3w 3d MEP


3.1) Water circulation plumbing 2023-04-26 2023-04-26 1d 2.1 Water circulation plumbing
3.2) Lighting cabling installation 2023-04-26 2023-04-26 1d 3.1SS Lighting cabling installation

3.3) Pump and filters installation 2023-04-26 2023-04-26 3.1 P


3.4) Light fixtures installation 2023-04-03 2023-04-03 1d Light fixtures installation

4) Finishing Works 2023-05-01 2023-05-31 4w 3d Finishing Works


4.1) Tiles and coping 2023-05-01 2023-05-03 3d 2.3 Tiles and coping
4.2) Patio installation 2023-05-04 2023-05-10 1w 4.1 Patio installation
4.3) Plaster and pattern installation 2023-05-29 2023-05-30 2d 2.5 Plaster and pattern installation
4.4) Outdoor furniture installation 2023-05-31 2023-05-31 1d 4.3 Outdoor furniture installation

5) Testing and start up 2023-04-03 2023-06-05 9w 1d Testing and start up


5.1) Piping pressure testing 2023-04-27 2023-04-27 1d 3.1 Piping pressure testing
5.2) Cabling installation testing 2023-04-27 2023-04-27 1d 3.2 Cabling installation testing
5.3) Functional testing 2023-04-03 2023-04-03 1d Functional testing
5.4) Pool filling and start up 2023-06-01 2023-06-05 3d 4.3+1d Pool filling and start up
5.5) Handover 2023-06-05 2023-06-05 5.4 Handover