Plan 8-Sep-22 7-Nov-22 96 Daily follow up with the supplier to reduce the leadtime
Forecast 03/10 -Due to new load changes requested by SBM the new lead time for it was
NSX250 Power Filter 3P 690VAC, 1 reschedule. SE is pushing to get it as earlier as possible.
4 Schneider 1105779091 France 0 3-Aug-22 05/11 - Forecast to receive it on 07/11.
piece
Actual
SWITCH RSP30-08033O6ZT-
5 Belden 1105774345 Germany 3-Aug-22 03/10 - PO delivered - Material in House
EKKUYHSE2AXX.X.XX
Actual
Plan 8-Sep-22 19-Nov-22 108 03/10 -Due to new load changes requested by SBM the new lead time for it was
Forecast reschedule. SE is pushing to get it as earlier as possible.
10 LC1D80P7 TeSys D contactor Schneider 1203741793 France 3-Aug-22 05/11 - Delayed
Actual
Plan 8-Sep-22 7-Nov-22 96 03/10 -Due to new load changes requested by SBM the new lead time for it was
12 NSX250HB1 CIRCUIT BREAKER MA Schneider Forecast 1105781567 Spain 3-Aug-22 reschedule. SE is pushing to get it as earlier as possible.
Actual 05/11 - Forecast to receive it on 07/11.
Plan 8-Sep-22 7-Nov-22 96 03/10 -Due to new load changes requested by SBM the new lead time for it was
13 NSX100HB1 CIRCUIT BREAKER MA Schneider Forecast 1105781567 Spain 3-Aug-22 reschedule. SE is pushing to get it as earlier as possible.
Actual 05/11 - Forecast to receive it on 07/11.
Plan 8-Sep-22 7-Nov-22 96 03/10 -Due to new load changes requested by SBM the new lead time for it was
13 NSX100HB1 CIRCUIT BREAKER 2.2 Schneider Forecast 1105781567 Spain 3-Aug-22 reschedule. SE is pushing to get it as earlier as possible.
Actual 05/11 - Forecast to receive it on 07/11.
Plan 8-Sep-22 7-Nov-22 96 03/10 -Due to new load changes requested by SBM the new lead time for it was
13 NSX250 HB 175kA AC3P 220A MA Schneider Forecast 1105781567 France 3-Aug-22 reschedule. SE is pushing to get it as earlier as possible.
Actual 05/11 - Forecast to receive it on 07/11.
FUSE HOLDER 3P 50A FOR FUSE 14 Plan 30-Nov-22 119 Daily follow up with the supplier to reduce the leadtime
13 Schneider Forecast 1203721356 France 3-Aug-22 03/10 - Siemens supplier has postponed deliver due to shortage.
X 51 MM
Actual 05/11 - Delayed
Plan 1-Nov-22 90 Daily follow up with the supplier to reduce the leadtime
13 ADJUSTABLE DELAY UNIT FOR MN Schneider Forecast 1105781566 Spain 3-Aug-22 03/10 -Supplier has postponed deliver due to shortage.
Actual 05/11 - PO delivered - Material in House
Plan 27-Oct-22 85 03/10 -Due to new load changes requested by SBM the new lead time for it was
CONTROLLER ETHERNET ROFIBUS
14 Schneider Forecast 1203741793 Chile 3-Aug-22 reschedule. SE is pushing to get it as earlier as possible.
0,4 8A 115 230VAC
Actual 05/11 - PO delivered - Material in House