MASTER WORK PROGRAM FOR NEW INTERIOR DESIGN WORK FOR

DC BODY AT PUBLIKA, KUALA LUMPUR


PROJECT START: 11/9/2023 CONSTRUCTION ST10/26/2023 CONSTRUCTION END 12/22/2023 DISPLAY WEEK: 1

WEEK & DATE Nov 6, 2023 Nov 13, 2023 Nov 20, 2023 Nov 27, 2023 Dec 4, 2023 Dec 11, 2023 Dec 18, 2023 Dec 25, 2023 Jan 1, 2024
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

PRELIMINARIES

Drawing Preparation 100% 10/13/2023 10/18/2023

Submission to Authorities 100% 10/20/2023 10/24/2023

Hoarding Work & Installation 100% 10/26/2023 10/27/2023

Site Mobalisation 100% 10/26/2023 10/26/2023

ARCHITECTURE WORK

Plumbing Work & Water Sprinkler 100% 10/26/2023 10/28/2023

Floor Render & Leveling Work 100% 10/26/2023 10/27/2023

Site Marking 100% 10/26/2023 10/30/2023

Brick Wall, Partitioning Work & Glass Partitioning Work 90% 10/28/2023 11/3/2023

Mechanical & Eletrical Work 70% 10/31/2023 11/3/2023

Plaster Ceiling Structure Work 100% 11/4/2023 11/6/2023

Lighting Point Work 90% 11/6/2023 11/8/2023

Ceiling Board Work 80% 11/9/2023 11/13/2023

Celing Paint Work 0% 11/10/2023 11/13/2023

Toilet Waterproofing, Finishing & Fittings 100% 11/14/2023 11/17/2023

Door Installation Work 0% 11/6/2023 11/7/2023

Wall Painting Work 0% 11/4/2023 11/7/2023

Floor Finish Work 0% 11/20/2023 11/23/2023

Lighting Fittings 0% 11/13/2023 11/15/2023

Mechanical & Eletrical Fittings 0% 11/8/2023 11/10/2023

CARPENTRY WORK

Carpentry Fabrication Work 0% 11/3/2023 11/20/2023

Reception Counter Installation 0% 11/22/2023 11/24/2023

Reception Wall Panel Installation 0% 11/20/2023 11/24/2023

Consultation Room 1

Working Table Installation 0% 11/20/2023 11/24/2023

Base Cabinet Installation 0% 11/20/2023 11/24/2023

Consultation Room 2

Working Table Installation 0% 11/20/2023 11/24/2023

Base Cabinet Installation 0% 11/20/2023 11/24/2023

Treatment Room 1

Base Cabinet Installtion 0% 11/20/2023 11/24/2023


WEEK & DATE Nov 6, 2023 Nov 13, 2023 Nov 20, 2023 Nov 27, 2023 Dec 4, 2023 Dec 11, 2023 Dec 18, 2023 Dec 25, 2023 Jan 1, 2024
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Tall Cabinet Installation 0% 11/20/2023 11/24/2023

Quartz Stone Installation 0% 11/20/2023 11/24/2023

Treatment Room 2

Base Cabinet Installtion 0% 11/20/2023 11/24/2023

Tall Cabinet Installation 0% 11/20/2023 11/24/2023

Quartz Stone Installation 0% 11/20/2023 11/24/2023

Treatment Room 3

Base Cabinet Installtion 0% 11/27/2023 11/30/2023

Tall Cabinet Installation 0% 11/27/2023 11/30/2023

Quartz Stone Installation 0% 11/27/2023 11/30/2023

Treatment Room 4

Base Cabinet Installtion 0% 11/27/2023 11/30/2023

Tall Cabinet Installation 0% 11/27/2023 11/30/2023

Quartz Stone Installation 0% 11/27/2023 11/30/2023

Consultation Room 5

Base Cabinet Installtion 0% 11/27/2023 11/30/2023

Tall Cabinet Installation 0% 11/27/2023 11/30/2023

Quartz Stone Installation 0% 11/27/2023 11/30/2023

Consultation Room 6

Base Cabinet Installtion 0% 11/27/2023 11/30/2023

Tall Cabinet Installation 0% 11/27/2023 11/30/2023

Quartz Stone Installation 0% 11/27/2023 11/30/2023

Staff Pantry

Base Cabinet Installtion 0% 11/27/2023 11/30/2023

Tall Cabinet Installation 0% 11/27/2023 11/30/2023

Quartz Stone Installation 0% 11/27/2023 11/30/2023

Sink & Faucet 0% 11/27/2023 11/30/2023

Salad Bar

Base Cabinet Installtion 0% 11/27/2023 11/30/2023

Quartz Stone Installation 0% 11/27/2023 11/30/2023

Eletrical Appliances 0% 11/27/2023 11/30/2023

LOOSE FURNITURE

3 Seater Sofa 0% 11/28/2023 11/30/2023

Arm Chair 0% 11/28/2023 11/30/2023

Office Chair 0% 11/28/2023 11/30/2023

High Back Chair 0% 11/28/2023 11/30/2023

Low Back Chair 0% 11/28/2023 11/30/2023

Page 2 of 3
WEEK & DATE Nov 6, 2023 Nov 13, 2023 Nov 20, 2023 Nov 27, 2023 Dec 4, 2023 Dec 11, 2023 Dec 18, 2023 Dec 25, 2023 Jan 1, 2024
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
SCOPE OF WORK PROGRESS START END
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Pantry Chair 0% 11/28/2023 11/30/2023

POST CONSTRUCTION

Post Construction Cleaning 0% 12/1/2023 12/1/2023

Quality Assurances & Quality Control 0% 12/4/2023 12/4/2023

Rectification & Finishing Work 0% 12/5/2023 12/8/2023

NOTE: This Master Work Program is based on the overall planning of the design and construction phase. Any delays or changes to the masterwork program dateline, we will update and inform to the client.