PT. Bukit Candi Sejahtera is a general contractor that will be performing plumbing work from October 2023 to December 2023. The work includes item preparation in October, fabrication from October to December, and installation in 5 stages from October to December. The installation will include clean water, rain water, sewage water, waste water, and vent systems over the course of the 3 month period.
PT. Bukit Candi Sejahtera is a general contractor that will be performing plumbing work from October 2023 to December 2023. The work includes item preparation in October, fabrication from October to December, and installation in 5 stages from October to December. The installation will include clean water, rain water, sewage water, waste water, and vent systems over the course of the 3 month period.
PT. Bukit Candi Sejahtera is a general contractor that will be performing plumbing work from October 2023 to December 2023. The work includes item preparation in October, fabrication from October to December, and installation in 5 stages from October to December. The installation will include clean water, rain water, sewage water, waste water, and vent systems over the course of the 3 month period.
General Contractor Branch Office : Komplek Ruko ABC Sagulung, Kota Batam – 29425 Email : btm.ptbcs@gmail.com Mobile : +62 811 6941 289
PLUMBING WORK SCHEDULE
ESTIMASI OCTOBER NOVEMBER DESEMBER NO DESCRIPTION START FINISH 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 A ITEM PREPARATION 02/10/2023 16/10/2023 1 Container loading for site oficce and store 02/10/2023 02/10/2023 Arrange position of container & connection electricity, 2 table and accesoris 03/10/2023 05/10/2023 3 Arrange fabrication area 06/10/2023 07/10/2023 4 arrange tools and handtools 08/10/2023 09/10/2023 5 Arrange power supply for fabrication 10/10/2023 10/10/2023 6 loading tools and handtools 11/10/2023 11/10/2023 7 Loading material for fabrication ( support and accesoris 12/10/2023 15/10/2023 8 Parcial manpower loading 16/10/2023 16/10/2023
B FABRICATION WORK 17/10/2023 17/12/2023
C INSTALATION WORK 1ST 17/10/2023 15/11/2023
1 Clean Water 17/10/2023 15/11/2023 2 Rain Water 23/10/2023 02/11/2023 3 Sewage Water 17/10/2023 26/10/2023 4 Waste Water 20/10/2023 29/10/2023 5 Vent System 30/11/2023 012/11/23
D INSTALATION WORK 2ST 03/11/2023 17/12/2023
1 Clean Water 03/11/2023 17/12/2023 2 Rain Water 03/11/2023 12/11/2023 3 Waste Water System 03/11/2023 05/11/2023 4 Vent System 03/11/2023 05/11/2023
E INSTALATION WORK 3ST 13/11/2023 26/11/2023
1 Rain Water 13/11/2023 26/11/2023 2 Waste Water System 13/11/2023 15/11/2023 3 Vent System 15/11/2023 16/11/2023
F INSTALATION WORK 4ST 26/12/2023 03/12/2023
1 Clean Water 26/11/2023 29/11/2023 2 Rain Water 26/11/2023 03/12/2023 3 Waste Water System 26/11/2023 29/11/2023 4 Vent System 26/11/2023 29/11/2023
F INSTALATION WORK 5ST 04/12/2023 17/12/2023
1 Clean Water 04/12/2023 17/12/2023 2 Rain Water 04/12/2023 17/12/2023 3 Waste Water System 07/12/2023 08/12/2023 4 Vent System 07/12/2023 09/12/2023 5 Sewage Water 04/12/2023 06/12/2023