Starting

S.no Describition Of the Work End Date Duration Required Labour Remark
Date
Skilled Unskilled
1 Block Work 2/10/2023 2/18/2023 8 3 4
2 Plumbing & Electrical 2/18/2023 2/21/2023 3
3 Plastering 2/18/2023 2/23/2023 5 6 7
4 Floor Tile 2/24/2023 2/28/2023 4 4 5
5 T. Wall Tile 2/24/2023 2/27/2023 3 2 2
6 T.Floor Tile 2/27/2023 2/28/2023 1 2 3
7 Pantry Counter 2/24/2023 2/27/2023 3 2
8 Putty 2/28/2023 3/3/2023 3 8 4
9 Primer 3/4/2023 3/4/2023 0 3
10 Switch Plates 3/5/2023 3/5/2023 1 2
11 Painting 3/6/2023 3/7/2023 1 3
12 Door & Window Fixing 3/8/2023 3/10/2023 2 2 2
13 CP & Sanitary 3/11/2023 3/11/2023 1 2 2
14 Lightining & AC works 3/12/2023 3/16/2023 4 4