ID Task Task Name Duration Start Finish Successors Predecessors
Mode Half 1, 2024
A S O N D J F M A
35 Beam & Slab 5 days 12/21/2023 12/29/2023 36 34 Formwork[1],Labours
shuttering
36 Bar Bending 3 days 12/29/2023 1/3/2024 37 35 Labours,Steel [1]
37 placing of Reinf 2 days 1/3/2024 1/8/2024 38 36 Labours
38 checking 1 day 1/8/2024 1/9/2024 39 37 PM,Site engg
39 Casting 1 day 1/9/2024 1/10/2024 40 38 Labours,M 25 [1]
40 brick masonr 10 days 1/11/2024 1/29/2024 41 39 bricks[1],Labours
41 Electrical Pipings 3 days 1/29/2024 2/2/2024 42 40 Labours,Site engg
42 plastering 5 days 2/2/2024 2/10/2024 43 41 Cement[1],Labours,Sand [1]
43 Fixing Doors & 3 days 2/12/2024 2/15/2024 42 Labours
Windows