ATTN : Ar. Debbie I.

Guerrero
THRU: Engr. Frans Vergel S. Manaois
FROM: SKY CONSTRUCTION CORPORATION
DATE : September 9, 2021
SUBJECT: SM City Baguio – Driveway Rehabilitation
Mobilization

Greetings!

We hereby recommend to adjust the start of mobilization for SM City Baguio – Driveway
Rehabilitation to the first week of January 2022. Considering that the project integrity and timeline
might be greatly affected due to the rainy season for the next couple of months as shown in the table
below. Another factor is the stopping of construction operations on October 15 to December
2021. Lastly, we also need time to process the necessary government permits to proceed
with our Driveway Rehabilitation Project.

SOURCE: https://www.temperatureweather.com/pacific/weather/en-weather-in-philippines-baguio.htm

Kindly review the readjusted timeline and key plan attached in the following pages. We hope
for your kind consideration. Thank you.

Sincerely yours,

Sky Construction Corporation


PROJECT: SM CITY BAGUIO - DRIVEWAY REHABILITATION
Location: Luneta Hill, Upper Session Rd, Baguio City

PROPOSED T I M E L I NE
JANUARY
ITEM DESCRIPTION DURATION START FINISH 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A Phase 1 - RDU Carpark Entrance (Left)
1 Demolition of Existing Slab including Gutter incl. Hauling of Debris 3 days Jan. 3, 2022 Jan. 5, 2022

2 Soil Base Preparation and Steel Works 3 days Jan. 6, 2022 Jan. 8, 2022

3 Concreting for Roads, Gutters and Curbs 1 day Jan. 8, 2022 Jan. 9, 2022 7 days- CURING

4 Application of Asphalt Joint Sealant for Road Cracks 2 days Jan. 10,2022 Jan.11,2022
B Phase 2 - UGF Driveway (Infront of BDO)
1 Demolition of Existing Slab including Gutter incl. Hauling of Debris 3 days Jan. 10, 2022 Jan. 12, 2022

2 Soil Base Preparation and Steel Works 3 days Jan. 13, 2022 Jan. 15, 2022

3 Concreting for Roads, Gutters and Curbs 1 day Jan. 15, 2022 Jan. 16, 2022 7 days- CURING

4 Application of Asphalt Joint Sealant for Road Cracks 1day Jan. 17,2022 Jan.18,2022
C Phase 3 - RDU Carpark Entrance (Right)
1 Demolition of Existing Slab including Gutter and Existing Sidewalk (Entrance 2) incl. Hauling of Debris 5 days Jan. 17, 2022 Jan. 21, 2022

2 Soil Base Preparation and Steel Works 5 days Jan. 18, 2022 Jan. 22, 2022

3 Concreting for Roads, Gutters, Curbs, and Sidewalk 2 days Jan. 21, 2022 Jan. 23, 2022 7 days- CURING

4 Application of Asphalt Joint Sealant for Road Cracks 2 days Jan. 24,2022 Jan.25,2022

5 Stone Cladding of Existing Riprap (Entrance 2) 3 days Jan. 25,2022 Jan. 27,2022
D Phase 4 - Main Drop Off (Entrance 1)
1 Temporary Board-up / Fencing 1 day Jan. 24, 2022 Jan. 25, 2021
2 Removal of Existing Stone Finish and Old Asphalt incl. Hauling of Debris 2 days Jan. 25, 2022 Jan. 26, 2022

3 Laying of 3" Thick Hot Mix Asphalt 1 night Jan. 27, 2022 Jan. 28, 2022
4 Repainting of Concrete Curbs (Mall Drop-off and Driveway area) 2 days Jan. 28,2022 Jan. 29,2022

Prepared By: Approved by:

Sky Construction Corporation


PROJECT: SM CITY BAGUIO – DRIVEWAY REHABILITATION KEYPLAN
LOCATION: Location: Luneta Hill, Upper Session Rd, Baguio City

Phase 1: RDU Carpark Entrance (Left) – January 3 – 11, 2022


Phase 3: RDU Carpark Entrance (Right) incl. Sidewalk and Stone Cladding – January 17 – 27, 2022
Phase 2: UGF Driveway (Infront of BDO) – January 10 – 18, 2022
Phase 4 : Main Drop Off (Entrance 1) – January 24 – 29, 2022