BURGAN BASE PROJECT TIMELINE R0

Original 2022 2023


Activity ID Activity Description Start Finish
Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
BURGAN BASE CONSTRUCTION 298 22-Nov-22 16-Sep-23
1 MOBILIZATION
1.1 Permit/address card 2 22-Nov-22 24-Nov-22
1.2 Survey & Setting out 2 22-Nov-22 24-Nov-22
1.3 Receive IFC Drawings 2 22-Nov-22 24-Nov-22
1.4 Underground service drawings 2 22-Nov-22 24-Nov-22
1.5 Site office mobilization work 3 22-Nov-22 25-Nov-22
2 ENGINEERING
2.1 SUBMITTAL/APPROVAL
2.1.1 Submission for civil works 4 22-Nov-22 26-Nov-22
2.1.2 Submission for structural works 4 22-Nov-22 26-Nov-22
2.1.3 Submission for MEP works 5 22-Nov-22 27-Nov-22
2.1.4 Submission for Final Schedule 3 22-Nov-22 25-Nov-22
3 CHEMICAL WAREHOUSE (PKG2 CIVIL) 72 26-Nov-22 06-Feb-23
3.1 Civil Works
3.1.1 Site preperation and Setting out 1 26-Nov-22 27-Nov-22
3.1.2 Excavation works for foundations 4 27-Nov-22 01-Dec-22
3.1.3 Form works and rebar cutting and bending works 4 27-Nov-22 01-Dec-22
3.1.4 Shuttering works, rebar fixing and concrete pour for foundations 5 01-Dec-22 06-Dec-22
3.1.5 Shuttering works, rebar fixing and concrete pour for ramp retaining walls 6 07-Dec-22 13-Dec-22
3.1.6 Shuttering works, rebar fixing and concrete pour for ground beams 8 14-Dec-22 22-Dec-22
3.1.7 Backfilling, compaction of warehouse infill 3 22-Dec-22 25-Dec-22
3.1.8 Trench Works 6 26-Dec-22 01-Jan-23
3.1.9 Floor slab rebar fixing, concrete pour 7 02-Jan-23 09-Jan-23
3.2 Steel Structural works
3.2.1 Erection of Warehouse steel structure columns 4 11-Jan-23 15-Jan-23
3.2.2 Erection of Warehouse steel structure Rafters 4 16-Jan-23 20-Jan-23
3.2.3 Erection of Warehouse steel structure Purlins 4 21-Jan-23 25-Jan-23
3.2.4 Erection of Warehouse steel structure Walls 4 26-Jan-23 30-Jan-23
3.2.5 Erection of Warehouse steel structure Roof 4 31-Jan-23 04-Feb-23
3.2.6 Installation of Ridge cover, flashings, rain gutter 1 05-Feb-23 06-Feb-23
3.2.7 Finishing Works 2 04-Feb-23 06-Feb-23
4 ACID PLANT (PKG4 CIVIL) 65 07-Feb-23 13-Apr-23
4.1 Civil Works
4.1.1 Site preperation and Setting out 1 07-Feb-23 08-Feb-23
4.1.2 Excavation works for foundations 3 09-Feb-23 12-Feb-23
4.1.3 Form works and rebar cutting and bending works 4 13-Feb-23 17-Feb-23
4.1.4 Shuttering works, rebar fixing and concrete pour for foundations 4 18-Feb-23 22-Feb-23
4.1.5 Shuttering works, rebar fixing and concrete pour for ground beams 4 23-Feb-23 27-Feb-23
4.1.6 Trench Works 10 28-Feb-23 10-Mar-23
4.1.7 Floor slab rebar fixing, concrete pour 8 11-Mar-23 19-Mar-23
4.1.8 Sump pit works 15 20-Mar-23 04-Apr-23
4.1.9 Concrete Hump wall 6 05-Apr-23 11-Apr-23
4.1.10 Finishing Works 6 05-Apr-23 11-Apr-23
4.2 Steel Structural works
4.2.1 Trench Cover and Gratings 2 06-Apr-23 08-Apr-23
4.2.2 Steel Structural works for shade 6 06-Apr-23 12-Apr-23
4.2.3 Metal Fencing Works 4 09-Apr-23 13-Apr-23
5 CHEMICAL WAREHOUSE (PKG4 MEP) 70 13-Apr-23 22-Jun-23
5.1 Electrical Works
5.1.1 UG Works 5 20-Dec-22 25-Dec-22
5.1.2 Installation of Conduits, wiring and cables Warehouse 10 13-Apr-23 23-Apr-23
5.1.3 Fixing of light fixtures, power sockets and associated works warehouse 12 13-Apr-23 25-Apr-23
5.1.4 Installation of Distribution Panels 8 26-Apr-23 04-May-23
BURGAN BASE PROJECT TIMELINE R0

Original 2022 2023


Activity ID Activity Description Start Finish
Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
5.1.5 Fixing of light fixtures, power sockets and associated works other utilities 6 05-May-23 11-May-23
5.1.6 Commissioning, testing and inspections 2 12-May-23 14-May-23
5.2 Plumbing Works
5.2.1 UG Works 5 20-Dec-22 25-Dec-22
5.2.2 Drainage Works and Connections 10 13-Apr-23 23-Apr-23
5.2.3 Installation of Fixtures and accessories 5 24-Apr-23 29-Apr-23
5.2.4 Commissioning, testing and inspections 3 30-Apr-23 03-May-23
5.3 Fire Fighting and Detection System
5.3.1 UG Works 5 20-Dec-22 25-Dec-22
5.3.2 Installation of Pipe and pipe fittings for main line and branches 15 14-Apr-23 29-Apr-23
5.3.3 Installation of Fire Pump set and water tank 12 30-Apr-23 12-May-23
5.3.4 installation of Fire Hose reel and sprinklers 18 12-May-23 30-May-23
5.3.5 Installation of smoke detectors, wiring and associated works 15 30-May-23 14-Jun-23
5.3.6 Commissioning, testing and inspections 7 15-Jun-23 22-Jun-23
5.4 CCTV, Data, Telecom Network
5.4.1 Installation of RJ45 Sockets, cabling for DATA, IT and Telephone 10 30-Apr-23 10-May-23
5.4.2 Installation of PABX system 5 10-May-23 15-May-23
5.4.3 Installation of IT Cabinet with switches 5 16-May-23 21-May-23
5.4.4 Installation of CCTV camera and wiring 10 21-May-23 31-May-23
5.4.5 Installation of CCTV system 6 01-Jun-23 07-Jun-23
5.4.6 Commissioning, testing and inspections 2 15-Jun-23 17-Jun-23
5.5 HVAC
5.5.1 Installation of Air Curtains 2 08-Jun-23 10-Jun-23
5.5.2 Installation of Split AC Units 2 08-Jun-23 10-Jun-23
5.5.3 Installation of Desert Coolers 2 08-Jun-23 10-Jun-23
5.5.4 Commissioning, testing and inspections 5 15-Jun-23 20-Jun-23
6 ACID PLANT (PKG4 MEP) 40 16-Jun-23 26-Jul-23
6.1 Electrical Works
6.1.1 UG Works 5 20-Dec-22 25-Dec-22
6.1.2 Installation of Conduits, wiring and cables 6 16-Jun-23 22-Jun-23
6.1.3 Fixing of light fixtures, power sockets and associated works 8 16-Jun-23 24-Jun-23
6.1.4 Installation of Distribution Panels 7 25-Jun-23 02-Jul-23
6.1.5 Fixing of light fixtures, power sockets and associated works other utilities 5 03-Jul-23 08-Jul-23
6.1.6 Commissioning, testing and inspections 2 16-Jul-23 18-Jul-23
6.2 Plumbing Works
6.2.1 UG Works 5 20-Dec-22 25-Dec-22
6.2.2 Drainage Works and Connections 10 16-Jun-23 26-Jun-23
6.2.3 Installation of Fixtures and accessories 5 27-Jun-23 02-Jul-23
6.2.3 Commissioning, testing and inspections 3 03-Jul-23 06-Jul-23
6.3 Fire Fighting and Detection System
6.3.1 UG Works 5 20-Dec-22 25-Dec-22
6.3.2 Installation of Pipe and pipe fittings for main line and branches 10 17-Jun-23 27-Jun-23
6.3.3 Installation of Fire Pump set and tank for foam system 8 28-Jun-23 06-Jul-23
6.3.4 installation of Fire Hose reel and sprinklers 10 06-Jul-23 16-Jul-23
6.3.5 Installation of smoke detectors, wiring and associated works 5 16-Jul-23 21-Jul-23
6.3.6 Commissioning, testing and inspections 2 22-Jul-23 24-Jul-23
6.4 CCTV, Data, Telecom Network
6.4.1 Installation of RJ45 Sockets, cabling for DATA, IT and Telephone 5 28-Jun-23 03-Jul-23
6.4.2 Installation of PABX system 5 03-Jul-23 08-Jul-23
6.4.3 Installation of IT Cabinet with switches 5 09-Jul-23 14-Jul-23
6.4.4 Installation of CCTV camera and wiring 6 14-Jul-23 20-Jul-23
6.4.5 Installation of CCTV system 4 21-Jul-23 25-Jul-23
6.4.6 Commissioning, testing and inspections 1 25-Jul-23 26-Jul-23
7 FUTURE (PKG 4) 40 27-Jul-23 05-Sep-23
BURGAN BASE PROJECT TIMELINE R0

Original 2022 2023


Activity ID Activity Description Start Finish
Duration Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
7.1 Site Preparation and Setting Out 1 27-Jul-23 28-Jul-23
7.2 Civil Works for water tank area 7 29-Jul-23 05-Aug-23
7.3 Plumbing works for water tanks 8 06-Aug-23 14-Aug-23
7.4 Civil Works for septic tank area 8 15-Aug-23 23-Aug-23
7.5 Drainage Works for septic tank 6 24-Aug-23 30-Aug-23
7.6 Installation of mechanical oil and grease interceptor 5 31-Aug-23 05-Sep-23
8 HANDOVER 10 06-Sep-23 16-Sep-23
8.1 Snagging/Demobilization Works 5 06-Sep-23 11-Sep-23
8.2 Testing and Commissioning 4 12-Sep-23 16-Sep-23
8.3 Project Handover 0 16-Sep-23