You are on page 1of 1

Nawe Bilal Malikzai Construction Co (NBMCC),

Establishment of LTA Construction of Provincial Cold Chain Buildings in variouslocations, Afghanistan, on Long Term Agreement LRPS-2023-9183732

Activity ID Activity Name Original Start Finish August 2023 September 2023 October 2023 November 2023 December 2023 January 2024
Duration
30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28
RFP/COK/026/2023-2 Establishment of 139d 01-Aug-2023
LTA Construction 17-Dec-2023
of Provincial Cold Chain Buildings 17-Dec-2023, RFP/COK/026/2023-2 Establishment of LTA Construction of Provincial Cold Chain Building

RFP/COK/026/2023-2.1 Pre Construction 5d 01-Aug-2023 05-Aug-2023 05-Aug-2023, RFP/COK/026/2023-2.1 Pre Construction


A1000 Pre Costruction meeting 1d 01-Aug-2023 01-Aug-2023 Pre Costruction meeting
A1010 Mobilization (site comp, equipment, & personal. 2d 01-Aug-2023 02-Aug-2023 Mobilization (site comp, equipment, & personal.
A1020 Pre-Construction Survey. 2d 01-Aug-2023 02-Aug-2023 Pre-Construction Survey.
A1030 Submitalof Material for Approval. 4d 01-Aug-2023 04-Aug-2023 Submitalof Material for Approval.
A1040 soil test for geotechnical investigation and structural design of foundation
5d 01-Aug-2023 05-Aug-2023 soil test for geotechnical investigation and structural design of foundation
129d
RFP/COK/026/2023-2.2 construction of School Building 06-Aug-2023 12-Dec-2023 12-Dec-2023, RFP/COK/026/2023-2.2 construction of School Building

RFP/COK/026/2023-2.2.3 Structural works 51d 06-Aug-2023 25-Sep-2023 25-Sep-2023, RFP/COK/026/2023-2.2.3 Structural works
RFP/COK/026/2023-2.2.3.10 Foundation 25d 06-Aug-2023 30-Aug-2023 30-Aug-2023, RFP/COK/026/2023-2.2.3.10 Foundation
A1190 Excavation of foundation 2d 06-Aug-2023 07-Aug-2023 Excavation of foundation
A1200 Reomval of extra material and cleaning 1d 08-Aug-2023 08-Aug-2023 Reomval of extra material and cleaning
A1210 Tow layers of 10mm thick Well compacted soil 95% M.D.D 2d 09-Aug-2023 10-Aug-2023 Tow layers of 10mm thick Well compacted soil 95% M.D.D
A1211 Installation of PE sheet for under the PCC in the foundations 1d 11-Aug-2023 11-Aug-2023 Installation of PE sheet for under the PCC in the foundations
A1212 PCC below column's footings th = 10 cm 2d 12-Aug-2023 13-Aug-2023 PCC below column's footings th = 10 cm
A1213 column footings 3d 14-Aug-2023 16-Aug-2023 column footings
A1220 Stone masonry 5d 17-Aug-2023 21-Aug-2023 Stone masonry
A1230 plinth beams 4d 22-Aug-2023 25-Aug-2023 plinth beams
A1240 Backfilling with soil inside the rooms 5d 26-Aug-2023 30-Aug-2023 Backfilling with soil inside the rooms
RFP/COK/026/2023-2.2.3.9 First Floor 13d 31-Aug-2023 12-Sep-2023 12-Sep-2023, RFP/COK/026/2023-2.2.3.9 First Floor
A1430 RCC Concrete of stair Columns and columns. 3d 31-Aug-2023 02-Sep-2023 RCC Concrete of stair Columns and columns.
A1440 RCC Concrete of slab 10d 03-Sep-2023 12-Sep-2023 RCC Concrete of slab
RFP/COK/026/2023-2.2.3.1 Second Floor 13d 13-Sep-2023 25-Sep-2023 25-Sep-2023, RFP/COK/026/2023-2.2.3.1 Second Floor
A2180 RCC Concrete of stair Columns and columns. 3d 13-Sep-2023 15-Sep-2023 RCC Concrete of stair Columns and columns.
A2190 RCC Concrete of slab 10d 16-Sep-2023 25-Sep-2023 RCC Concrete of slab
RFP/COK/026/2023-2.2.1 Architectural Works 96d 08-Sep-2023 12-Dec-2023 12-Dec-2023, RFP/COK/026/2023-2.2.1 Architectural Works
A1570 Electrical Work 90d 08-Sep-2023 06-Dec-2023 Electrical Work
A1580 walls burnt brick masonry 23d 28-Sep-2023 20-Oct-2023 walls burnt brick masonry
A1600 Supply and installation of aluminum and PVC 8000 windows 6d 15-Oct-2023 20-Oct-2023 Supply and installation of aluminum and PVC 8000 windows
A1601 Supply and installation of aluminum and PVC 8000 doors 6d 15-Oct-2023 20-Oct-2023 Supply and installation of aluminum and PVC 8000 doors
A1602 Roofing Works 10d 21-Oct-2023 30-Oct-2023 Roofing Works
A1603 Water supply, Sewarege and Plumbing Works 10d 21-Oct-2023 30-Oct-2023 Water supply, Sewarege and Plumbing Works
A1604 Fire Alarm System 10d 21-Oct-2023 30-Oct-2023 Fire Alarm System
A1605 Mechanical System 35d 21-Oct-2023 24-Nov-2023 Mechanical System
A1610 Plastering of Exterior walls and interior walls 30d 21-Oct-2023 19-Nov-2023 Plastering of Exterior walls and interior walls
A1620 PCC for floors 10d 15-Nov-2023 24-Nov-2023 PCC for floors
A1630 Marble Stones for Entrance Stair steps and windows sill inside rooms
5d 20-Nov-2023 24-Nov-2023 Marble Stones for Entrance Stair steps and windows sill inside rooms
A1640 Supply and installation of Handrail 5d 25-Nov-2023 29-Nov-2023 Supply and installation of Handrail
A1650 Painting Works 13d 30-Nov-2023 12-Dec-2023 Painting Works
RFP/COK/026/2023-2.5 Construction of Septic Tank 37d 21-Oct-2023 26-Nov-2023 26-Nov-2023, RFP/COK/026/2023-2.5 Construction of Septic Tank
A1940 Excavation 3d 21-Oct-2023 23-Oct-2023 Excavation
A1950 compaction 2d 24-Oct-2023 25-Oct-2023 compaction
A1960 Filling of septic tank floor with gravel 6d 26-Oct-2023 31-Oct-2023 Filling of septic tank floor with gravel
A1970 PCC for floor under RCC slab 1d 01-Nov-2023 01-Nov-2023 PCC for floor under RCC slab
A1980 RCC works 15d 02-Nov-2023 16-Nov-2023 RCC works
A1981 Waterproofing for septic tank 5d 17-Nov-2023 21-Nov-2023 Waterproofing for septic tank
A1990 Plumbing work 4d 22-Nov-2023 25-Nov-2023 Plumbing work
A2000 Cleaning of area 1d 26-Nov-2023 26-Nov-2023 Cleaning of area
RFP/COK/026/2023-2.3 Compeletion 4d 13-Dec-2023 16-Dec-2023 16-Dec-2023, RFP/COK/026/2023-2.3 Compeletion
A1170 Site Cleaning 2d 13-Dec-2023 14-Dec-2023 Site Cleaning
A1180 Demobilization 2d 15-Dec-2023 16-Dec-2023 Demobilization
RFP/COK/026/2023-2.4 Project Close Out 1d 17-Dec-2023 17-Dec-2023 17-Dec-2023, RFP/COK/026/2023-2.4 Project Close Out
A1160 Hand Over 1d 17-Dec-2023 17-Dec-2023 Hand Over

Actual Level of Effort


Prepared By: Eng Abdul Matin Rawofi
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary