DESIGN OF 4 KANAL FARM HOUSE IN LAHORE

BASE LINE SCHEDULE SUBMISSION

Activity ID Activity Name Original Start Finish Total Resources Calendar 2022 2023
Duration Float
Nov Dec Jan
FHDL Farm House Design at Lahore 60 01-Nov-22 30-Dec-22 0 5 Days Work 30-Dec-22, FHDL Farm House
Week
FHDL.1 Desk Study 3 01-Nov-22 03-Nov-22 0 5 Days Work 03-Nov-22, FHDL.1 Desk Study
Week
A1040 Preliminary Study for Requirements Collection 1 01-Nov-22 01-Nov-22 0 Chief 5 Days Work Preliminary Study for Requirements Collection
Architect, Week
Senior
A1050 Finalization of Requirement Collection Tools 2 02-Nov-22 03-Nov-22 0 Chief 5 Days Work Finalization of Requirement Collection Tools
Architect, Week
Senior
FHDL.2 Requirement Collection 6 04-Nov-22 09-Nov-22 0 5 Days Work 09-Nov-22, FHDL.2 Requirement Collection
Week
A1000 Kickoff Meeting 1 04-Nov-22 04-Nov-22 0 Chief 5 Days Work Kickoff Meeting
Architect, Week
Senior
A1010 Requirement Collection from Client 2 05-Nov-22 06-Nov-22 0 Senior 5 Days Work Requirement Collection from Client
Architect Week
A1020 Finalization of Requirement Tracability Matrix 2 07-Nov-22 08-Nov-22 0 Senior 5 Days Work Finalization of Requirement Tracability Matrix
Architect Week
A1030 Signing off Scope Finalization Docs 1 09-Nov-22 09-Nov-22 0 Senior 5 Days Work Signing off Scope Finalization Docs
Architect Week
FHDL.3 Field Testing 11 10-Nov-22 20-Nov-22 0 5 Days Work 20-Nov-22, FHDL.3 Field Testing
Week
A1060 Mobilization for Geotechnical Isvestigations 1 10-Nov-22 10-Nov-22 0 Geotech 5 Days Work Mobilization for Geotechnical Isvestigations
engr, Week
Laboratory
A1070 SPT Test for Borehole-1 3 11-Nov-22 13-Nov-22 0 Geotech 5 Days Work SPT Test for Borehole-1
engr, Week
Laboratory
A1080 SPT Test for Broehole-2 3 14-Nov-22 16-Nov-22 0 Geotech 5 Days Work SPT Test for Broehole-2
engr, Week
Laboratory
A1090 Laboratory Testing & Finalization of Results 3 17-Nov-22 19-Nov-22 0 Geotech 5 Days Work Laboratory Testing & Finalization of Results
engr, Week
Laboratory
A1100 Submission of Results 1 20-Nov-22 20-Nov-22 0 Geotech 5 Days Work Submission of Results
engr, Week
Laboratory

Actual Level of Effort summary Date Revision Checked Approved


Page 1 of 3
27-Oct-22 Assignment-1_Rev-00
Actual Work
Remaining Work
Critical Remaining Work
Milestone
DESIGN OF 4 KANAL FARM HOUSE IN LAHORE
BASE LINE SCHEDULE SUBMISSION

Activity ID Activity Name Original Start Finish Total Resources Calendar 2022 2023
Duration Float
Nov Dec Jan
FHDL.4 Architecture Design 15 21-Nov-22 05-Dec-22 0 5 Days Work 05-Dec-22, FHDL.4 Architecture Design
Week
A1110 Preparation & Submission of Concept Design 4 21-Nov-22 24-Nov-22 0 Architect 5 Days Work Preparation & Submission of Concept Design
Week
A1120 Approval of Concept Design 4 23-Nov-22 26-Nov-22 0 Architect 5 Days Work Approval of Concept Design
Week
A1130 Preparation & Submission of Detailed Layout 2 27-Nov-22 28-Nov-22 0 Architect 5 Days Work Preparation & Submission of Detailed Layout Design
Design Week
A1140 Approval of Detailed Layout Design 2 29-Nov-22 30-Nov-22 0 Architect 5 Days Work Approval of Detailed Layout Design
Week
A1150 Preparation & Submission of Furtniture Layout 4 01-Dec-22 04-Dec-22 0 Interior 5 Days Work Preparation & Submission of Furtniture Layout Desig
Design designer Week
A1160 Approval of Furniture Layout Design 4 02-Dec-22 05-Dec-22 0 Interior 5 Days Work Approval of Furniture Layout Design
designer Week
FHDL.5 Structure Design 5 06-Dec-22 10-Dec-22 0 5 Days Work 10-Dec-22, FHDL.5 Structure Design
Week
A1180 Finalization of Design Loads 1 06-Dec-22 06-Dec-22 0 Lead 5 Days Work Finalization of Design Loads
Structrue Week
Engineer
A1190 Calculation & Design Analysis 2 07-Dec-22 08-Dec-22 0 Structure 5 Days Work Calculation & Design Analysis
Engr Week
A1200 Preparation & Submission of Structure Design 2 09-Dec-22 10-Dec-22 0 Structure 5 Days Work Preparation & Submission of Structure Design
Engr Week
FHDL.6 MEP Design 6 11-Dec-22 16-Dec-22 0 5 Days Work 16-Dec-22, FHDL.6 MEP Design
Week
A1210 Preparation & Submission of Fresh Water 2 11-Dec-22 12-Dec-22 0 Hydraulic 5 Days Work Preparation & Submission of Fresh Water Sup
Supply Design Calculations Engr Week
A1220 Preparation & Submission of Sewerage 2 13-Dec-22 14-Dec-22 0 Hydraulic 5 Days Work Preparation & Submission of Sewerage Sys
System Design Drawings Calculations Engr Week
A1230 Preparation & Submission of Electrical 2 15-Dec-22 16-Dec-22 0 MEP 5 Days Work Preparation & Submission of Electrical Sys
Systems Design Calculations Designer Week

Actual Level of Effort summary Date Revision Checked Approved


Page 2 of 3
27-Oct-22 Assignment-1_Rev-00
Actual Work
Remaining Work
Critical Remaining Work
Milestone
DESIGN OF 4 KANAL FARM HOUSE IN LAHORE
BASE LINE SCHEDULE SUBMISSION

Activity ID Activity Name Original Start Finish Total Resources Calendar 2022 2023
Duration Float
Nov Dec Jan
FHDL.7 Land Scape Design 8 17-Dec-22 24-Dec-22 0 5 Days Work 24-Dec-22, FHDL.7 Land Scape De
Week
A1240 Preparation & Submission Concept Design 5 17-Dec-22 21-Dec-22 0 Landscape 5 Days Work Preparation & Submission Concept De
Expert Week
A1250 Approval of Concept Design 5 18-Dec-22 22-Dec-22 0 Landscape 5 Days Work Approval of Concept Design
Expert Week
A1260 Preparation & Submission of Final Landscape 2 23-Dec-22 24-Dec-22 0 Landscape 5 Days Work Preparation & Submission of Final L
Design Expert Week
FHDL.8 Drawings & Docs Submission 6 25-Dec-22 30-Dec-22 0 5 Days Work 30-Dec-22, FHDL.8 Drawings
Week
A1270 Submission of Construction Drawings forArchi 1 25-Dec-22 25-Dec-22 0 Draftsman 5 Days Work Submission of Construction Drawin
Construction Drawings Archi Week
A1280 Submission of Structure Drawings 1 26-Dec-22 26-Dec-22 0 Draftsman 5 Days Work Submission of Structure Drawings
Structure Week
A1290 Submission of Plumbing Drawings 1 27-Dec-22 27-Dec-22 0 Draftsman 5 Days Work Submission of Plumbing Drawing
MEP Week
A1300 Submission of Sewerage Drawings 1 28-Dec-22 28-Dec-22 0 Draftsman 5 Days Work Submission of Sewerage Drawin
MEP Week
A1310 Submission of Land Scape Drawings 1 29-Dec-22 29-Dec-22 0 Draftsman 5 Days Work Submission of Land Scape Dra
Archi Week
A1320 Submission of Specifications 1 30-Dec-22 30-Dec-22 0 Lead 5 Days Work Submission of Specifications
Structrue Week
Engineer

Actual Level of Effort summary Date Revision Checked Approved


Page 3 of 3
27-Oct-22 Assignment-1_Rev-00
Actual Work
Remaining Work
Critical Remaining Work
Milestone