ID Task Task Name Duration Start Finish Successors Predecessors

Mode Half 1, 2024


A S O N D J F M A
1 Construction of G+1 84 days 9/25/2023 2/15/2024
Building
2 surve & Lineout 1 day 9/25/2023 9/26/2023 4 Labours,Site engg
3 Sub Structure 22 days 9/26/2023 11/2/2023
4 Excavation 5 days 9/26/2023 10/4/2023 5 2 JCB[1],Labours
5 Earth Shoring 2 days 10/5/2023 10/9/2023 6 4 Formwork[1],Labours
6 PCC of foundation 1 day 10/9/2023 10/10/2023 7 5 Cement[1],Sand [1]
7 RCC for Foundation 3 days 10/11/2023 10/14/2023 8 6 Labours,M 25 [1],Site engg,Steel [1],Vibrator[1]
8 Shuttering 2 days 10/16/2023 10/18/2023 9 7 Formwork[1]
9 Pouring concrete CF 1 day 10/18/2023 10/19/2023 10 8 Labours,Vibrator[1],Site engg

10 Removal of 2 days 10/20/2023 10/24/2023 11 9 Labours


shuttering
11 Column upto plinh 1 day 10/24/2023 10/25/2023 12 10 Formwork[1],Labours,Site engg
12 plinth beam 2 days 10/26/2023 10/28/2023 13 11 Formwork[1],Labours,Site engg
Shuttering
13 PB reinforcement 2 days 10/28/2023 11/1/2023 14 12 Labours,Steel [1]
14 PB concreting 1 day 11/1/2023 11/2/2023 15 13 CA[1],Formwork[1],M 25 [1],Site engg
15 Complection of Sub 0 days 11/2/2023 11/2/2023 17 14 11/2
structure
16 super structure 39 days 11/2/2023 1/9/2024
17 Column Extension 2 days 11/2/2023 11/7/2023 18 15 Steel [1]
18 Column reinf 2 days 11/7/2023 11/9/2023 19 17 Labours,Site engg,Steel [1]
19 Shuttering 2 days 11/10/2023 11/13/2023 20 18 Formwork[1],Labours,Site engg
20 concreting 1 day 11/13/2023 11/14/2023 21 19 M 25 [1],Site engg
21 Beam & Slab 5 days 11/15/2023 11/23/2023 22 20 Formwork[1],Labours
shuttering
22 Bar Bending 3 days 11/23/2023 11/28/2023 23 21 Labours,Site engg,Steel [1]
23 Placing of Reinf 3 days 11/28/2023 12/4/2023 24 22 Labours
24 Checking 1 day 12/4/2023 12/5/2023 25 23 PM,Site engg
25 Casting 1 day 12/6/2023 12/7/2023 26,31 24 M 25 [1],Site engg
26 Brick masonr 10 days 12/7/2023 12/23/2023 27 25 bricks[1],Labours,Site engg
27 electrical Pipings 2 days 12/23/2023 12/28/2023 28 26 Labours,Site engg
28 Plastering 5 days 12/28/2023 1/4/2024 29 27 Cement[1],Labours,Sand [1]
29 Fixing Doors & 2 days 1/5/2024 1/9/2024 28 Labours,PM,Site engg
Windows
30 First Floor 41 days 12/7/2023 2/15/2024
31 Column Extension 2 days 12/7/2023 12/9/2023 32 25 Formwork[1],Labours,Steel [1]
32 Column Reinf 2 days 12/11/2023 12/13/2023 33 31 Site engg
33 Column shuttering 3 days 12/13/2023 12/19/2023 34 32 Formwork[1],Steel [1]
34 Concrete placing 1 day 12/19/2023 12/20/2023 35 33 M 25 [1]

Task Project Summary Manual Task Start-only Deadline

Project: EXAM G+1 Split Inactive Task Duration-only Finish-only Progress


Date: 10/3/2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Successors Predecessors
Mode Half 1, 2024
A S O N D J F M A
35 Beam & Slab 5 days 12/21/2023 12/29/2023 36 34 Formwork[1],Labours
shuttering
36 Bar Bending 3 days 12/29/2023 1/3/2024 37 35 Labours,Steel [1]
37 placing of Reinf 2 days 1/3/2024 1/8/2024 38 36 Labours
38 checking 1 day 1/8/2024 1/9/2024 39 37 PM,Site engg
39 Casting 1 day 1/9/2024 1/10/2024 40 38 Labours,M 25 [1]
40 brick masonr 10 days 1/11/2024 1/29/2024 41 39 bricks[1],Labours
41 Electrical Pipings 3 days 1/29/2024 2/2/2024 42 40 Labours,Site engg
42 plastering 5 days 2/2/2024 2/10/2024 43 41 Cement[1],Labours,Sand [1]
43 Fixing Doors & 3 days 2/12/2024 2/15/2024 42 Labours
Windows

Task Project Summary Manual Task Start-only Deadline

Project: EXAM G+1 Split Inactive Task Duration-only Finish-only Progress


Date: 10/3/2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2