#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MARCH-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Ansar/Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Mar-22 07. 30 05. 30 10 - - 11KV BS1 RMD With dewa completed and Capacitor bank asbuilt drawings in progress
6-Mar-22 - - - - - --------HOLIDAY----------
8-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal
9-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal
10-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal
12-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal
13-Mar-22 - - - - - --------HOLIDAY----------
15-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works and final checks internal at 11kV SWGR
20-Mar-22 - - - - - --------HOLIDAY----------
27-Mar-22 - - - - - --------HOLIDAY----------
4-Dec-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - Incomer completed with AFRY
5-Dec-21 07. 30 05. 30 10 - - ES Interlocks Ferrules Checks verified with AFRY( BUS-1 --Without Feeders)
6-Dec-21 07. 30 05. 30 10 - - ES Interlocks Ferrules Checks verified with AFRY( BUS-2 and BUS3 --Without Feeders) - Completed
7-Dec-21 07. 30 05. 30 10 - - ES Interlock Ferrules Checks verified with AFRY( BUS-1,2,3 --With metering Feeders) - Completed
8-Dec-21 07. 30 05. 30 10 - - CB Close Interlock Ferrules Checks verified with AFRY( BUS-1 --Without metering Feeders) -
Completed
1) CB Close Interlock Ferrules Checks verified with AFRY( BUS-2 and BUS3 --Without metering
9-Dec-21 07. 30 05. 30 10 - - Feeders) - Completed
2) ID 121(Name plate Details) verified for BS1, Capacitor and With metering completed with DEWA
11-Dec-21 07. 30 05. 30 10 - - CB Close Interlock Ferrules Checks verified with AFRY(With metering Feeders) - Completed
12-Dec-21 07. 30 05. 30 10 - - CB Close Interlock Ferrules Checks verified with AFRY(Capacitor Feeders) - In Progress
13-Dec-21 07. 30 05. 30 10 - - 11KV SWGR MMS Data verification with AFRY Completed
14-Dec-21 07. 30 05. 30 10 - - Rack-in Interlock checks - With and Without metering Completed
15-Dec-21 07. 30 05. 30 10 - - ES Interlock checks - With and Without metering Completed
16-Dec-21 07. 30 05. 30 10 - - CB Closing Interlocks checks - With and Without metering Completed
18-Dec-21 07. 30 05. 30 10 - - 11KV SWGR EMS Data with AFRY In Progress and Capacitor Bank MMS Data with AFRY In Progress
19-Dec-21 07. 30 05. 30 10 - - Interlock ferrule checks for Bus Earth switches
20-Dec-21 07. 30 05. 30 10 - - BS-1,2 Rack-in, CB Closing and Bus Earth switches Interlocks dewa witness completed
Capacitor bank CB Interlock checks ferrule verification Completed with Consultant and Incomer In
21-Dec-21 07. 30 05. 30 10 - -
Progress
22-Dec-21 07. 30 05. 30 10 - - Capacitor bank CB, ES and Rack-in Interlock checks - DEWA Witness In Progress
23-Dec-21 07. 30 05. 30 10 - - Interlock ferrulle checks Incomers- Consultant Witness Completed
25-Dec-21 07. 30 05. 30 10 - - Capacitor bank CB, ES and Rack-in Interlock checks Internal and RMD/Test report works
Interlock test at Incomers completed and Capacitor bank feeders except F01, F49 DEWA Witness
26-Dec-21 07. 30 05. 30 10 - -
Completed
27-Dec-21 07. 30 05. 30 10 - - C.BANK Documentation
- - - - -
1-Mar-21
- - - - -
2-Mar-21
- - - - -
3-Mar-21
4-Mar-21 - - - - -
- - - - - --------FRIDAY----------
5-Mar-21
- - - - -
6-Mar-21
7-Mar-21 - - - - -
10-Mar-21 07. 30 05. 30 10 - - 132kv primary injection supporting & 132kv gis lcc ferrule check - 2 bays
11-Mar-21 07. 30 05. 30 10 - - scms signal list source point updation(lvac + 132kv gis)
12-Mar-21 - - - - - --------FRIDAY----------
17-Mar-21 07. 30 05. 30 10 - - common alarms verification upto scms(lvac,dc ch 1,dc ch2,el dc,avr)
07. 30 05. 30 10 - - common alarms verification upto scms(400&132kvfrp,metering panel,and schedule updation)
18-Mar-21
19-Mar-21 - - - - - --------FRIDAY----------
1.schedule updation for telecom,fire alarm,hvac,solar panel & emergency dg
07. 30 05. 30 10 - - 2.132kv wiring checks
20-Mar-21
07. 30 05. 30 10 - - 132kv signals & operations typical checks - cable feeder completed,ict - inprogress
21-Mar-21
132kv signals & operations typical checks - ict completed,bus coupler - completed,reactor -
07. 30 05. 30 10 - - inprogress
22-Mar-21
07. 30 05. 30 10 - - 132kv signals & operations typical checks - reactor completed,bus section - completed
23-Mar-21
26-Mar-21 - - - - - --------FRIDAY----------
30-Mar-21 07. 30 05. 30 10 - - 132kV VSS scheme check - AC Circuit internal inprogress
31-Mar-21 07. 30 05. 30 10 - - 132kV VSS scheme check - AC Circuit internal inprogress
1-Apr-21 07. 30 05. 30 10 - - 132kV VSS scheme check - AC Circuit internal Operations completed
2-Apr-21 - - - - - --------FRIDAY----------
3-Apr-21 07. 30 05. 30 10 - - 132kV VSS scheme check - DC Circuit internal inprogress
5-Apr-21 07. 30 05. 30 10 - - 132KV Measurements verifed with SCMS eng. - cable feeder completed
6-Apr-21 07. 30 05. 30 10 - - 132kV control operations verified with SCMS Engineer E05 to E16 completed except E 14
8-Apr-21 07. 30 05. 30 10 - - 1.400kV control operations and signals verified with SCMS Engineer C05,C03 - completed
9-Apr-21 - - - - - --------FRIDAY----------
10-Apr-21 07. 30 05. 30 10 - - 400kv VSS wiring rectification works in progress (red ticks points completed)
1.400kV buscoupler & bussection control operations and signals verified with SCMS Engineer 2.132
11-Apr-21 07. 30 05. 30 10 - - kv VSS ferrule rectification inprogress
1.400kv VSS voltage injection measurements ICT,BC,BS typical feeders verified with SCMS engineer
13-Apr-21 07. 00 2.00 7 - - 2.400kv control operations C02 to C08 bays verified
16-Apr-21 - - - - - --------FRIDAY----------
25-Apr-21 07. 00 2.00 7 - - DZ3, DZ4 132kV BBP Sensitivity test completed. - supporting
26-Apr-21 07. 00 2.00 7 - - CZ, DZ1 132kV BBP Sensitivity test completed.- supporting
27-Apr-21 07. 00 2.00 7 - - DZ2 132kV BBP Sensitivity test completed.- supporting
30-Apr-21 - - - - - --------FRIDAY----------
4-May-21 07. 00 2.00 7 - - 400kV VSS sync.checks verified (LONG Transfer & Short transfer)
7-May-21 - - - - - --------FRIDAY----------
10-May-21 07. 00 2.00 7 - - 400kV C02 ,C04 Main 1 relay testing co ordination- completed
11-May-21 - - - - - HOLIDAY
12-May-21 - - - - - HOLIDAY
13-May-21 - - - - - HOLIDAY
14-May-21 - - - - - --------FRIDAY----------
15-May-21 - - - - - HOLIDAY
16-May-21 07. 30 05. 30 10 - - 400kV C05 Main 1 relay testing co ordination- completed
1.ScMs co ordination (132kv ,400kv main relay communication checking)
17-May-21 07. 30 05. 30 10 - - 2.PDMS panel signals wiring done and signal checked upto hmi
18-May-21 07. 30 05. 30 10 - - SCMS co ordination
1.SCMS co ordination
19-May-21 07. 30 05. 30 10 - - 2 LVAC - EMVS switch fixing
3.400kv DCDB.1 ELR relay replacement co ordination
21-May-21 - - - - - --------FRIDAY----------
22-May-21
23-May-21
24-May-21
25-May-21
26-May-21
27-May-21
28-May-21
29-May-21
30-May-21
31-May-21
2-May-21
3-May-21
4-May-21
5-May-21
6-May-21
7-May-21
8-May-21
9-May-21
10-May-21
11-May-21
12-May-21
13-May-21
14-May-21
15-May-21
16-May-21
17-May-21
18-May-21
19-May-21
20-May-21
21-May-21
28-May-21 - - - - - --------FRIDAY----------
3-Aug-21 07. 30 05. 30 10 - - 1.11kv SWGR - FAT MOM Verfication- 5 POINTS completed
6-Aug-21 - - - - - --------FRIDAY----------
9-Aug-21 07. 30 05. 30 10 - - 1.HLDB - Outgoing cable verification- 14 cables ready to witness
2.11kv SWGR - FAT MOM Verfication - with DEWA - 134 cleared with DEWA
13-Aug-21 - - - - - --------FRIDAY----------
14-Aug-21 07. 30 05. 30 10 - - 1.CB Motor checks with 85% & 110% with afry.
2.Site note issues Rectification co - ordiantion with O&M.
15-Aug-21 07. 30 05. 30 10 - - 1.HLDB - Outgoing cable verification- 15 No of cables completed with afry.
2.11kV SWGR CT FAT Report Verification - inprogress
17-Aug-21 07. 30 05. 30 10 - - 1.HLDB & LVAC SLD Verification completed with AFRY.
2.VCB & CT FAT Reports Verification - inprogress
21-Aug-21 07. 30 05. 30 10 - - 1.HLDB - Outgoing cable verification - 7 cables completed with afry
2.132kV MMS DATA Updation.
22-Aug-21 07. 30 05. 30 10 - - 1.11kV SWGR _ FAT comment - 1 point cleared with AFRY.
2.11kV SWGR _CT Ferrules verification - inprogress
23-Aug-21 07. 30 05. 30 10 - - 1.11kV SWGR _ FAT comment - 3 point cleared with AFRY.
2.11kV SWGR _CT Ferrules verification - inprogress
26-Aug-21 07. 30 05. 30 10 - - 1.11kV Cable Drum test. - 3 drums completed with dewa.
2.11kV - Aux.relay ferrule Verification - Inprogress.
27-Aug-21 - - - - - --------FRIDAY----------
28-Aug-21 07. 30 05. 30 10 - - 1.11kV primary Drawing Verification - Section view - inprogress
29-Aug-21 07. 30 05. 30 10 - - 1.11kV primary Drawing Verification
30-Aug-21 - - - - - LEAVE
31-Aug-21 - - - - - LEAVE
1.11kv
SWGR -
Checklis
t
Verificat
ion
conplete
d
1.11kv
SWGR -
FAT
MOM
Verficati
on- 5
POINTS
complet
ed
1.11kv
SWGR -
FAT
MOM
Verficati
on- 4
POINTS
complet
ed
2.11kV
SWGR -
Compon
ent List
Verficati
on
inprogre
ss
3.Label
preparat
ion for
Snag
points.
1.11kv
SWGR -
FAT
MOM
Verficati
on- 4
POINTS
complet
ed
2.11kV
SWGR -
Compon
ent List
Verficati
on
inprogre
ss
3.Label
preparat
ion for
Snag
points.
1.11kv
SWGR -
FAT
MOM
Verficati
on
2.11kV
SWGR -
Compon
ent List
Verficati
on -
complet
ed
3.Label
preparat
ion for
Snag
points.
ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MAY -2021
CUSTOMER: ETA PCS SITE CO-ORDINATOR: VINOTH
PROJECT : 132/11kV QUDS S/S (CUC 5) ENGINEER NAME: ELAVARASAN
Normal Special
Date Time-In Time-Out O.T Hrs Job Details
Hrs O.T Hrs
1-May-21 07. 00 2.00 7 - - Site visiting,safety induction & Documents verification
7-May-21 - - - - - --------FRIDAY----------
11-May-21 - - - - - HOLIDAY
12-May-21 - - - - - HOLIDAY
13-May-21 - - - - - HOLIDAY
14-May-21 - - - - - --------FRIDAY----------
15-May-21 - - - - - HOLIDAY
21-May-21 - - - - - --------FRIDAY----------
28-May-21 - - - - - --------FRIDAY----------
9-Nov-21 07. 30 05. 30 10 - - 1.Heating & lighting ckt checks - AFRY Witness completed
2.c.bank - un balance checks internal - c.bank -4,5,6, completed
1.HV Preparation - Bus-3 Busbar comp witnessed with afry
10-Nov-21 07. 30 05. 30 10 - - 2.LVAC - -6 CABLE IR Verified
3.c.bank - un balance checks internal - c.bank -1,2,3, completed
12-Nov-21 - - - - - --------FRIDAY----------
15-Nov-21 07. 30 05. 30 10 - - 1.HV Preparation - Bus duct & Multicore box (Room-1&2).witnessed with afry
2.Sitenote points clearnce
19-Nov-21 - - - - - --------FRIDAY----------
27-Nov-21 07. 30 05. 30 10 - - Ferrules check completed for CB RACK IN Interlocks in WOM,WM Feeders - completed
28-Nov-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - WM,WOM Completed with AFRY
29-Nov-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - C.BANK Completed with AFRY
30-Nov-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - Incomer inprogress with AFRY
2-Jan-22
3-Jan-22
4-Jan-22
5-Jan-22
6-Jan-22
7-Jan-22
8-Jan-22
9-Jan-22
10-Jan-22
11-Jan-22
12-Jan-22
13-Jan-22
14-Jan-22
15-Jan-22
16-Jan-22
17-Jan-22
18-Jan-22
19-Jan-22
20-Jan-22
21-Jan-22
22-Jan-22
23-Jan-22
24-Jan-22
25-Jan-22
26-Jan-22
27-Jan-22
28-Jan-22
29-Jan-22
30-Jan-22
31-Jan-22
CUSTOMER SIGNATURE
ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF Jan-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Ansar/Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Jan-22 - - - - - --------HOLIDAY----------
11KV SWGR RMD Drawing verification - In Progress and 11KV Cable inspection with DEWA
4-Jan-22 07. 30 05. 30 10 - -
In Progress
5-Jan-22 07. 30 05. 30 10 - - 11KV SWGR RMD Drawing verification, BS2 Drawing completed - In Progress
6-Jan-22 07. 30 05. 30 10 - - Capacitor bank surge arrester testing completed and Level3 ferrule checks in progress
8-Jan-22 - - - - - --------HOLIDAY----------
15-Jan-22 - - - - - --------HOLIDAY----------
20-Jan-22 07. 30 05. 30 10 - - Capacitor bank O & M Manual verification and site note clearance with AFRY
22-Jan-22 - - - - - --------HOLIDAY----------
23-Jan-22 07. 30 05. 30 10 - - LVAC O & M Manual comments works, Capacitor bank cable internal and LVAC L3 Internal
24-Jan-22 07. 30 05. 30 10 - - Capacitor bank cables HV Test - Bank-1,2,3 Completed and 11KV RMD Drawing works
Capacitor bank cables HV Test - Bank-5,6,7 Completed and Capacitor bank Interlock test
25-Jan-22 07. 30 05. 30 10 - -
completed
28-Jan-22 07. 30 05. 30 10 - - LVAC Incomer cable IR Test completed with AFRY
29-Jan-22 - - - - - --------HOLIDAY----------
5-Feb-22 - - - - - --------HOLIDAY----------
6-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test - Internal and documentation works
11-Feb-22 07. 30 05. 30 10 - - 11kV SWGR RMD Drawing verification with AFRY In Progress
11kV SWGR RMD Drawing verification with AFRY In Progress LVAC RMD Drawing
12-Feb-22 07. 30 05. 30 10 - -
verification with AFRY In Progress
13-Feb-22 - - - - - --------HOLIDAY----------
Capacitor bank RMD Drawing verification with DEWA In Progress and Capacitor bank
15-Feb-22 07. 30 05. 30 10 - -
torque checks In P rogress
16-Feb-22 07. 30 05. 30 10 - - Capacitor bank RMD Drawing verification with DEWA Completed
18-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank RMD Drawing works
20-Feb-22 - - - - - --------HOLIDAY----------
21-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank RMD Drawing works
22-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing works
23-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing works
24-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress
25-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress
26-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress
27-Feb-22 - - - - - --------HOLIDAY----------
28-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress
28-Jun-22 07. 30 05. 30 10 - - 11Kv swgr- O&M manual Preparation DEWA VERIFICATION - Inprogress
29-Jun-22 07. 30 05. 30 10 - - 11Kv swgr- O&M manual Preparation DEWA VERIFICATION - Completed.
30-Jun-22 07. 30 05. 30 10 - - GIS- O&M manual Preparation DEWA VERIFICATION - Inprogress
13-Jul-22 07. 30 05. 30 10 - - 11KV SWGR L3 Ferrule checks - without metering - Room1 Completed
14-Jul-22 07. 30 05. 30 10 - - 11KV SWGR L3 Ferrule checks - without metering - Room2 Completed
- - 11KV SWGR Capacitor bank Installation check list and Capacitor Drawing Verification (in
19-Jul-22 07. 30 05. 30 10 progress)
20-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Installation Drawing Verification
21-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Ferruels checks
22-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Interlock checks
23-Jul-22 - - - - - --------HOLIDAY----------
24-Jul-22 07. 30 05. 30 10 - - 11KV Swgr RMD Drawing works
25-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Interlock checks - Test report and documents works
30-Jul-22 - - - - - --------HOLIDAY----------
13-Aug-22 - - - - - --------HOLIDAY----------
132kV SWGR O&M Manual verification completed except AS BUILT Drawing and 132kV SWGR FAT
15-Aug-22 07. 30 05. 30 10 - -
Report verification completed and 11kV SWGR FAT Report in progress
16-Aug-22 07. 30 05. 30 10 - - LVAC and HLDB Outgoing cables verification and RMD Drawing Scaning works
20-Aug-22 - - - - - --------HOLIDAY----------
21-Aug-22 07. 30 05. 30 10 - - Pad lock works and project meeting
11kV SWGR FAT Report verification completed and LVAC FAT Report verification completed.
22-Aug-22 07. 30 05. 30 10 - - Capacitor bank FAT Report verification in progress
Capacitor bank drawing - 2 Drawings completed
23-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data verification
24-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data preparation and verification with DEWA
29-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data preparation and verification with DEWA
30-Aug-22 07. 31 05. 31 11 - - LVAC MMS Data preparation and verification with DEWA
31-Aug-22 07. 32 05. 32 12 - - 132kV SWGR & LVAC MMS MMS Data preparation and verification with DEWA
For
For
1-Jun-22
2-Jun-22
3-Jun-22
4-Jun-22 - - - - - --------HOLIDAY----------
5-Jun-22
6-Jun-22
7-Jun-22
11-Jun-22 - - - - - --------HOLIDAY----------
18-Jun-22 - - - - - --------HOLIDAY----------
25-Jun-22 - - - - - --------HOLIDAY----------
for
17-Sep-22 - - - - - --------HOLIDAY----------
11-Sep-22
12-Sep-22
13-Sep-22
14-Sep-22
15-Sep-22
16-Sep-22
17-Sep-22
18-Sep-22
19-Sep-22
20-Sep-22 07. 30 05. 30 10 - - 11kV Without Metering Trip Logic test Dewa Witness
24-Sep-22 - - - - - --------HOLIDAY----------
25-Sep-22 07. 30 05. 30 10 - - 11kV Incomer Trip Logic Test Internal Preparation
26-Sep-22 07. 30 05. 30 10 - - 11kV With Metering & Incomer Trip Logic test Dewa Witness
27-Sep-22 07. 30 05. 30 10 - - 11kV Incomer Trip Logic test Dewa Witness
28-Sep-22 07. 30 05. 30 10 - - 11kV BUS SECTION-1 Trip Logic test Dewa Witness
30-Sep-22 07. 30 05. 30 10 - - 11kV BS-2 Trip Logic test&DMZ Panel Outgoing cable Checks Dewa Witness
17-Sep-22 - - - - - --------HOLIDAY----------
24-Sep-22 - - - - - --------HOLIDAY----------
11-Oct-22
12-Oct-22
13-Oct-22
14-Oct-22
15-Oct-22 --------HOLIDAY----------
16-Oct-22
17-Oct-22
18-Oct-22
19-Oct-22
20-Oct-22
21-Oct-22
22-Oct-22 --------HOLIDAY----------
23-Oct-22
24-Oct-22
25-Oct-22
26-Oct-22
27-Oct-22
28-Oct-22
29-Oct-22 --------HOLIDAY----------
30-Oct-22
31-Oct-22
15-Oct-22 - - - - - --------HOLIDAY----------
20-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing completed except Incomers and site note feeders
29-Oct-22 - - - - - --------HOLIDAY----------
15-Oct-22 - - - - - --------HOLIDAY----------
29-Oct-22 - - - - - --------HOLIDAY----------