Client: Consultant: 

THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 569 10-May-22 A 29-Nov-23 569
STUDY & DESIGN OF SHUWAIKH PORT (Detailed Work Program)
2 PHASE 1 to PHASE 4 540 10-May-22 A 31-Oct-23 540

3 PRELIMINARIES 16 Calendar Days (7/7) 10-May-22 A 25-May-22 A 16


4 SP-PRE-0010 Contract Start-Up (Commencement) 0 Calendar Days (7/7) 10-May-22 A Contract Start-Up (Commencement),
5 SP-PRE-0020 Mobilisation of the Team 15 Calendar Days (7/7) 10-May-22 A 24-May-22 A
6 SP-PRE-0030 Preparation of the PMP document and submission 15 Calendar Days (7/7) 11-May-22 A 25-May-22 A
7 SP-PRE-0040 Preparation of Project Schedule and submission 15 Calendar Days (7/7) 11-May-22 A 25-May-22 A
8 PHASE 1: DATA COLLECTION & PROJECT SCHEDULE PREPARATION (89 Days) 115 10-May-22 A 01-Sep-22 A 127
9 Site visit, Stakeholders meetings, Data collection, Review and Analysis 115 10-May-22 A 01-Sep-22 A 127
10 SP-PH1-0010 Data Collection from KPA 5 Calendar Days (7/7) 10-May-22 A 14-May-22 A
11 SP-PH1-0020 Review of all Information provided by KPA 14 Calendar Days (7/7) 15-May-22 A 28-May-22 A
12 SP-PH1-0030A Interface Meeting with consultancies working in the port (for berth 1-7) 5 Work Days (5/7) 29-May-22 A 02-Jun-22 A
13 SP-PH1-0030B Interface Meeting with consultancies working in the port (for passenger terminal & infrastructure upgrade) 5 Work Days (5/7) 29-May-22 A 02-Jun-22 A
14 SP-PH1-0040A Introductory meetings/workshops with EPA for initial approval process 1 Work Days (5/7) 19-May-22 A 19-May-22 A
15 SP-PH1-0040B Introductory meetings/workshops with KM for initial approval process 1 Work Days (5/7) 26-May-22 A 26-May-22 A
16 SP-PH1-0040C Introductory meetings/workshops with KFF for initial approval process 1 Work Days (5/7) 02-Jun-22 A 02-Jun-22 A
17 SP-PH1-0040D1 Introductory meetings/workshops with MOI - Cost Guard 1 Work Days (5/7) 26-May-22 A 26-May-22 A
18 SP-PH1-0040D2 Introductory meetings/workshops with MOI - Port Security 1 Work Days (5/7) 02-Jun-22 A 02-Jun-22 A
19 SP-PH1-0040D3 Introductory meetings/workshops with MOI - Port Security and Projects 1 Work Days (5/7) 08-Jun-22 A 08-Jun-22 A
20 SP-PH1-0040E Introductory meetings/workshops with MEW for initial approval process 1 Work Days (5/7) 20-Jun-22 A 20-Jun-22 A
21 SP-PH1-0040F Introductory meetings/workshops with MPW for initial approval process 1 Work Days (5/7) 20-Jun-22 A 20-Jun-22 A
22 SP-PH1-0040F1 Introductory meeting/workshops with Ministry of Public Works (MPW) - Mega Project Dept (MAK Port) 1 Work Days (5/7) 10-Aug-22 A 10-Aug-22 A
23 SP-PH1-0040G Introductory meetings/workshops with KOC for initial approval process 1 Work Days (5/7) 15-Aug-22 A 15-Aug-22 A
24 SP-PH1-0040H Introductory meetings/workshops with PAAFR for initial approval process 1 Work Days (5/7) 15-Jun-22 A 15-Jun-22 A
25 SP-PH1-0040I Introductory meetings/workshops with MOC for initial approval process 1 Work Days (5/7) 15-Jun-22 A 15-Jun-22 A
26 SP-PH1-0040J Introductory meetings/workshops with KGAC for initial approval process 1 Work Days (5/7) 07-Jun-22 A 07-Jun-22 A
27 SP-PH1-0040K Introductory meetings/workshops with PART for initial approval process 1 Work Days (5/7) 22-Jun-22 A 22-Jun-22 A
28 SP-PH1-0040L1 Introductory meetings/workshops with MOH - Sea Transport Department 1 Work Days (5/7) 25-Jun-22 A 26-Jun-22 A
29 SP-PH1-0040L2 Introductory meetings/workshops with MOH - General Health Department 1 Work Days (5/7) 27-Jun-22 A 27-Jun-22 A
30 SP-PH1-0040M Introductory meetings/workshops with Other Stakeholders for initial approval process 13 Work Days (5/7) 05-Jun-22 A 21-Jun-22 A
31 SP-PH1-0040N1 Introductory meetings/workshops with 3rd Party for collecting waste from the Port 1 Work Days (5/7) 15-Aug-22 A 15-Aug-22 A
32 SP-PH1-0050A Data collection (Rules/Regulations/Requirements/information related to the project) from EPA 15 Work Days (5/7) 12-Jun-22 A 30-Jun-22 A
33 SP-PH1-0050B Data collection (Rules/Regulations/Requirements/information related to the project) from KM 15 Work Days (5/7) 05-Jun-22 A 23-Jun-22 A
34 SP-PH1-0050C Data collection (Rules/Regulations/Requirements/information related to the project) from KFF 15 Work Days (5/7) 22-Jun-22 A 12-Jul-22 A
35 SP-PH1-0050D Data collection (Rules/Regulations/Requirements/information related to the project) from MOI 15 Work Days (5/7) 22-Jun-22 A 12-Jul-22 A
36 SP-PH1-0050E Data collection (Rules/Regulations/Requirements/information related to the project) from MEW 15 Work Days (5/7) 22-Jun-22 A 12-Jul-22 A
37 SP-PH1-0050F Data collection (Rules/Regulations/Requirements/information related to the project) from MPW 7 Work Days (5/7) 22-Jun-22 A 30-Jun-22 A
38 SP-PH1-0050G Data collection (Rules/Regulations/Requirements/information related to the project) from KOC 12 Work Days (5/7) 17-Aug-22 A 01-Sep-22 A
39 SP-PH1-0050H Data collection (Rules/Regulations/Requirements/information related to the project) from PAAFR 15 Work Days (5/7) 22-Jun-22 A 12-Jul-22 A
40 SP-PH1-0050I Data collection (Rules/Regulations/Requirements/information related to the project) from MOC 15 Work Days (5/7) 22-Jun-22 A 12-Jul-22 A
41 SP-PH1-0050J Data collection (Rules/Regulations/Requirements/information related to the project) from KGAC 15 Work Days (5/7) 22-Jun-22 A 12-Jul-22 A
42 SP-PH1-0050K Data collection (Rules/Regulations/Requirements/information related to the project) from PART 15 Work Days (5/7) 23-Jun-22 A 13-Jul-22 A
43 SP-PH1-0050L Data collection (Rules/Regulations/Requirements/information related to the project) from MOH 15 Work Days (5/7) 28-Jun-22 A 18-Jul-22 A
44 SP-PH1-0050M Data collection (Rules/Regulations/Requirements/information related to the project) from Other Stakeholders 15 Work Days (5/7) 22-Jun-22 A 12-Jul-22 A
45 SP-PH1-0050N1 Data collection (Rules/Regulations/Requirements/information related to the project) from 3rd Party 12 Work Days (5/7) 16-Aug-22 A 31-Aug-22 A
46 SP-PH1-0060 Interface meetings and collection of the requirements from KPA internal departments 7 Work Days (5/7) 13-Jul-22 A 24-Jul-22 A
47 SP-PH1-0260 Site Walk-around for the Team with KPA & Key Stakeholders 1 Work Days (5/7) 29-May-22 A 29-May-22 A
48 SP-PH1-0270 Review of Existing Port Operations & Conditions 14 Calendar Days (7/7) 30-May-22 A 12-Jun-22 A
49 Review of RINA Study 14 Calendar Days (7/7) 01-Jun-22 A 14-Jun-22 A 14
50 SP-PH1-0280 Review Trade Forecasts for Shuwaikh Port 14 Calendar Days (7/7) 01-Jun-22 A 14-Jun-22 A
51 KPA Technical Meetings 41 Work Days (5/7) 31-May-22 A 26-Jul-22 A 41
52 SP-PH1-0300 KPA Progress Meetings 1 1 Work Days (5/7) 31-May-22 A 31-May-22 A
53 SP-PH1-0310 KPA Progress Meetings 2 1 Work Days (5/7) 14-Jun-22 A 14-Jun-22 A
54 SP-PH1-0320 KPA Progress Meetings 3 1 Work Days (5/7) 28-Jun-22 A 28-Jun-22 A
55 SP-PH1-0330 KPA Progress Meetings 4 1 Work Days (5/7) 07-Jul-22 A 07-Jul-22 A

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 1 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
56 SP-PH1-0340 KPA Progress Meetings 5 1 Work Days (5/7) 26-Jul-22 A 26-Jul-22 A
57 Review of Reclamation & Design Study for Constructing a Container Terminal 46 15-May-22 A 29-Jun-22 A 36
58 SP-PH1-0400 Initial review comment on geotechnical, seismic (if required) characteristics and coastal structures 21 Calendar Days (7/7) 15-May-22 A 04-Jun-22 A
59 SP-PH1-0410 Initial review and comments for extra berths requirements 14 Calendar Days (7/7) 15-Jun-22 A 28-Jun-22 A
60 SP-PH1-0420 Presentation of Initial Findings & Recommentations on Reclamation 1 Work Days (5/7) 29-Jun-22 A 29-Jun-22 A
61 Review of Dredging Study for Increasing the Draft, Width and Length of the Navigation Channel 28 15-Jun-22 A 12-Jul-22 A 28
62 SP-PH1-0450 Initial Review comments & Recommendations 25 Calendar Days (7/7) 15-Jun-22 A 09-Jul-22 A
63 SP-PH1-0460 Presentation of initial recommendations to KPA 1 Work Days (5/7) 12-Jul-22 A 12-Jul-22 A
64 Survey of Existing Building & Facilities 73 19-May-22 A 31-Jul-22 A 66
65 SP-PH1-0500 Prepare complete list of Buildings & Facilities to be surveyed 5 Calendar Days (7/7) 19-May-22 A 23-May-22 A
66 SP-PH1-0510 Confirm Agreement with KPA on listing 5 Work Days (5/7) 24-May-22 A 30-May-22 A
67 SP-PH1-0520 On-site Survey of Existing Building & Facilities 7 Calendar Days (7/7) 31-May-22 A 06-Jun-22 A
68 SP-PH1-0530 Prepare Base Map of surveyed buildings 7 Calendar Days (7/7) 07-Jun-22 A 13-Jun-22 A
69 SP-PH1-0540 Prepare Survey note 5 Calendar Days (7/7) 07-Jun-22 A 11-Jun-22 A
70 Topographical Survey 49 22-May-22 A 09-Jul-22 A 60
71 SP-PH1-0545 Submit topographical survey proposal and sub profile to KPA 0 Work Days (5/7) 22-May-22 A Submit topographical survey proposal and sub profile to KPA, 22-May-22 A
72 SP-PH1-0546 KPA review and approval of the proposal and the sub profile 7 Calendar Days (7/7) 23-May-22 A 29-May-22 A
73 SP-PH1-0550 Surveying Tender 10 Calendar Days (7/7) 30-May-22 A 08-Jun-22 A
74 SP-PH1-0555 Mobilization of Contractor/Survey team/equipments 5 Calendar Days (7/7) 09-Jun-22 A 13-Jun-22 A
75 SP-PH1-0560 Topographical Site Survey 21 Calendar Days (7/7) 14-Jun-22 A 04-Jul-22 A
76 SP-PH1-0565 Prepare Mapping from Topographical Survey 5 Calendar Days (7/7) 05-Jul-22 A 09-Jul-22 A
77 CAD Drawings and Survey Report 23 Calendar Days (7/7) 08-Jul-22 A 31-Jul-22 A 7
78 SP-PH1-0570 Generate CAD Drawings 23 Calendar Days (7/7) 08-Jul-22 A 31-Jul-22 A
79 SP-PH1-0580 Generate Survey Report 21 Calendar Days (7/7) 10-Jul-22 A 31-Jul-22 A
80 Environmental Impact Assessment Review 19 Calendar Days (7/7) 15-May-22 A 02-Jun-22 A 19
81 SP-PH1-0600 Review of the EIA 14 Calendar Days (7/7) 15-May-22 A 28-May-22 A
82 SP-PH1-0610 Preparation of a Compliance Database for Design Team for DD 5 Calendar Days (7/7) 29-May-22 A 02-Jun-22 A
83 Traffic Assessment 65 25-May-22 A 28-Jul-22 A 80
84 Information gathering 17 Calendar Days (7/7) 25-May-22 A 10-Jun-22 A 15
85 SP-PH1-0900 Site Visit 2 Calendar Days (7/7) 25-May-22 A 26-May-22 A
86 SP-PH1-0910 Liaison with all concerned authorities to obtain traffic problems 10 Calendar Days (7/7) 27-May-22 A 05-Jun-22 A
87 SP-PH1-0920 Compilation, Review, Validation, Analysis & Validity 5 Calendar Days (7/7) 06-Jun-22 A 10-Jun-22 A
88 Traffic Count Survey 39 15-Jun-22 A 23-Jul-22 A 38
89 SP-PH1-0924 Submit traffic study proposal and sub profile to KPA 0 Work Days (5/7) 15-Jun-22 A Submit traffic study proposal and sub profile to KPA, 15-Jun-22 A
90 SP-PH1-0926 KPA review and approval of the proposal and the sub profile 7 Calendar Days (7/7) 16-Jun-22 A 22-Jun-22 A
91 SP-PH1-0930 Undertake a Road Inventory 3 Calendar Days (7/7) 23-Jun-22 A 25-Jun-22 A
92 SP-PH1-0940 Presentation & Agreement of 5No locations for Automatic Traffic Counting 2 Calendar Days (7/7) 26-Jun-22 A 27-Jun-22 A
93 SP-PH1-0950 Placement of ATC 2 Calendar Days (7/7) 28-Jun-22 A 29-Jun-22 A
94 SP-PH1-0960 Monitoring through ATC 10 Calendar Days (7/7) 30-Jun-22 A 09-Jul-22 A
95 SP-PH1-0970 Agreement of location of 5No junctions for Turning Movement Counts (TMC) 2 Calendar Days (7/7) 10-Jul-22 A 11-Jul-22 A
96 SP-PH1-0980 Organise TMC 2 Calendar Days (7/7) 12-Jul-22 A 13-Jul-22 A
97 SP-PH1-0990 Undertake TMC 3 Calendar Days (7/7) 14-Jul-22 A 16-Jul-22 A
98 SP-PH1-1000 Selection of 3No Main Routes for Journey Time Survey (JTS) 2 Calendar Days (7/7) 17-Jul-22 A 18-Jul-22 A
99 SP-PH1-1010 Undertake JTS 3 Calendar Days (7/7) 19-Jul-22 A 21-Jul-22 A
100 SP-PH1-1020 Regroup all data gathered and prepare for use 2 Calendar Days (7/7) 22-Jul-22 A 23-Jul-22 A
101 Analysis of Existing Traffic Volumes 5 Calendar Days (7/7) 24-Jul-22 A 28-Jul-22 A 5
102 SP-PH1-1070N Prepare the Traffic count survey report 5 Calendar Days (7/7) 24-Jul-22 A 28-Jul-22 A
103 Phase I Deliverables 90 10-May-22 A 07-Aug-22 A 116
104 Monthly Progress Reports 22 Work Days (5/7) 06-Jun-22 A 06-Jul-22 A 22
105 SP-PH1-D-1300 Issue Monthly Progress Report No 1 (1st of Phase 1) 0 Work Days (5/7) 06-Jun-22 A Issue Monthly Progress Report No 1 (1st of Phase 1), 06-Jun-22 A
106 SP-PH1-D-1310 Issue Monthly Progress Report No 2 (2nd of Phase 1) 0 Work Days (5/7) 06-Jul-22 A Issue Monthly Progress Report No 2 (2nd of Phase 1), 06-Jul-22 A
107 Schedule/Report/Presentation 26 07-Jul-22 A 01-Aug-22 A 116
108 SP-PH1-D-1400 Updated Work Program Schedule and submit to KPA 7 Calendar Days (7/7) 26-Jul-22 A 01-Aug-22 A
109 SP-PH1-D-1410 Update Phase Man-Month Input Report and submit to KPA 7 Calendar Days (7/7) 26-Jul-22 A 01-Aug-22 A
110 SP-PH1-D-1430 Output of the topography survey and building survey 1 Calendar Days (7/7) 31-Jul-22 A 31-Jul-22 A
111 SP-PH1-D-1440 Presentation of Phase 1 Report to KPA 1 Work Days (5/7) 07-Jul-22 A 07-Jul-22 A

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 2 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
112 Phase 1 Report 90 10-May-22 A 07-Aug-22 A 115
113 SP-PH1-D-1500 Data collection and Phase report preparation 57 Calendar Days (7/7) 10-May-22 A 06-Jul-22 A
114 SP-PH1-D-1510 Finalise Phase 1 Report for final release 4 Calendar Days (7/7) 06-Jul-22 A 09-Jul-22 A
115 SP-PH1-D-1512 Submit Technical note for the review of Infrastructure Tender 0 Calendar Days (7/7) 09-Jun-22 A Submit Technical note for the review of Infrastructure Tender, 09-Jun-22 A
116 SP-PH1-D-1515 Issue Project Design Program Report 0 Work Days (5/7) 07-Jul-22 A Issue Project Design Program Report, 07-Jul-22 A
117 SP-PH1-D-1520 Issue Phase 1 Report to KPA 0 Work Days (5/7) 07-Jul-22 A Issue Phase 1 Report to KPA, 07-Jul-22 A
118 SP-PH1-D-1530 Review by KPA of Phase 1 Report & Associated Documents 7 Calendar Days (7/7) 13-Jul-22 A 19-Jul-22 A
119 SP-PH1-D-1540 Apply KPA Comments & Modification 14 Calendar Days (7/7) 19-Jul-22 A 01-Aug-22 A
120 SP-PH1-D-1550 Issue Phase 1 Final Report to KPA (with incorporation of comments) 0 Work Days (5/7) 01-Aug-22 A Issue Phase 1 Final Report to KPA (with incorporation of comments), 01-Aug-22 A
121 SP-PH1-D-1560 Review by KPA of Phase 1 Report & Associated Documents/Approval 7 Calendar Days (7/7) 01-Aug-22 A 07-Aug-22 A
122 PHASE 2: GENERAL LAYOUT DESIGN & ALTERNATIVES (132 Days) 207 07-Aug-22 A 01-Mar-23 296
123 Phase 2 Initials 177 07-Aug-22 A 30-Jan-23 177
124 SP-PH2-2000 Start with Phase 2 and close out of Phase 1 1 Work Days (5/7) 07-Aug-22 A 07-Aug-22 A
125 SP-PH2-2010 Internal SMEC Workshop to start Phase 2 1 Calendar Days (7/7) 08-Aug-22 A 08-Aug-22 A
126 SP-PH2-2020N Data collections from any missing entity or entries do not reply or required follow up 30 Calendar Days (7/7) 07-Aug-22 A 05-Sep-22 A
127 Options presentation, review and acceptance 44 08-Aug-22 A 20-Sep-22 A 44
128 SP-PH2-2110 Prepare for Workshop on spatial relationship 5 Calendar Days (7/7) 09-Aug-22 A 13-Aug-22 A
129 SP-PH2-2115 Study Future Expansion possibilities for port 14 Calendar Days (7/7) 08-Aug-22 A 21-Aug-22 A
130 SP-PH2-2120 Workshop spatial relationship between all components & disciplines 1 Calendar Days (7/7) 14-Aug-22 A 14-Aug-22 A
131 SP-PH2-2130 Organise the spatial relationship between all disciplines & require following workshops 5 Calendar Days (7/7) 15-Aug-22 A 19-Aug-22 A
132 SP-PH2-2140 Prepare high level block concept plans for various options by Discipline 14 Calendar Days (7/7) 22-Aug-22 A 04-Sep-22 A
133 SP-PH2-2150 Pull together all disciplines & workshop best fit for 3 options 14 Calendar Days (7/7) 31-Aug-22 A 13-Sep-22 A
134 SP-PH2-2160 Present Draft 3 options to the KPA 1 Work Days (5/7) 14-Sep-22 A 14-Sep-22 A
135 SP-PH2-2170 Discuss Evaluation multi Criteria of the 3 options with KPA 2 Calendar Days (7/7) 15-Sep-22 A 16-Sep-22 A
136 SP-PH2-2180 Incorporate all comments & proposed changes 5 Calendar Days (7/7) 15-Sep-22 A 19-Sep-22 A
137 SP-PH2-2190 Agree Phase 2 Report content with KPA 1 Work Days (5/7) 20-Sep-22 A 20-Sep-22 A
138 Coastal Modeling Study 35 Calendar Days (7/7) 22-Aug-22 A 25-Sep-22 A 35
139 SP-PH2-2370 Metocean 14 Calendar Days (7/7) 22-Aug-22 A 04-Sep-22 A
140 SP-PH2-2375 Wave transformation 21 Calendar Days (7/7) 05-Sep-22 A 25-Sep-22 A
141 Complementary/Supplementary data /Investigations (GI) 163 21-Aug-22 A 30-Jan-23 163
142 Marine Geotechnical Investigation 163 21-Aug-22 A 30-Jan-23 163
143 SP-PH2-2090N1 Submit GI study proposal and sub profile to KPA 0 Calendar Days (7/7) 21-Aug-22 A 21-Aug-22 A
144 SP-PH2-2090N2 KPA review and approval of the proposal and sub profile 6 Work Days (5/7) 21-Aug-22 A 28-Aug-22 A
145 SP-PH2-2090N3 Submit Borehole test (Soil Test Report) to KPA 1 Calendar Days (7/7) 29-Aug-22 A 29-Aug-22 A
146 SP-PH2-2090N4 Submit Site Plan and Locations of Boreholes to KPA 1 Calendar Days (7/7) 29-Aug-22 A 29-Aug-22 A
147 SP-PH2-2090N5 KPA Approval of boreholes locations 50 Work Days (5/7) 29-Aug-22 A 06-Nov-22 A
148 SP-PH2-2090N6 GI Tender 75 Calendar Days (7/7) 29-Aug-22 A 11-Nov-22 A
149 SP-PH2-2090N7 Mobilization of Contractor/GI team/equipmen 21 Calendar Days (7/7) 01-Dec-22* 21-Dec-22
150 SP-PH2-2090N8 Issue of the GIR 30 Calendar Days (7/7) 01-Jan-23 30-Jan-23
151 KPA Technical Meetings 91 Work Days (5/7) 09-Aug-22 A 13-Dec-22 91
152 SP-PH1-0350 KPA Progress Meetings 6 1 Work Days (5/7) 09-Aug-22 A 09-Aug-22 A
153 SP-PH2-2400 KPA Progress Meetings 7 1 Work Days (5/7) 23-Aug-22 A 23-Aug-22 A
154 SP-PH2-2410 KPA Progress Meetings 8 1 Work Days (5/7) 06-Sep-22 A 06-Sep-22 A
155 SP-PH2-2420 KPA Progress Meetings 9 1 Work Days (5/7) 20-Sep-22 A 20-Sep-22 A
156 SP-PH2-2430 KPA Progress Meetings 10 1 Work Days (5/7) 04-Oct-22 A 04-Oct-22 A
157 SP-PH2-2440 KPA Progress Meetings 11 1 Work Days (5/7) 18-Oct-22 A 18-Oct-22 A
158 SP-PH2-2450 KPA Progress Meetings 12 1 Work Days (5/7) 01-Nov-22 A 01-Nov-22 A
159 SP-PH2-2460 KPA Progress Meetings 13 1 Work Days (5/7) 15-Nov-22 A 15-Nov-22 A
160 SP-PH2-2470 KPA Progress Meetings 14 1 Work Days (5/7) 29-Nov-22 A 29-Nov-22 A
161 SP-PH2-3190 KPA Progress Meetings 15 1 Work Days (5/7) 13-Dec-22* 13-Dec-22
162 Preparation of Masterplan Concept Plans 22 Calendar Days (7/7) 21-Sep-22 A 12-Oct-22 A 156
163 SP-PH2-2500 Prepare Concept Plans - Reclamation and Dredging (New Container Terminal) 15 Calendar Days (7/7) 21-Sep-22 A 05-Oct-22 A
164 SP-PH2-2510 Prepare Concept Plans - Navigational Channel 15 Calendar Days (7/7) 21-Sep-22 A 05-Oct-22 A
165 SP-PH2-2520 Prepare Concept overall site plan 10 Calendar Days (7/7) 01-Oct-22 A 10-Oct-22 A
166 SP-PH2-2530 Prepare Concept Plans - Infrastructure (Wet Utilities) 10 Calendar Days (7/7) 21-Sep-22 A 30-Sep-22 A
167 SP-PH2-2540 Prepare Concept Plans - Infrastructure (Dry Utilities) 10 Calendar Days (7/7) 21-Sep-22 A 30-Sep-22 A

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 3 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
168 SP-PH2-2550 Prepare Concept Plans - Infrastructure (IT/Comms) 10 Calendar Days (7/7) 21-Sep-22 A 30-Sep-22 A
169 SP-PH2-2560 Prepare Concept Plans - Firefighting Systems 10 Calendar Days (7/7) 21-Sep-22 A 30-Sep-22 A
170 SP-PH2-2580A Prepare Concept Plans - Traffic Plans - vehicular, pedestrian, service (within port) 10 Calendar Days (7/7) 21-Sep-22 A 30-Sep-22 A
171 SP-PH2-2580B Prepare Concept Plans - multi story car parking building (for 30,000 cars) & several open area truck parking within port 10 Calendar Days (7/7) 26-Sep-22 A 05-Oct-22 A
172 SP-PH2-2590 Prepare Concept Plans - Traffic Plans & Proposal (outside of port) 10 Calendar Days (7/7) 21-Sep-22 A 30-Sep-22 A
173 SP-PH2-2600 Prepare Concept Plans - Landscaping 17 Calendar Days (7/7) 26-Sep-22 A 12-Oct-22 A
174 SP-PH2-2610 Prepare Concept Plans, Elevations & Sections for new buildings 12 Calendar Days (7/7) 21-Sep-22 A 02-Oct-22 A
175 Workshop, Presentations, Review, Option Selections etc. 112 29-Sep-22 A 18-Jan-23 234
176 SP-PH2-2700 Interdisciplinary Design Review of all Concept Plans 5 Calendar Days (7/7) 13-Oct-22 A 17-Oct-22 A
177 SP-PH2-2750 Prepare Cost estimates for the 3 Options 12 Calendar Days (7/7) 29-Sep-22 A 10-Oct-22 A
178 SP-PH2-2760 Prepare space analysis net to gross ratios 5 Calendar Days (7/7) 11-Oct-22 A 15-Oct-22 A
179 Options Review and Selection 93 18-Oct-22 A 18-Jan-23 93
180 SP-PH2-2770 Prepare workshop with KPA & Key decision makers 3 Calendar Days (7/7) 18-Oct-22 A 20-Oct-22 A
181 SP-PH2-2780 Presentation & Workshop with KPA on 3 options 1 Work Days (5/7) 23-Oct-22 A 23-Oct-22 A
182 SP-PH2-2790 Selection of preferred option with KPA to move forward with 5 Calendar Days (7/7) 24-Oct-22 A 28-Oct-22 A
183 SP-PH2-2800 SWOT analysis Workshop on 3 options 1 Calendar Days (7/7) 21-Oct-22 A 21-Oct-22 A
184 SP-PH2-2810 SWOT analysis Log & Review of items by all discipline leads 5 Calendar Days (7/7) 24-Oct-22 A 28-Oct-22 A
185 SP-PH2-2820 Incorporate all final comments & proposed changes 23 Calendar Days (7/7) 29-Oct-22 A 20-Nov-22 A
186 SP-PH2-2840 Collect all comments from all Stakeholders 78 Calendar Days (7/7) 30-Oct-22* 15-Jan-23
187 SP-PH2-2850 Incorporate all comments & proposed changes 78 Calendar Days (7/7) 02-Nov-22 18-Jan-23
188 Traffic Impact Assessment 6 Calendar Days (7/7) 11-Dec-22 16-Dec-22 6
189 Road Network & Zoning System Checks 3 Calendar Days (7/7) 11-Dec-22 13-Dec-22 3
190 SP-PH2-2900 Update of the network for the Project Impact area 3 Calendar Days (7/7) 11-Dec-22* 13-Dec-22
191 Matrix Estimation 3 Calendar Days (7/7) 14-Dec-22 16-Dec-22 3
192 SP-PH2-2910 Trip Matrix updating for consistency 3 Calendar Days (7/7) 14-Dec-22 16-Dec-22
193 Environmental Scoping Stage (if needed) 195 18-Aug-22 A 01-Mar-23 296
194 SP-PH2-3094 Submit EIA proposal and sub profile to KPA 0 Work Days (5/7) 18-Aug-22 A Submit EIA proposal and sub profile to KPA, 18-Aug-22 A
195 SP-PH2-3096 KPA review and approval of the proposal and sub profile 7 Calendar Days (7/7) 21-Aug-22 A 28-Aug-22 A
196 SP-PH2-3100 Data Collection 58 Calendar Days (7/7) 28-Aug-22 A 25-Oct-22 A
197 SP-PH2-3120 Preparation of scoping report 14 Calendar Days (7/7) 25-Oct-22 A 08-Nov-22 A
198 SP-PH2-3130 Scoping Report Review 7 Calendar Days (7/7) 08-Nov-22 A 15-Nov-22 A
199 SP-PH2-3140 Update Scoping Report 23 Calendar Days (7/7) 15-Nov-22 A 08-Dec-22 A
200 SP-PH2-3150 Public participation in coordination with EPA (if needed) 15 Calendar Days (7/7) 01-Dec-22* 15-Dec-22
201 SP-PH2-3160 Update scoping report based on public participation (if needed) 16 Calendar Days (7/7) 15-Dec-22 30-Dec-22
202 SP-PH2-3180 Scoping Report Review and reply to Client by EPA 76 Calendar Days (7/7) 16-Dec-22 01-Mar-23
203 Phase 2 Deliverables 131 07-Aug-22 A 15-Dec-22 131
204 Monthly Progress Reports 85 Work Days (5/7) 09-Aug-22 A 06-Dec-22 A 85
205 SP-PH2-D-3200 Issue Monthly Progress Report No 3 (1st of Phase 2) 0 Work Days (5/7) 09-Aug-22 A Issue Monthly Progress Report No 3 (1st of Phase 2), 09-Aug-22 A
206 SP-PH2-D-3210 Issue Monthly Progress Report No 4 (2nd of Phase 2) 0 Work Days (5/7) 06-Sep-22 A Issue Monthly Progress Report No 4 (2nd of Phase 2), 06-Sep-22 A
207 SP-PH2-D-3220 Issue Monthly Progress Report No 5 (3rd of Phase 2) 0 Work Days (5/7) 06-Oct-22 A Issue Monthly Progress Report No 5 (3rd of Phase 2), 06-Oct-22 A
208 SP-PH2-D-3230 Issue Monthly Progress Report No 6 (4th of Phase 2) 0 Work Days (5/7) 06-Nov-22 A Issue Monthly Progress Report No 6 (4th of Phase 2), 06-Nov-22 A
209 SP-PH2-D-3390 Issue Monthly Progress Report No 7 (5th of Phase 2) 0 Work Days (5/7) 06-Dec-22 A Issue Monthly Progress Report No 7 (5th of Phase 2), 06-Dec-22 A
210 Schedule/Report/Presentation 32 10-Nov-22 A 11-Dec-22 32
211 SP-PH2-D-3240 Updated Work Program Scheule and submit to KPA 8 Calendar Days (7/7) 04-Dec-22* 11-Dec-22
212 SP-PH2-D-3250 Update Phase Man-Month Input Report and submit to KPA 8 Calendar Days (7/7) 04-Dec-22* 11-Dec-22
213 SP-PH2-D-3260 Presentation of Phase 2 Report 1 Work Days (5/7) 20-Nov-22 A 20-Nov-22 A
214 SP-PH2-D-3270 Prepared 3D Animations for three options 32 Calendar Days (7/7) 10-Nov-22* 11-Dec-22
215 SP-PH2-D-3280 Prepare & submit Coastal Modeling Report 5 Calendar Days (7/7) 10-Nov-22 A 14-Nov-22 A
216 Phase 2 Report 131 07-Aug-22 A 15-Dec-22 131
217 SP-PH2-D-3300 Preparation & Submission of the M/P and the design alternatives 65 Calendar Days (7/7) 07-Aug-22 A 10-Oct-22 A
218 SP-PH2-D-3310 Finalize M/P and the design alternatives 5 Calendar Days (7/7) 06-Oct-22 A 10-Oct-22 A
219 SP-PH2-D-3320 Submit M/P and Design Alternatives Report to KPA 0 Work Days (5/7) 20-Nov-22 A Submit M/P and Design Alternatives Report to KPA, 20-Nov-22 A
220 SP-PH2-D-3330 1st Review and comments by KPA on M/P and Design alternatives 15 Calendar Days (7/7) 20-Nov-22 A 04-Dec-22 A
221 SP-PH2-D-3340 Apply KPA Comments & Modification and resubmit 8 Calendar Days (7/7) 04-Dec-22* 11-Dec-22
222 SP-PH2-D-3350 2nd Review and comments by KPA on M/P and Design alt ernatives 5 Calendar Days (7/7) 11-Dec-22 15-Dec-22
223 PHASE 3: DESIGN DEVELOPMENT (Selected Option) (96 Days) 226 17-Dec-22 30-Jul-23 226

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 4 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
224 Phase 3 Initials 90 18-Dec-22 17-Mar-23 90
225 SP-PH3-3400 Agreement from KPA to start with Phase 3 and Close out of Phase 2 1 Work Days (5/7) 18-Dec-22 18-Dec-22
226 SP-PH3-3410 Internal workshop on chosen option to commence design 1 Calendar Days (7/7) 19-Dec-22 19-Dec-22
227 SP-PH3-3420 Meet national council for culture, Arts and Literature 1 Work Days (5/7) 22-Jan-23* 22-Jan-23
228 Complementary/Supplementary data /Investigations (GI) 83 25-Dec-22 17-Mar-23 83
229 Geotechnical Investigations 83 25-Dec-22 17-Mar-23 83
230 SP-PH3-2194 Submit GI study proposal and sub profile to KPA 0 Work Days (5/7) 25-Dec-22* Submit GI study proposal and sub profile to KPA, 25-Dec-22*
231 SP-PH3-2196 KPA review and approval of the proposal and sub profile 9 Calendar Days (7/7) 25-Dec-22 02-Jan-23
232 SP-PH3-2200A GI Tender 9 Calendar Days (7/7) 02-Jan-23 10-Jan-23
233 SP-PH3-2210 Mobilization of Contractor/GI team/equipments 14 Calendar Days (7/7) 10-Jan-23 23-Jan-23
234 SP-PH3-2260 Site Investigations (Boreholes & CPT) - Spot Checks 14 Calendar Days (7/7) 24-Jan-23 06-Feb-23
235 SP-PH3-2270 Laboratory Testing - Spot Checks 21 Calendar Days (7/7) 08-Feb-23 28-Feb-23
236 SP-PH3-2280 Submit Borehole test (Soil Test Report) to KPA 0 Work Days (5/7) 28-Feb-23 Submit Borehole test (Soil Test Report) to KPA, 28-Feb-23
237 SP-PH3-2290 Submit Site Plan and Locations of Boreholes to KPA 0 Work Days (5/7) 28-Feb-23 Submit Site Plan and Locations of Boreholes to KPA, 28-Feb-23
238 SP-PH3-2295 KPA review and approval of Borehole site plan 7 Calendar Days (7/7) 01-Mar-23 07-Mar-23
239 SP-PH3-2300 Preparation of the Geotechnical Factual Report (GFR) 5 Calendar Days (7/7) 01-Mar-23 05-Mar-23
240 SP-PH3-2310 Review of the GFR 2 Calendar Days (7/7) 08-Mar-23 09-Mar-23
241 SP-PH3-2320 Preparation of the Geotechnical Investigation Report (GIR) 5 Calendar Days (7/7) 10-Mar-23 14-Mar-23
242 SP-PH3-2330 Review of the GIR 2 Calendar Days (7/7) 15-Mar-23 16-Mar-23
243 SP-PH3-2340 Issue of the GIR 1 Calendar Days (7/7) 17-Mar-23 17-Mar-23
244 Traffic Impact Assessment (Cont... from Phase 2) 29 Calendar Days (7/7) 28-Dec-22 25-Jan-23 29
245 Model Calibration & Validation 10 Calendar Days (7/7) 28-Dec-22 06-Jan-23 10
246 SP-PH2-2930 Iterative Calibration of Model 4 Calendar Days (7/7) 01-Jan-23 04-Jan-23
247 SP-PH3-2920 Iterative assignment running with network & adjustment 4 Calendar Days (7/7) 28-Dec-22 31-Dec-22
248 SP-PH3-2940 Estimate Base Year Matrix 2 Calendar Days (7/7) 05-Jan-23 06-Jan-23
249 Development of Traffic Model 10 Calendar Days (7/7) 07-Jan-23 16-Jan-23 10
250 SP-PH3-2950 Traffic Analysis Zone System & Road Hierarchy 3 Calendar Days (7/7) 07-Jan-23 09-Jan-23
251 SP-PH3-2960 Trip Generation 3 Calendar Days (7/7) 10-Jan-23 12-Jan-23
252 SP-PH3-2970 Trip Distribution & Modal Split 2 Calendar Days (7/7) 13-Jan-23 14-Jan-23
253 SP-PH3-2980 Trip Assignment 2 Calendar Days (7/7) 15-Jan-23 16-Jan-23
254 Review and Analysis 9 Calendar Days (7/7) 17-Jan-23 25-Jan-23 9
255 SP-PH3-2990 Traffic Analysis 2 Calendar Days (7/7) 17-Jan-23 18-Jan-23
256 SP-PH3-3000 Analysis of Traffic Circulation & Accessibility 2 Calendar Days (7/7) 19-Jan-23 20-Jan-23
257 SP-PH3-3010 Review of Proposed Concept Solution for the Mitigation Measures 5 Calendar Days (7/7) 21-Jan-23 25-Jan-23
258 Overall Site Civil Design Development 58 Calendar Days (7/7) 20-Dec-22 15-Feb-23 58
259 SP-PH3-3500 Prepare Earthworks models 15 Calendar Days (7/7) 20-Dec-22 03-Jan-23
260 SP-PH3-3505 Prepare fresh water supply systems and plans/drawings 21 Calendar Days (7/7) 04-Jan-23 24-Jan-23
261 SP-PH3-3510 Prepare irrigation water supply systems and plans/drawings 21 Calendar Days (7/7) 04-Jan-23 24-Jan-23
262 SP-PH3-3515 Prepare pavement designs and plans/drawings 21 Calendar Days (7/7) 04-Jan-23 24-Jan-23
263 SP-PH3-3520 Prepare fencing & gates designs/drawings 21 Calendar Days (7/7) 04-Jan-23 24-Jan-23
264 SP-PH3-3525 Prepare Geometric Road Designs (Road long/cross sections & details/drawings) 21 Calendar Days (7/7) 04-Jan-23 24-Jan-23
265 SP-PH3-3530 Structural Design of roads details/drawings 21 Calendar Days (7/7) 09-Jan-23 29-Jan-23
266 SP-PH3-3535 Prepare Site lighting system/network design/drawings 21 Calendar Days (7/7) 09-Jan-23 29-Jan-23
267 SP-PH3-3540 Prepare Site communication/telephone/IT network design/drawings 21 Calendar Days (7/7) 09-Jan-23 29-Jan-23
268 SP-PH3-3545 Prepare foul water management systems and plans/drawings 21 Calendar Days (7/7) 25-Jan-23 14-Feb-23
269 SP-PH3-3550 Prepare stormwater drainage systems and plans/drawings 21 Calendar Days (7/7) 25-Jan-23 14-Feb-23
270 SP-PH3-3555 Prepare Site landscape design/drawings 15 Calendar Days (7/7) 31-Jan-23 14-Feb-23
271 SP-PH3-3560 Car parking facilities design/drawings 15 Calendar Days (7/7) 31-Jan-23 14-Feb-23
272 SP-PH3-3570 Prepare outside signage design/drawings 15 Calendar Days (7/7) 01-Feb-23 15-Feb-23
273 KPA Technical Meetings 61 Work Days (5/7) 27-Dec-22 21-Mar-23 61
274 SP-PH3-3600 KPA Progress Meetings 16 1 Work Days (5/7) 27-Dec-22 27-Dec-22
275 SP-PH3-3610 KPA Progress Meetings 17 1 Work Days (5/7) 10-Jan-23 10-Jan-23
276 SP-PH3-3630 KPA Progress Meetings 18 1 Work Days (5/7) 24-Jan-23 24-Jan-23
277 SP-PH3-3660 KPA Progress Meetings 19 1 Work Days (5/7) 07-Feb-23 07-Feb-23
278 SP-PH3-3670 KPA Progress Meetings 20 1 Work Days (5/7) 21-Feb-23 21-Feb-23
279 SP-PH3-3680 KPA Progress Meetings 21 1 Work Days (5/7) 07-Mar-23 07-Mar-23

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 5 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
280 SP-PH3-4910 KPA Progress Meetings 22 1 Work Days (5/7) 21-Mar-23 21-Mar-23
281 Existing/New Buildings Design Development 58 Calendar Days (7/7) 17-Dec-22 12-Feb-23 58
282 Existing Buildings to be Refurbished, new building and New Port Warehousing 50 Calendar Days (7/7) 17-Dec-22 04-Feb-23 50
283 SP-PH3-3720 Prepare outline of new buildings 10 Calendar Days (7/7) 20-Dec-22 29-Dec-22
284 SP-PH3-3730S Architectural Works 35 Calendar Days (7/7) 17-Dec-22 20-Jan-23
285 SP-PH3-3810S Structures 50 Calendar Days (7/7) 17-Dec-22 04-Feb-23
286 SP-PH3-3910S Interior Design Works 30 Calendar Days (7/7) 17-Dec-22 15-Jan-23
287 SP-PH3-3980S Landscaping 35 Calendar Days (7/7) 17-Dec-22 20-Jan-23
288 SP-PH3-4030S Mechanical Design Works 30 Calendar Days (7/7) 17-Dec-22 15-Jan-23
289 SP-PH3-4110S Electrical Design Works 30 Calendar Days (7/7) 27-Dec-22 25-Jan-23
290 SP-PH3-4160S SMART Building Systems 30 Calendar Days (7/7) 01-Jan-23 30-Jan-23
291 SP-PH3-4210S Special Systems 30 Calendar Days (7/7) 02-Jan-23 31-Jan-23
292 Port Logistics & Operational Areas Development 45 Calendar Days (7/7) 20-Dec-22 02-Feb-23 45
293 SP-PH3-4270 Semi-automated container terminal 25 Calendar Days (7/7) 20-Dec-22 13-Jan-23
294 SP-PH3-4280 Customs inspecting zone 25 Calendar Days (7/7) 30-Dec-22 23-Jan-23
295 SP-PH3-4290 Terminal operating system 25 Calendar Days (7/7) 09-Jan-23 02-Feb-23
296 Reclamation/Marine Works (New Container Terminal) 55 Calendar Days (7/7) 20-Dec-22 12-Feb-23 55
297 New Container terminal marine work 55 Calendar Days (7/7) 20-Dec-22 12-Feb-23 55
298 SP-PH3-4400 Design and specification of the equipment/ cranes 15 Calendar Days (7/7) 20-Dec-22 03-Jan-23
299 SP-PH3-4410 Infilling Works 35 Calendar Days (7/7) 22-Dec-22 25-Jan-23
300 SP-PH3-4420 Geotechnical deign and Ground improvement Works 35 Calendar Days (7/7) 22-Dec-22 25-Jan-23
301 SP-PH3-4430 Coastal Structures 40 Calendar Days (7/7) 20-Dec-22 28-Jan-23
302 SP-PH3-4440 Marine design of the berth (quay wall and accessories) 40 Calendar Days (7/7) 04-Jan-23 12-Feb-23
303 Navigation Channel Update Works Design 35 Calendar Days (7/7) 04-Jan-23 07-Feb-23 35
304 SP-PH3-4450 Channel Design 35 Calendar Days (7/7) 04-Jan-23 07-Feb-23
305 SP-PH3-4460 Dredging Works for landside activities 30 Calendar Days (7/7) 04-Jan-23 02-Feb-23
306 Environmental Impact Assessment 165 Calendar Days (7/7) 16-Feb-23 30-Jul-23 165
307 SP-PH3-4500 Preparation & Submission of ESIA 29 Calendar Days (7/7) 16-Feb-23 16-Mar-23
308 SP-PH3-4510 ESIA Study Review by KEPA 32 Calendar Days (7/7) 16-Mar-23 16-Apr-23
309 SP-PH3-4520 Update ESIA Study 62 Calendar Days (7/7) 16-Apr-23 16-Jun-23
310 SP-PH3-4530 Submission to KEPA 1 Calendar Days (7/7) 16-Jun-23 16-Jun-23
311 SP-PH3-4540 ESIA Review (to be continued in Phase 4) 44 Calendar Days (7/7) 17-Jun-23 30-Jul-23
312 Workshop, Presentations, Review and Approvals etc. 15 Work Days (5/7) 09-Feb-23 01-Mar-23 15
313 SP-PH3-4600 Presentation of Design to all stakeholders i.e. Kuwait Municipality, KFF, MPW, MOC, MEW for Organizatio nal Approvals 15 Work Days (5/7) 09-Feb-23 01-Mar-23
314 SP-PH3-4610A Submission to Kuwait Municipality for Urban Planning department approval 15 Work Days (5/7) 09-Feb-23 01-Mar-23
315 SP-PH3-4610B Submission to stakeholders for Design approvals including (KFFD, MEW, PART, MOI, MPW) 15 Work Days (5/7) 09-Feb-23 01-Mar-23
316 Deliverables 95 18-Dec-22 22-Mar-23 95
317 Monthly Progress Reports 41 Work Days (5/7) 08-Jan-23 06-Mar-23 41
318 SP-PH3-D-5000 Issue Monthly Progress Report No 8 (1st of Phase 3) 0 Work Days (5/7) 08-Jan-23* Issue Monthly Progress Report No 8 (1st of Phase 3), 08-Jan-23*
319 SP-PH3-D-5010 Issue Monthly Progress Report No 9 (2nd of Phase 3) 0 Work Days (5/7) 06-Feb-23 Issue Monthly Progress Report No 9 (2nd of Phase 3), 06-Feb-23
320 SP-PH3-D-5020 Issue Monthly Progress Report No 10 (3rd of Phase 3) 0 Work Days (5/7) 06-Mar-23 Issue Monthly Progress Report No 10 (3rd of Phase 3), 06-Mar-23
321 Schedule/Report/Presentation 29 09-Feb-23 09-Mar-23 29
322 SP-PH3-D-5040 Presentation of Phase 3 Report & Associated Documents 1 Work Days (5/7) 09-Feb-23 09-Feb-23
323 SP-PH3-D-5050 Prepared 3D Animations for the selected/preferred option 8 Calendar Days (7/7) 02-Mar-23 09-Mar-23
324 SP-PH3-D-5060 Finalize and Submit Outline Specification Report 6 Work Days (5/7) 02-Mar-23 09-Mar-23
325 SP-PH3-D-5070 Finalize and Submit Cost Estimate Report 6 Work Days (5/7) 02-Mar-23 09-Mar-23
326 SP-PH3-D-5080 Finalize and submit Materials/Systems/Market/Implementation Report 6 Work Days (5/7) 02-Mar-23 09-Mar-23
327 SP-PH3-D-5090 Update and submit Work Program Scheule to KPA 6 Work Days (5/7) 02-Mar-23* 09-Mar-23
328 SP-PH3-D-5100 Update and submit Phase Man-Month Input Report to KPA 6 Work Days (5/7) 02-Mar-23 09-Mar-23
329 Phase 3 Report 95 18-Dec-22 22-Mar-23 95
330 SP-PH3-2830 Presentation/Workshop of Concept to Kuwait Municipality 1 Work Days (5/7) 15-Jan-23* 15-Jan-23
331 SP-PH3-D-5110 Phase 3 report preparation 54 Calendar Days (7/7) 18-Dec-22 09-Feb-23
332 SP-PH3-D-5120 Submit Phase 3 Report/Design Development Drawings to KPA 0 Work Days (5/7) 09-Feb-23 Submit Phase 3 Report/Design Development Drawings to KPA, 09-Feb-23
333 SP-PH3-D-5130 Review by KPA of Phase 3 Report & Associated Documents 15 Calendar Days (7/7) 09-Feb-23 23-Feb-23
334 SP-PH3-D-5140 Apply KPA Comments and Modifications and resubmit 15 Calendar Days (7/7) 23-Feb-23 09-Mar-23
335 SP-PH3-D-5150 ReSubmit Phase 3 Report/Design Development Drawings to KPA after comments incorporation 0 Work Days (5/7) 09-Mar-23 ReSubmit Phase 3 Report/Design Development Drawings to KPA after comment

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 6 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
336 SP-PH3-D-5160 Review by KPA of Phase 3 Report & Associated Documents/Approval 14 Calendar Days (7/7) 09-Mar-23 22-Mar-23
337 PHASE 4: IFC DRAWING & TENDER DOCUMENTS (223 Days) 223 23-Mar-23 31-Oct-23 223
338 Phase 4 Initials 2 23-Mar-23 24-Mar-23 2
339 SP-PH4-5500 Start with Phase 4 and Close out of Phase 3 1 Work Days (5/7) 23-Mar-23 23-Mar-23
340 SP-PH4-5510 Internal workshop to commence final design 1 Calendar Days (7/7) 24-Mar-23 24-Mar-23
341 KPA Technical Meetings 141 Work Days (5/7) 04-Apr-23 17-Oct-23 141
342 SP-PH4-5600 KPA Progress Meetings 23 1 Work Days (5/7) 04-Apr-23 04-Apr-23
343 SP-PH4-5610 KPA Progress Meetings 24 1 Work Days (5/7) 18-Apr-23 18-Apr-23
344 SP-PH4-5620 KPA Progress Meetings 25 1 Work Days (5/7) 02-May-23 02-May-23
345 SP-PH4-5630 KPA Progress Meetings 26 1 Work Days (5/7) 16-May-23 16-May-23
346 SP-PH4-5640 KPA Progress Meetings 27 1 Work Days (5/7) 30-May-23 30-May-23
347 SP-PH4-5650 KPA Progress Meetings 28 1 Work Days (5/7) 13-Jun-23 13-Jun-23
348 SP-PH4-5660 KPA Progress Meetings 29 1 Work Days (5/7) 27-Jun-23 27-Jun-23
349 SP-PH4-5670 KPA Progress Meetings 30 1 Work Days (5/7) 11-Jul-23 11-Jul-23
350 SP-PH4-5680 KPA Progress Meetings 31 1 Work Days (5/7) 25-Jul-23 25-Jul-23
351 SP-PH4-5690 KPA Progress Meetings 32 1 Work Days (5/7) 08-Aug-23 08-Aug-23
352 SP-PH4-5700 KPA Progress Meetings 33 1 Work Days (5/7) 22-Aug-23 22-Aug-23
353 SP-PH4-5710 KPA Progress Meetings 34 1 Work Days (5/7) 05-Sep-23 05-Sep-23
354 SP-PH4-5720 KPA Progress Meetings 35 1 Work Days (5/7) 19-Sep-23 19-Sep-23
355 SP-PH4-5730 KPA Progress Meetings 36 1 Work Days (5/7) 03-Oct-23 03-Oct-23
356 SP-PH4-6620 KPA Progress Meetings 37 1 Work Days (5/7) 17-Oct-23 17-Oct-23
357 Final Design and Working Drawings 47 Calendar Days (7/7) 25-Mar-23 10-May-23 47
358 Overall Site Civil Works 30 Calendar Days (7/7) 25-Mar-23 23-Apr-23 30
359 SP-PH4-5800 Overall Site Works 30 Calendar Days (7/7) 25-Mar-23 23-Apr-23
360 Buildings and Warehouses 47 Calendar Days (7/7) 25-Mar-23 10-May-23 47
361 SP-PH4-5810 Architectural Works 25 Calendar Days (7/7) 25-Mar-23 18-Apr-23
362 SP-PH4-5820 Structures 25 Calendar Days (7/7) 30-Mar-23 23-Apr-23
363 SP-PH4-5830 Interior Design Works 25 Calendar Days (7/7) 04-Apr-23 28-Apr-23
364 SP-PH4-5840 Landscaping 20 Calendar Days (7/7) 11-Apr-23 30-Apr-23
365 SP-PH4-5850 Mechanical Design 25 Calendar Days (7/7) 09-Apr-23 03-May-23
366 SP-PH4-5860 Electrical Design 25 Calendar Days (7/7) 09-Apr-23 03-May-23
367 SP-PH4-5870 SMART Building Systems 20 Calendar Days (7/7) 14-Apr-23 03-May-23
368 SP-PH4-5880 Special Systems 20 Calendar Days (7/7) 16-Apr-23 05-May-23
369 SP-PH4-5890 New Port Warehousing 25 Calendar Days (7/7) 16-Apr-23 10-May-23
370 Reclamation/Coastal Works (New Container Terminal) and Navigation Channel 27 Calendar Days (7/7) 14-Apr-23 10-May-23 27
371 SP-PH4-5900 Reclamation Update 25 Calendar Days (7/7) 14-Apr-23 08-May-23
372 SP-PH4-5905 Marine works deign including the quay wall, accessories and crane beam 25 Calendar Days (7/7) 14-Apr-23 08-May-23
373 SP-PH4-5910 Dredging works Update 25 Calendar Days (7/7) 14-Apr-23 08-May-23
374 SP-PH4-5920 Navigation Channel Update 25 Calendar Days (7/7) 16-Apr-23 10-May-23
375 Port Logistics & Operational Development 25 Calendar Days (7/7) 16-Apr-23 10-May-23 25
376 SP-PH4-5950 Port Logistics & Operational Development 25 Calendar Days (7/7) 16-Apr-23 10-May-23
377 Authorities Approvals & Stakeholder Reviews & Workshops 26 Work Days (5/7) 08-May-23 12-Jun-23 26
378 SP-PH4-6000 Presentation/Workshop of Detail Design to stakeholders i.e. Kuwait Municipality, KFF, MPW, MOC and MEW 7 Work Days (5/7) 08-May-23 16-May-23
379 SP-PH4-6010A Submission to Kuwait Municipality for Urban Planning department approval 14 Work Days (5/7) 17-May-23 05-Jun-23
380 SP-PH4-6010B Submission to stakeholders for Design approvals including (KFFD, MEW, PART, MOI, MPW) 14 Work Days (5/7) 17-May-23 05-Jun-23
381 SP-PH4-6100 Collect all comments from all Stakeholders 5 Work Days (5/7) 06-Jun-23 12-Jun-23
382 Tender Documents 102 Calendar Days (7/7) 25-Mar-23 04-Jul-23 102
383 Procedure and Conditions of Contract 49 Calendar Days (7/7) 14-Apr-23 01-Jun-23 49
384 SP-PH4-6200 Prepare Tendering Procedure 15 Calendar Days (7/7) 14-Apr-23 28-Apr-23
385 SP-PH4-6210 Present Tendering Procedure to KPA 1 Calendar Days (7/7) 29-Apr-23 29-Apr-23
386 SP-PH4-6220 Finalize Tendering Procedure to submit to KPA for approval 10 Calendar Days (7/7) 30-Apr-23 09-May-23
387 SP-PH4-6230 Prepare Conditions of Contract 25 Calendar Days (7/7) 29-Apr-23 23-May-23
388 SP-PH4-6240 Finalize Conditions of Contract to submit to KPA for approval 10 Calendar Days (7/7) 23-May-23 01-Jun-23
389 Technical Documents 102 Calendar Days (7/7) 25-Mar-23 04-Jul-23 102
390 SP-PH4-4850 Technical Specifications 20 Calendar Days (7/7) 25-Mar-23 13-Apr-23
391 SP-PH4-6300 General Specifications 20 Calendar Days (7/7) 25-Mar-23 13-Apr-23

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 7 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
392 SP-PH4-6310 Particular Specifications 40 Calendar Days (7/7) 14-Apr-23 23-May-23
393 SP-PH4-6320 Drawings 25 Calendar Days (7/7) 11-May-23 04-Jun-23
394 SP-PH4-6330 Bill of Quantities 30 Calendar Days (7/7) 16-May-23 14-Jun-23
395 SP-PH4-6340 Analysis of Prices 15 Calendar Days (7/7) 05-Jun-23 19-Jun-23
396 SP-PH4-6350 Addendum (if any) 10 Calendar Days (7/7) 20-Jun-23 29-Jun-23
397 SP-PH4-6360 Technical Requirements 10 Calendar Days (7/7) 25-Jun-23 04-Jul-23
398 Finalization of Phase 4 95 Calendar Days (7/7) 19-Apr-23 22-Jul-23 95
399 SP-PH4-6400 Prepare Architecture Report Section 10 Calendar Days (7/7) 19-Apr-23 28-Apr-23
400 SP-PH4-6410 Prepare Overall Civil Report Section 10 Calendar Days (7/7) 24-Apr-23 03-May-23
401 SP-PH4-6420 Prepare Structural Report Section 10 Calendar Days (7/7) 24-Apr-23 03-May-23
402 SP-PH4-6430 Prepare HVAC Report Section 10 Calendar Days (7/7) 04-May-23 13-May-23
403 SP-PH4-6440 Prepare Plumbing Report Section 10 Calendar Days (7/7) 04-May-23 13-May-23
404 SP-PH4-6450 Prepare Electrical Report Section 10 Calendar Days (7/7) 04-May-23 13-May-23
405 SP-PH4-6460 Prepare SMART Building Report Section 10 Calendar Days (7/7) 04-May-23 13-May-23
406 SP-PH4-6470 Prepare Reclamation & Coastal Report Section 10 Calendar Days (7/7) 09-May-23 18-May-23
407 SP-PH4-6480 Prepare Navigation Channel Report Section 10 Calendar Days (7/7) 11-May-23 20-May-23
408 SP-PH4-6490 Prepare New Warehousing Report Section 10 Calendar Days (7/7) 11-May-23 20-May-23
409 SP-PH4-6500 Prepare Port Logistics & Operational Report Section 10 Calendar Days (7/7) 11-May-23 20-May-23
410 SP-PH4-6510 Summary Report 5 Calendar Days (7/7) 21-May-23 25-May-23
411 SP-PH4-6520 Incorporate all comments & proposed changes 8 Calendar Days (7/7) 13-Jun-23 20-Jun-23
412 SP-PH4-6540 Regulatory Approvals Report Section 5 Calendar Days (7/7) 21-Jun-23 25-Jun-23
413 SP-PH4-6550 Prepare Material Report 15 Calendar Days (7/7) 29-May-23 12-Jun-23
414 SP-PH4-6560 Prepare Sample Boards 25 Calendar Days (7/7) 26-May-23 19-Jun-23
415 SP-PH4-6570 Prepare 3D Animations 20 Calendar Days (7/7) 13-Jun-23 02-Jul-23
416 SP-PH4-6580 Prepare scaled (As-to-Be Built Model) 40 Calendar Days (7/7) 13-Jun-23 22-Jul-23
417 SP-PH4-6590 Interdisciplinary Design Review of all Plans 5 Calendar Days (7/7) 21-May-23 25-May-23
418 SP-PH4-6600 Peer Reviews of all Plans 5 Calendar Days (7/7) 26-May-23 30-May-23
419 SP-PH4-6610 Incorporate Comments from IDC & Peer Reviews 5 Calendar Days (7/7) 31-May-23 04-Jun-23
420 Deliverables 223 23-Mar-23 31-Oct-23 223
421 Monthly Progress Reports 131 Work Days (5/7) 06-Apr-23 08-Oct-23 131
422 SP-PH4-D-6700 Issue Monthly Progress Report No 11 (1st of Phase 4) 0 Work Days (5/7) 06-Apr-23 Issue Monthly Progress Report No 11 (1st of Phase 4), 06-Apr-23
423 SP-PH4-D-6710 Issue Monthly Progress Report No 12 (2nd of Phase 4) 0 Work Days (5/7) 07-May-23 Issue Monthly Progress Report No 12 (2nd of Phase 4), 07-May-23
424 SP-PH4-D-6720 Issue Monthly Progress Report No 13 (3rd of Phase 4) 0 Work Days (5/7) 06-Jun-23 Issue Monthly Progress Report No 13 (3rd of Phase 4), 06-J
425 SP-PH4-D-6730 Issue Monthly Progress Report No 14 (4th of Phase 4) 0 Work Days (5/7) 06-Jul-23 Issue Monthly Progress Report No 14 (4th of Phase
426 SP-PH4-D-6740 Issue Monthly Progress Report No 15 (5th of Phase 4) 0 Work Days (5/7) 06-Aug-23 Issue Monthly Progress Report No 15 (5th of
427 SP-PH4-D-6750 Issue Monthly Progress Report No 16 (6th of Phase 4) 0 Work Days (5/7) 06-Sep-23 Issue Monthly Progress Report No 16
428 SP-PH4-D-6760 Issue Monthly Progress Report No 17 (7th of Phase 4) 0 Work Days (5/7) 08-Oct-23 Issue Monthly Progress Repo
429 Schedule/Report/Presentation 103 Work Days (5/7) 21-May-23 10-Oct-23 103
430 SP-PH4-D-6800 Presentation of Phase 4 Report & Videos to KPA 1 Work Days (5/7) 21-May-23 21-May-23
431 SP-PH4-D-6810 Fnalize and submit Technical Specification Report to KPA 10 Work Days (5/7) 24-May-23 06-Jun-23
432 SP-PH4-D-6820 Finalize and Submit Working Drawing Report to KPA 10 Work Days (5/7) 05-Jun-23 18-Jun-23
433 SP-PH4-D-6830 Finalie and submit Bill of Quantities Report 10 Work Days (5/7) 15-Jun-23 28-Jun-23
434 SP-PH4-D-6840 Finalize and submit Cost Estimate Report 10 Work Days (5/7) 20-Jun-23 03-Jul-23
435 SP-PH4-D-6850 Submit Sample Boards (Arc, Interior, Lanscape) 5 Work Days (5/7) 20-Jun-23 26-Jun-23
436 SP-PH4-D-6860 Finalize and submit As-to-Be Built Model 10 Work Days (5/7) 23-Jul-23 03-Aug-23
437 SP-PH4-D-6890 Update and submit Phase Man-Month Input Report to KPA 7 Work Days (5/7) 02-Oct-23 10-Oct-23
438 Phase 4 Report 223 23-Mar-23 31-Oct-23 223
439 SP-PH4-D-7000 Preparation of Phase 4 Drawings/Reports and base map in GIS format 59 Calendar Days (7/7) 23-Mar-23 20-May-23
440 SP-PH4-D-7010 Submit Drawings/Reports to KPA (1st submission) 0 Work Days (5/7) 21-May-23 Submit Drawings/Reports to KPA (1st submission), 21-May-23
441 SP-PH4-D-7020 Review by KPA of Phase 4 Drawings/Reports 14 Calendar Days (7/7) 21-May-23 03-Jun-23
442 SP-PH4-D-7030 Apply KPA Comments & Modification including finalization of execution Contract Documents (1st review) 30 Calendar Days (7/7) 05-Jun-23 04-Jul-23
443 SP-PH4-D-7040 ReSubmit Phase 4 Drawings/Reports and Contract Document to KPA after comments incorporation (2nd submission) 0 Work Days (5/7) 04-Jul-23 ReSubmit Phase 4 Drawings/Reports and Contract D
444 SP-PH4-D-7050 Review by KPA on amended Drawings/Reports and Contract Documents (2nd review) 14 Calendar Days (7/7) 05-Jul-23 18-Jul-23
445 SP-PH4-D-7060 Apply KPA Comments & Modification 45 Calendar Days (7/7) 19-Jul-23 01-Sep-23
446 SP-PH4-D-7070A Obtaining design planning approval from KM urban planning department 45 Calendar Days (7/7) 19-Jul-23 01-Sep-23
447 SP-PH4-D-7070B Obtaining design approval from the following stakeholders (KFFD, MEW, PART, MOI, MPW) 45 Calendar Days (7/7) 19-Jul-23 01-Sep-23

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 8 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR
Client: Consultant: 
THE CONSULTANCY STUDY AND DESIGN OF SHUWAIKH PORT

KUWAIT PORTS AUTHORITY (KPA) DETAILED WORK PROGRAM (REV 04)               
# Activity ID Activity Name Duration Calendar Start Finish 2022 2023 2024
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
448 SP-PH4-D-7070C Obtain building permit from KPA building permit department 29 Calendar Days (7/7) 03-Sep-23 01-Oct-23
449 SP-PH4-D-7080 Submit amended Drawings/Reports, Contract Documents and permits (3rd submission) 0 Work Days (5/7) 03-Sep-23 Submit amended Drawings/Reports, C
450 SP-PH4-D-7090 Review and comments by KPA on Drawings/Reports, Contract Documents and permits (3rd review) 7 Calendar Days (7/7) 03-Sep-23 09-Sep-23
451 SP-PH4-D-7100 Apply KPA Comments & Modification including finalization of Tender Documents 32 Calendar Days (7/7) 09-Sep-23 10-Oct-23
452 SP-PH4-D-7110 Submit final amended Drawings/Reports, Contract Documents, Reports, permits etc. (4th submission) 0 Work Days (5/7) 10-Oct-23 Submit final amended Drawin
453 SP-PH4-D-7120 Final Review by KPA on amended Drawings/Reports, Contract Documents, Reports, permits & approval (4th review/approval 21 Calendar Days (7/7) 11-Oct-23 31-Oct-23
454 SP-PH4-D-7130 Close out Phase 4 1 Calendar Days (7/7) 31-Oct-23 31-Oct-23
455 PHASE 5 - EVALUATION OF BIDS 15 Calendar Days (7/7) 15-Nov-23 29-Nov-23 15

456 Prepare Balanced BOQ 15 Calendar Days (7/7) 15-Nov-23 29-Nov-23 15


457 Prepare Contract Documents 15 Calendar Days (7/7) 15-Nov-23 29-Nov-23 15
458 Prepare Tender Analysis Report 15 Calendar Days (7/7) 15-Nov-23 29-Nov-23 15

Commencement Date        : 10-May-22 Preliminaries Level of Effort Date Revision Checked Appro...


Notes: 1. Calendar Days (7/7) - Duration without off days/weekends
Duration                             : 540 Calendar Days 15-May-22 DETAILED WORK PROGRAM (REV 00) MT AR
Phase 1 Tasks Summary             2. Work Days (5/7) - 5 work days per week
Completion Date                : 31-Oct-2023        25-May-22 DETAILED WORK PROGRAM (REV 01) MT AR
Phase 2 Tasks Milestone             3. The schedule shall be updated, reviewed & adjuested at end of each Phase
02-Jun-2022 DETAILED WORK PROGRAM (REV 02) MT AR
  Phase 3 Tasks 31-Jul-2022 DETAILED WORK PROGRAM (REV 03) MT AR
Page 9 of 9
© Oracle Corporation   Phase 4 Tasks 08-Dec-2022 DETAILED WORK PROGRAM (REV 04) MT AR