You are on page 1of 1

CIVIL WORK FOR PROPOSED PAVEMENT WORKS OF INLAY DEPARTMENT TO GREY MENDING PEB SHED ETC.

AT DAWOOD MILL

Activity ID Activity Name Original Start Finish June 2022 July 2022 August 2022 September 2022 October 2022 November 2022
Duration
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
62TO
01-Jul-22 31-Aug-22 31-Aug-22, CIVIL WORK FOR PROPOSED PAVEMENT WORKS OF INLAY DEPAR
CIVIL WORK FOR PROPOSED PAVEMENT WORKS OF INLAY DEPARTMENT GREY MENDING PEB SHED ETC. AT DAWOOD MILL
62 01-Jul-22 31-Aug-22 31-Aug-22, BALANCE ACTIVITIES
BALANCE ACTIVITIES
A1000 Aggregate Base Course Laying and Compaction 7 01-Jul-22 07-Jul-22 Aggregate Base Course Laying and Compaction
A1005 Eid Holidays 10 08-Jul-22 17-Jul-22 Eid Holidays
A1010 Kerb Stone Fixing 15 18-Jul-22 01-Aug-22 Kerb Stone Fixing
A1020 Laying of Pavers (Client Supplied Items) 10 02-Aug-22 11-Aug-22 Laying of Pavers (Client Supplied Items)
A1030 Construction of Storm Water Drain Channel (If approved by CED Department) 20 12-Aug-22 31-Aug-22 Construction of Storm Water Drain Channel (If approved by CED Department)

Primary Baseline Remaining Work Milestone Page 1 of 1 The schedule is subject to revision in case of delay of approvals or delay in
Actual Work Critical Remaining Work Summary
provision of Client Supplied Items.