You are on page 1of 32

ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.

C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MARCH-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Ansar/Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs

1-Mar-22 07. 30 05. 30 10 - - 11KV BS1 RMD With dewa completed and Capacitor bank asbuilt drawings in progress

2-Mar-22 07. 30 05. 30 10 - - 11KV RMD Drawings verification

3-Mar-22 07. 30 05. 30 10 - - 11KV RMD Drawings verification

4-Mar-22 07. 30 05. 30 10 - - 11KV RMD Drawings With dewa completed

5-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works - Internal

6-Mar-22 - - - - - --------HOLIDAY----------

7-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works - Internal

8-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal

9-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal

10-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal

11-Mar-22 07. 30 05. 30 10 - - Final checks Internal

12-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works internal and Final checks Internal

13-Mar-22 - - - - - --------HOLIDAY----------

14-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works

15-Mar-22 07. 30 05. 30 10 - - Asbuilt drawing works and final checks internal at 11kV SWGR

16-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

17-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

18-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

19-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

20-Mar-22 - - - - - --------HOLIDAY----------

21-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

22-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

23-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

24-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

25-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

26-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress - CONSULTANT

27-Mar-22 - - - - - --------HOLIDAY----------

28-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress

29-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress

30-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress

31-Mar-22 07. 30 05. 30 10 - - Final checks witness in progress

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF DEC -2021
CUSTOMERETA PCS SITE CO-ORDINATOR: Mr.Ansar
PROJECT 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Normal Special
Date Time-In Time-Out O.T Hrs Job Details
Hrs O.T Hrs
1-Dec-21 07. 30 05. 30 10 - - HOLIDAY
2-Dec-21 07. 30 05. 30 10 - - HOLIDAY
3-Dec-21 07. 30 05. 30 10 - - --------FRIDAY----------

4-Dec-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - Incomer completed with AFRY

5-Dec-21 07. 30 05. 30 10 - - ES Interlocks Ferrules Checks verified with AFRY( BUS-1 --Without Feeders)

6-Dec-21 07. 30 05. 30 10 - - ES Interlocks Ferrules Checks verified with AFRY( BUS-2 and BUS3 --Without Feeders) - Completed

7-Dec-21 07. 30 05. 30 10 - - ES Interlock Ferrules Checks verified with AFRY( BUS-1,2,3 --With metering Feeders) - Completed

8-Dec-21 07. 30 05. 30 10 - - CB Close Interlock Ferrules Checks verified with AFRY( BUS-1 --Without metering Feeders) -
Completed

1) CB Close Interlock Ferrules Checks verified with AFRY( BUS-2 and BUS3 --Without metering
9-Dec-21 07. 30 05. 30 10 - - Feeders) - Completed
2) ID 121(Name plate Details) verified for BS1, Capacitor and With metering completed with DEWA

10-Dec-21 07. 30 05. 30 10 - - --------FRIDAY----------

11-Dec-21 07. 30 05. 30 10 - - CB Close Interlock Ferrules Checks verified with AFRY(With metering Feeders) - Completed

12-Dec-21 07. 30 05. 30 10 - - CB Close Interlock Ferrules Checks verified with AFRY(Capacitor Feeders) - In Progress

13-Dec-21 07. 30 05. 30 10 - - 11KV SWGR MMS Data verification with AFRY Completed

14-Dec-21 07. 30 05. 30 10 - - Rack-in Interlock checks - With and Without metering Completed

15-Dec-21 07. 30 05. 30 10 - - ES Interlock checks - With and Without metering Completed

16-Dec-21 07. 30 05. 30 10 - - CB Closing Interlocks checks - With and Without metering Completed

17-Dec-21 07. 30 05. 30 10 - - --------FRIDAY----------

18-Dec-21 07. 30 05. 30 10 - - 11KV SWGR EMS Data with AFRY In Progress and Capacitor Bank MMS Data with AFRY In Progress

19-Dec-21 07. 30 05. 30 10 - - Interlock ferrule checks for Bus Earth switches

20-Dec-21 07. 30 05. 30 10 - - BS-1,2 Rack-in, CB Closing and Bus Earth switches Interlocks dewa witness completed

Capacitor bank CB Interlock checks ferrule verification Completed with Consultant and Incomer In
21-Dec-21 07. 30 05. 30 10 - -
Progress

22-Dec-21 07. 30 05. 30 10 - - Capacitor bank CB, ES and Rack-in Interlock checks - DEWA Witness In Progress

23-Dec-21 07. 30 05. 30 10 - - Interlock ferrulle checks Incomers- Consultant Witness Completed

24-Dec-21 07. 30 05. 30 10 - - --------FRIDAY----------

25-Dec-21 07. 30 05. 30 10 - - Capacitor bank CB, ES and Rack-in Interlock checks Internal and RMD/Test report works
Interlock test at Incomers completed and Capacitor bank feeders except F01, F49 DEWA Witness
26-Dec-21 07. 30 05. 30 10 - -
Completed
27-Dec-21 07. 30 05. 30 10 - - C.BANK Documentation

28-Dec-21 07. 30 05. 30 10 - - BS-1 RMD GA Drawing inprogress

29-Dec-21 07. 30 05. 30 10 - - RMD Drawing verification in progress, 7 Drawings completed

30-Dec-21 07. 30 05. 30 10 RMD Drawing verification in progress

31-Dec-21 07. 30 05. 30 10 - - --------FRIDAY----------

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

CUSTOMER: WINSTAR SITE CO-ORDINATOR: MADHAVAN


PROJECT : 400/132kV RACECORS S/S ENGINEER NAME: MURALIDHARAN.S

Normal O.T Special


Date Time-In Time-Out Job Details
Hrs Hrs O.T Hrs

- - - - -
1-Mar-21

- - - - -
2-Mar-21

- - - - -
3-Mar-21

4-Mar-21 - - - - -

- - - - - --------FRIDAY----------
5-Mar-21

- - - - -
6-Mar-21

7-Mar-21 - - - - -

8-Mar-21 07. 30 05. 30 10 - - scms signal list source point updation(common )

9-Mar-21 07. 30 05. 30 10 - - scms signal list source point updation(common)

10-Mar-21 07. 30 05. 30 10 - - 132kv primary injection supporting & 132kv gis lcc ferrule check - 2 bays

11-Mar-21 07. 30 05. 30 10 - - scms signal list source point updation(lvac + 132kv gis)

12-Mar-21 - - - - - --------FRIDAY----------

13-Mar-21 07. 30 05. 30 10 - - scms common bcu signals verification internal

14-Mar-21 07. 30 05. 30 10 - - scms common bcu signals verification internal

15-Mar-21 07. 30 05. 30 10 - - lvac scs contacts verification internal


1.'lvac scs contacts verification internal
07. 30 05. 30 10 - - 2.132kv cable feeder signals verification upto scms-e06
16-Mar-21

17-Mar-21 07. 30 05. 30 10 - - common alarms verification upto scms(lvac,dc ch 1,dc ch2,el dc,avr)

07. 30 05. 30 10 - - common alarms verification upto scms(400&132kvfrp,metering panel,and schedule updation)
18-Mar-21

19-Mar-21 - - - - - --------FRIDAY----------
1.schedule updation for telecom,fire alarm,hvac,solar panel & emergency dg
07. 30 05. 30 10 - - 2.132kv wiring checks
20-Mar-21
07. 30 05. 30 10 - - 132kv signals & operations typical checks - cable feeder completed,ict - inprogress
21-Mar-21
132kv signals & operations typical checks - ict completed,bus coupler - completed,reactor -
07. 30 05. 30 10 - - inprogress
22-Mar-21
07. 30 05. 30 10 - - 132kv signals & operations typical checks - reactor completed,bus section - completed
23-Mar-21

24-Mar-21 07. 30 05. 30 10 - - 132kV hard wire checks related to SCMS

25-Mar-21 07. 30 05. 30 10 - - Common bcu remaining cable schedule preparation

26-Mar-21 - - - - - --------FRIDAY----------

27-Mar-21 07. 30 05. 30 10 - - 132kV modification done related to signals


1.Scms modification - 80 percentage completed
07. 30 05. 30 10 - - 2.SCMS signals updating with SCMS Engineer(common Bcu,132kV completed)
28-Mar-21

1.Scms modification - completed


2.SCMS signals updating with SCMS Engineer(400kV completed)
29-Mar-21 07. 30 05. 30 10 - - 3.132kV BB M2 signal modification done
4.132kV VSS internal checks - started

30-Mar-21 07. 30 05. 30 10 - - 132kV VSS scheme check - AC Circuit internal inprogress

31-Mar-21 07. 30 05. 30 10 - - 132kV VSS scheme check - AC Circuit internal inprogress

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF APRIL -2021


CUSTOMER: WINSTAR SITE CO-ORDINATOR: MADHAVAN
PROJECT : 400/132kV RACECORS S/S ENGINEER NAME: MURALIDHARAN.S

Normal O.T Special


Date Time-In Time-Out Job Details
Hrs Hrs O.T Hrs

1-Apr-21 07. 30 05. 30 10 - - 132kV VSS scheme check - AC Circuit internal Operations completed

2-Apr-21 - - - - - --------FRIDAY----------

3-Apr-21 07. 30 05. 30 10 - - 132kV VSS scheme check - DC Circuit internal inprogress

1.ICT AMK modification completed


4-Apr-21 07. 30 05. 30 10 - - 2.132kV VSS modification completed
3.132kV control operations verified with SCMS Engineer E03,04,05 completed

5-Apr-21 07. 30 05. 30 10 - - 132KV Measurements verifed with SCMS eng. - cable feeder completed

6-Apr-21 07. 30 05. 30 10 - - 132kV control operations verified with SCMS Engineer E05 to E16 completed except E 14

1.132kV control operations verified with SCMS Engineer E16 to E34completed


7-Apr-21 07. 30 05. 30 10 - - 2.132kV VSS Measurements limits verified with SCMS Engineer

8-Apr-21 07. 30 05. 30 10 - - 1.400kV control operations and signals verified with SCMS Engineer C05,C03 - completed

9-Apr-21 - - - - - --------FRIDAY----------

10-Apr-21 07. 30 05. 30 10 - - 400kv VSS wiring rectification works in progress (red ticks points completed)

1.400kV buscoupler & bussection control operations and signals verified with SCMS Engineer 2.132
11-Apr-21 07. 30 05. 30 10 - - kv VSS ferrule rectification inprogress

1.132 kv VSS ferrule rectification completed & issues noted


12-Apr-21 07. 30 05. 30 10 - - 2.400kv VSS voltage injection measurements OHL typical feeders verified with SCMS engineer

1.400kv VSS voltage injection measurements ICT,BC,BS typical feeders verified with SCMS engineer
13-Apr-21 07. 00 2.00 7 - - 2.400kv control operations C02 to C08 bays verified

1.400kv VSS schme checking with scms engineer - inprogress


14-Apr-21 07. 00 2.00 7 - - 2.400kv control operations C08 to C13 bays verified
15-Apr-21 07. 00 2.00 7 - - 132 kv VSS ferrule checks - inprogress

16-Apr-21 - - - - - --------FRIDAY----------

132kv VSS ferrule check


17-Apr-21 07. 00 2.00 7 - - E19,20,22,23,25,26,28 Voltage circuit pg.no SC1,SC2 verified.
132kv VSS ferrule check
18-Apr-21 07. 00 2.00 7 - - E11 to E18,24,27 Voltage circuit pg.no SC1,SC2 verified.
1.132kv VSS ferrule check
19-Apr-21 07. 00 2.00 7 - - E03 to E10 Voltage circuit pg.no SC1,SC2 verified.
2.IO list ferrule
1.132kv witness
VSS ferrule supporting with EPE
check
20-Apr-21 07. 00 2.00 7 - - E03 to E14 DC circuit pg.no QB1,QB2 verified.
2.400 KV IO list ferrule witness supporting with EPE
21-Apr-21 07. 00 2.00 7 - - 132kV Manfacturer supporting - alarm checks
1.132kv VSS ferrule check
E17 DC circuit pg.no QB1,QB2 verified.
22-Apr-21 07. 00 2.00 7 - - 2.ICT AMK ferrule rectification completed.
3.E30 & 18 ferrule rectification completed.. remaining ferrule mistakes noted.
23-Apr-21 - - - - - --------FRIDAY----------

1.400KV VSS AC circuit ferrule verified


24-Apr-21 07. 00 2.00 7 - - 2.SCMS AC bus wiring - rectified as per scheme completed

25-Apr-21 07. 00 2.00 7 - - DZ3, DZ4 132kV BBP Sensitivity test completed. - supporting
26-Apr-21 07. 00 2.00 7 - - CZ, DZ1 132kV BBP Sensitivity test completed.- supporting
27-Apr-21 07. 00 2.00 7 - - DZ2 132kV BBP Sensitivity test completed.- supporting

28-Apr-21 07. 00 2.00 7 - - 400KV VSS DC circuit ferrule verified

29-Apr-21 07. 00 2.00 7 - - 400KV Measurements verifed with SCMS eng.

30-Apr-21 - - - - - --------FRIDAY----------

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MAY -2021
CUSTOMER: WINSTAR SITE CO-ORDINATOR: MADHAVAN
PROJECT : 400/132kV RACECORS S/S ENGINEER NAME: MURALIDHARAN.S
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs

1-May-21 07. 00 2.00 7 - - 400KV Measurements verifed with SCMS eng.

1.Lvac labels preparation


2-May-21 07. 00 2.00 7 - - 2.400kv as built drawings - 2 drawing verified
1.132 kv measurements completed with scms.
3-May-21 07. 00 2.00 7 - - 2.132VSS in progress

4-May-21 07. 00 2.00 7 - - 400kV VSS sync.checks verified (LONG Transfer & Short transfer)

5-May-21 07. 00 2.00 7 - - VSS sync.checks verified C06&C09

6-May-21 07. 00 2.00 7 - - VSS sync.checks verified C06&C12

7-May-21 - - - - - --------FRIDAY----------

1.SCMS site note verification and updation


8-May-21 07. 00 2.00 7 - - 2.132kV O&M manual comments rectification.
9-May-21 07. 00 2.00 7 - - 400kV C02 Main 1 relay testing co ordination

10-May-21 07. 00 2.00 7 - - 400kV C02 ,C04 Main 1 relay testing co ordination- completed

11-May-21 - - - - - HOLIDAY

12-May-21 - - - - - HOLIDAY

13-May-21 - - - - - HOLIDAY

14-May-21 - - - - - --------FRIDAY----------

15-May-21 - - - - - HOLIDAY

16-May-21 07. 30 05. 30 10 - - 400kV C05 Main 1 relay testing co ordination- completed
1.ScMs co ordination (132kv ,400kv main relay communication checking)
17-May-21 07. 30 05. 30 10 - - 2.PDMS panel signals wiring done and signal checked upto hmi
18-May-21 07. 30 05. 30 10 - - SCMS co ordination

1.SCMS co ordination
19-May-21 07. 30 05. 30 10 - - 2 LVAC - EMVS switch fixing
3.400kv DCDB.1 ELR relay replacement co ordination

20-May-21 07. 30 05. 30 10 - - 132kv DCDB.2 ELR relay replacement co ordination

21-May-21 - - - - - --------FRIDAY----------

22-May-21

23-May-21

24-May-21
25-May-21
26-May-21
27-May-21
28-May-21

29-May-21
30-May-21
31-May-21

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MAY -2021
CUSTOMER: ETA PCS SITE CO-ORDINATOR: VINOTH
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: MURALIDHARAN.S
Normal Special
Date Time-In Time-Out O.T Hrs Job Details
Hrs O.T Hrs
1-May-21

2-May-21

3-May-21

4-May-21

5-May-21

6-May-21

7-May-21

8-May-21

9-May-21

10-May-21

11-May-21

12-May-21

13-May-21

14-May-21

15-May-21

16-May-21

17-May-21

18-May-21

19-May-21

20-May-21

21-May-21

22-May-21 07. 30 05. 30 10 - - Site visiting,safety induction & Documents verification

23-May-21 07. 30 05. 30 10 - - FAT Comments & Documents verification

24-May-21 07. 30 05. 30 10 - - FAT Comments & Documents verification

FAT Comments & Common drawing verfication


25-May-21 07. 30 05. 30 10 - - (1.SLD,Front view diagram)

FAT Comments & Common drawing verfication


26-May-21 07. 30 05. 30 10 - - (1.SLD,Front view diagram,foundation & rear view diagram)

FAT Comments & Common drawing verfication


27-May-21 07. 30 05. 30 10 - - (1.SLD,Front view diagram-inprogress,Component list - completed)

28-May-21 - - - - - --------FRIDAY----------

1.FAT MOM - Updation


29-May-21 07. 30 05. 30 10 - - 2.HLDB FAT Comments & Common drawing verfication
(1.HLDB - SLD,HLDB SChematiC Verification - inprogress)

1. Common drawing verfication


30-May-21 07. 30 05. 30 10 - - (1.HLDB - SLD,HLDB SChematiC Verification - completed,lvac scheme ferrule- inprogress)

31-May-21 07. 30 05. 30 10 - - LVAC schematics ferrule checks

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF AUGUST -2021
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Ansar
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs

1.LVAC - Red markup drawing verification ID-162,164,613 Signed with DEWA


1-Aug-21 07. 30 05. 30 10 - - 2.11kv SWGR - Checklist Verification-Issues Rectification
3.LVAC - 2 FAT MOM CLEARED

2-Aug-21 07. 30 05. 30 10 - - 1.11kv SWGR - Checklist Verification conpleted

3-Aug-21 07. 30 05. 30 10 - - 1.11kv SWGR - FAT MOM Verfication- 5 POINTS completed

1.11kv SWGR - FAT MOM Verfication- 4 POINTS completed


4-Aug-21 07. 30 05. 30 10 - - 2.11kV SWGR - Component List Verfication inprogress
3.Label preparation for Snag points.

1.11kv SWGR - FAT MOM Verfication


5-Aug-21 07. 30 05. 30 10 - - 2.11kV SWGR - Component List Verfication - completed
3.Label preparation for Snag points.

6-Aug-21 - - - - - --------FRIDAY----------

7-Aug-21 07. 30 05. 30 10 - - 1.11kv SWGR - FAT MOM Verfication


2.HLDB - Outgoing cables verfication - internal

8-Aug-21 07. 30 05. 30 10 - - 1.HLDB - Outgoing cable verification- inprogress


2.1.11kv SWGR - FAT MOM Verfication issues - Documents preparation for DEWA Meetings

9-Aug-21 07. 30 05. 30 10 - - 1.HLDB - Outgoing cable verification- 14 cables ready to witness
2.11kv SWGR - FAT MOM Verfication - with DEWA - 134 cleared with DEWA

1.Issues Rectification co ordination with O&M.


10-Aug-21 07. 30 05. 30 10 - - 2.CT Secondary ferrules check - F04,05 - COMPLETED
3. Aux.Relay Manfacture Year Verification - -inprogress

11-Aug-21 07. 30 05. 30 10 - - 1.Dewa Onsite Familiration co-ordination


2. Aux.Relay Manfacture Year Verification - -inprogress

12-Aug-21 07. 30 05. 30 10 - - HOLIDAY

13-Aug-21 - - - - - --------FRIDAY----------

14-Aug-21 07. 30 05. 30 10 - - 1.CB Motor checks with 85% & 110% with afry.
2.Site note issues Rectification co - ordiantion with O&M.

15-Aug-21 07. 30 05. 30 10 - - 1.HLDB - Outgoing cable verification- 15 No of cables completed with afry.
2.11kV SWGR CT FAT Report Verification - inprogress

16-Aug-21 07. 30 05. 30 10 - - 1.HLDB - outgoing cabls IR Preparation - 6 cables


2.11kV SWGR _ CB Motor issues rectification with O&M

17-Aug-21 07. 30 05. 30 10 - - 1.HLDB & LVAC SLD Verification completed with AFRY.
2.VCB & CT FAT Reports Verification - inprogress

1.Materials verfication with O&M


18-Aug-21 07. 30 05. 30 10 - - 2.VCB & CT FAT Reports Verification -Completed.
3.Site note-17- closed with AFRY & site note-14-2 points closed with afry

19-Aug-21 07. 30 05. 30 10 - - 1.11kV SWGR - DAM INSPECTION


20-Aug-21 - - - - - --------FRIDAY----------

21-Aug-21 07. 30 05. 30 10 - - 1.HLDB - Outgoing cable verification - 7 cables completed with afry
2.132kV MMS DATA Updation.

22-Aug-21 07. 30 05. 30 10 - - 1.11kV SWGR _ FAT comment - 1 point cleared with AFRY.
2.11kV SWGR _CT Ferrules verification - inprogress

23-Aug-21 07. 30 05. 30 10 - - 1.11kV SWGR _ FAT comment - 3 point cleared with AFRY.
2.11kV SWGR _CT Ferrules verification - inprogress

1.11kV SWGR _ FAT comment - 6 point cleared with DEWA.


24-Aug-21 07. 30 05. 30 10 - - 2.11kV SWGR _ DAM comment - 4 point cleared with DEWA.
3.11kV SWGR _CT Ferrules verification -COMPLETED

25-Aug-21 07. 30 05. 30 10 - - 1.11kV FAT MOM Verification


2.11kV - Aux.relay ferrule Verification

26-Aug-21 07. 30 05. 30 10 - - 1.11kV Cable Drum test. - 3 drums completed with dewa.
2.11kV - Aux.relay ferrule Verification - Inprogress.

27-Aug-21 - - - - - --------FRIDAY----------

28-Aug-21 07. 30 05. 30 10 - - 1.11kV primary Drawing Verification - Section view - inprogress
29-Aug-21 07. 30 05. 30 10 - - 1.11kV primary Drawing Verification
30-Aug-21 - - - - - LEAVE

31-Aug-21 - - - - - LEAVE

ENGINEER SIGNATURE CUSTOMER SIGNATURE


1.LVAC
- Red
markup
drawing
verificati
on ID-
162,164,
613
Signed
with
DEWA
2.11kv
SWGR -
Checklis
t
Verificat
ion-
Issues
Rectifica
tion
3.LVAC
- 2 FAT
MOM
CLEARE
D

1.11kv
SWGR -
Checklis
t
Verificat
ion
conplete
d
1.11kv
SWGR -
FAT
MOM
Verficati
on- 5
POINTS
complet
ed

1.11kv
SWGR -
FAT
MOM
Verficati
on- 4
POINTS
complet
ed
2.11kV
SWGR -
Compon
ent List
Verficati
on
inprogre
ss
3.Label
preparat
ion for
Snag
points.
1.11kv
SWGR -
FAT
MOM
Verficati
on- 4
POINTS
complet
ed
2.11kV
SWGR -
Compon
ent List
Verficati
on
inprogre
ss
3.Label
preparat
ion for
Snag
points.
1.11kv
SWGR -
FAT
MOM
Verficati
on
2.11kV
SWGR -
Compon
ent List
Verficati
on -
complet
ed
3.Label
preparat
ion for
Snag
points.
ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MAY -2021
CUSTOMER: ETA PCS SITE CO-ORDINATOR: VINOTH
PROJECT : 132/11kV QUDS S/S (CUC 5) ENGINEER NAME: ELAVARASAN
Normal Special
Date Time-In Time-Out O.T Hrs Job Details
Hrs O.T Hrs
1-May-21 07. 00 2.00 7 - - Site visiting,safety induction & Documents verification

2-May-21 07. 00 2.00 7 - - Drawings Arrangements preparation

3-May-21 07. 00 2.00 7 - - Drawings verification with DDCMS

4-May-21 07. 00 2.00 7 - - Drawings verification with DDCMS

5-May-21 07. 00 2.00 7 - - Fat MOM soft copy preparation

6-May-21 07. 00 2.00 7 - - Fat MOM soft copy preparation

7-May-21 - - - - - --------FRIDAY----------

8-May-21 07. 00 2.00 7 - - FAT MOM Verification

9-May-21 07. 00 2.00 7 - - FAT MOM Verification

10-May-21 07. 00 2.00 7 - - FAT MOM Verification

11-May-21 - - - - - HOLIDAY

12-May-21 - - - - - HOLIDAY

13-May-21 - - - - - HOLIDAY

14-May-21 - - - - - --------FRIDAY----------

15-May-21 - - - - - HOLIDAY

16-May-21 07. 30 05. 30 10 - - Cable Schedule verification

17-May-21 07. 30 05. 30 10 - - Cable Schedule verification

18-May-21 07. 30 05. 30 10 - - FAT Comments & Documents verification

19-May-21 07. 30 05. 30 10 - - FAT Comments & Documents verification

20-May-21 07. 30 05. 30 10 - - FAT Comments & Documents verification

21-May-21 - - - - - --------FRIDAY----------

22-May-21 07. 30 05. 30 10 - - MK - Ferrules checks

23-May-21 07. 30 05. 30 10 - - MK - Ferrules checks

24-May-21 07. 30 05. 30 10 - - MK - Ferrules checks

25-May-21 07. 30 05. 30 10 - - Internal wiring tightness verifiacation

26-May-21 07. 30 05. 30 10 - - Internal wiring tightness verifiacation

27-May-21 07. 30 05. 30 10 - - Components verification

28-May-21 - - - - - --------FRIDAY----------

29-May-21 07. 30 05. 30 10 - - Components verification

30-May-21 07. 30 05. 30 10 - - Components verification

31-May-21 07. 30 05. 30 10 - - MK - Wiring checks

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF Nov -2021
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Ansar
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1.CB Mechanical checks - BUS 1,2 Completed ex,Inc,BS
1-Nov-21 07. 30 05. 30 10 - -
2.Heating & lighting checks - Ferrules BUS 3 Completed
2-Nov-21 07. 30 05. 30 10 - - 1.CB Mechanical checks - BUS 3 & INC-1,2,3 & BS-1,2 Completed
2.CB Electrical checks - Ferrules BUS 1 Completed
3-Nov-21 07. 30 05. 30 10 - - 1.CB Electrical checks - Spring Charge Checks F01-F36 Completed
2.CB Electrical checks - Ferrules BUS 2 Completed
4-Nov-21 07. 30 05. 30 10 - - 1.CB General Checks - completed
2.CB Electrical checks - Ferrules BUS 3 Completed
5-Nov-21 - - - - - --------FRIDAY----------

1.CB Electrical l checks - Room -1 completed


6-Nov-21 07. 30 05. 30 10 - - 2.CB Coil Resistance completed with AFRY
3.CB
1.CB Closing coil Ferrules
Interchangability Verrification
- DEWA Witness-Completed
-preparartion
7-Nov-21 07. 30 05. 30 10 - - 2.CB Timing Checks - F71 - DEWA Witness Completed
3.CB Electrical Checks - DEWA Witness Completed
8-Nov-21 07. 30 05. 30 10 - - 1.Perimary Drawing Verification - ID 121 Name Plate Drawing - 8 pages out of 27 by DEWA.

9-Nov-21 07. 30 05. 30 10 - - 1.Heating & lighting ckt checks - AFRY Witness completed
2.c.bank - un balance checks internal - c.bank -4,5,6, completed
1.HV Preparation - Bus-3 Busbar comp witnessed with afry
10-Nov-21 07. 30 05. 30 10 - - 2.LVAC - -6 CABLE IR Verified
3.c.bank - un balance checks internal - c.bank -1,2,3, completed

11-Nov-21 07. 30 05. 30 10 - -


1.HV Preparation - Bus-3CABLE comp & F37 TO F48 - BUSBAR COMP.witnessed with afry
2.Sitenote points clearnce

12-Nov-21 - - - - - --------FRIDAY----------

13-Nov-21 07. 30 05. 30 10 - -


1.HV Preparation - Room-2 Cable & BUSBAR COMP.witnessed with afry
2.Sitenote points clearnce
14-Nov-21 07. 30 05. 30 10 - - 1.HV Preparation - Room-1 Cable & BUSBAR COMP.witnessed with afry
2.Sitenote points clearnce

15-Nov-21 07. 30 05. 30 10 - - 1.HV Preparation - Bus duct & Multicore box (Room-1&2).witnessed with afry
2.Sitenote points clearnce

16-Nov-21 07. 30 05. 30 10 - -


1.Site note Verification with AFRY
2.HV Preparation

17-Nov-21 07. 30 05. 30 10 - - 1.Site note Verification with AFRY


2.HV Preparation

18-Nov-21 07. 30 05. 30 10 - - 1.Site note Verification with AFRY


2.HV Preparation

19-Nov-21 - - - - - --------FRIDAY----------

20-Nov-21 07. 30 05. 30 10 - - 1.HV Preparation


2.FAT MOM & Site note Verification
1.HV Preparation
21-Nov-21 07. 30 05. 30 10 - - 2.FAT MOM & Site note Verification
3.Faulty CB Coils replacemnts anDCB Coil Resistance checks with AFRY - completed
1.HV Preparation
22-Nov-21 07. 30 05. 30 10 - - 2.FAT MOM & Site note Verification
3.Faulty CB Coils replacemnts-CB Timing ,functional test checks with AFRY - completed
23-Nov-21 07. 30 05. 30 10 - - BB & CABLE COMP(ROOM-1&2)inspection completed with DEWA.

24-Nov-21 07. 30 05. 30 10 - - CB COMP(ROOM-1&2)inspection completed with DEWA.


25-Nov-21 07. 30 05. 30 10 - - HV Completed.
26-Nov-21 - - - - - --------FRIDAY----------

27-Nov-21 07. 30 05. 30 10 - - Ferrules check completed for CB RACK IN Interlocks in WOM,WM Feeders - completed
28-Nov-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - WM,WOM Completed with AFRY
29-Nov-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - C.BANK Completed with AFRY
30-Nov-21 07. 30 05. 30 10 - - Internal Arrangements Drawing verification - Incomer inprogress with AFRY

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF JAN -2022
CUSTOMER: TAMCO SITE CO-ORDINATOR: IRFAN
PROJECT : 132/11kV CIRCLEX S/S NAME:
Normal Special
Date Time-In Time-Out O.T Hrs Job Details
Hrs O.T Hrs
1-Jan-22

2-Jan-22

3-Jan-22

4-Jan-22

5-Jan-22

6-Jan-22

7-Jan-22

8-Jan-22

9-Jan-22

10-Jan-22

11-Jan-22

12-Jan-22

13-Jan-22

14-Jan-22

15-Jan-22

16-Jan-22

17-Jan-22

18-Jan-22

19-Jan-22

20-Jan-22

21-Jan-22

22-Jan-22

23-Jan-22

24-Jan-22

25-Jan-22

26-Jan-22

27-Jan-22

28-Jan-22

29-Jan-22

30-Jan-22

31-Jan-22

CUSTOMER SIGNATURE
ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF Jan-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Ansar/Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs

1-Jan-22 - - - - - --------HOLIDAY----------

2-Jan-22 07. 30 05. 30 10 - - RMD Drawing verification - In Progress

3-Jan-22 07. 30 05. 30 10 - - 11KV SWGR RMD Drawing verification - In Progress

11KV SWGR RMD Drawing verification - In Progress and 11KV Cable inspection with DEWA
4-Jan-22 07. 30 05. 30 10 - -
In Progress

5-Jan-22 07. 30 05. 30 10 - - 11KV SWGR RMD Drawing verification, BS2 Drawing completed - In Progress

6-Jan-22 07. 30 05. 30 10 - - Capacitor bank surge arrester testing completed and Level3 ferrule checks in progress

7-Jan-22 07. 30 05. 30 10 - - Site note clearance with Consultant

8-Jan-22 - - - - - --------HOLIDAY----------

9-Jan-22 07. 30 05. 30 10 - - 11KV SWGR RMD Drawing verification,- In Progress

10-Jan-22 07. 30 05. 30 10 - - 11KV SWGR RMD Drawing verification,- In Progress

11-Jan-22 07. 30 05. 30 10 - - 11KV SWGR RMD Drawing verification, In Progress

12-Jan-22 07. 30 05. 30 10 - - 11KV SWGR RMD Drawing verification, completed

13-Jan-22 07. 30 05. 30 10 - - Site note clearance with Consultant

14-Jan-22 07. 30 05. 30 10 - - Site note clearance with Consultant

15-Jan-22 - - - - - --------HOLIDAY----------

16-Jan-22 07. 30 05. 30 10 - - Leave

17-Jan-22 07. 30 05. 30 10 - - Leave

18-Jan-22 07. 30 05. 30 10 - - Leave

19-Jan-22 07. 30 05. 30 10 - - Capacitor bank Interlock checks Internal

20-Jan-22 07. 30 05. 30 10 - - Capacitor bank O & M Manual verification and site note clearance with AFRY

21-Jan-22 07. 30 05. 30 10 - - Site note and FAT MOM Verification

22-Jan-22 - - - - - --------HOLIDAY----------

23-Jan-22 07. 30 05. 30 10 - - LVAC O & M Manual comments works, Capacitor bank cable internal and LVAC L3 Internal

24-Jan-22 07. 30 05. 30 10 - - Capacitor bank cables HV Test - Bank-1,2,3 Completed and 11KV RMD Drawing works

Capacitor bank cables HV Test - Bank-5,6,7 Completed and Capacitor bank Interlock test
25-Jan-22 07. 30 05. 30 10 - -
completed

26-Jan-22 07. 30 05. 30 10 - - Level3 Test Internal

27-Jan-22 07. 30 05. 30 10 - - LVAC Level3 Testing Completed

28-Jan-22 07. 30 05. 30 10 - - LVAC Incomer cable IR Test completed with AFRY

29-Jan-22 - - - - - --------HOLIDAY----------

30-Jan-22 07. 30 05. 30 10 LVAC, HLDB Outgoing cable IR Test

31-Jan-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test in progress

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF FEB-2022


CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Ansar/Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs

1-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test in progress

2-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test in progress

3-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test in progress

4-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test in progress

5-Feb-22 - - - - - --------HOLIDAY----------

6-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test - Internal and documentation works

7-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test in progress

8-Feb-22 07. 30 05. 30 10 - - 11kV SWGR Level3 Test completed

9-Feb-22 07. 30 05. 30 10 - - 11kV SWGR and LVAC documentation works

10-Feb-22 07. 30 05. 30 10 - - 11kV SWGR and LVAC documentation works

11-Feb-22 07. 30 05. 30 10 - - 11kV SWGR RMD Drawing verification with AFRY In Progress

11kV SWGR RMD Drawing verification with AFRY In Progress LVAC RMD Drawing
12-Feb-22 07. 30 05. 30 10 - -
verification with AFRY In Progress

13-Feb-22 - - - - - --------HOLIDAY----------

14-Feb-22 07. 30 05. 30 10 - - Capacitor bank torque checks In P rogress

Capacitor bank RMD Drawing verification with DEWA In Progress and Capacitor bank
15-Feb-22 07. 30 05. 30 10 - -
torque checks In P rogress

16-Feb-22 07. 30 05. 30 10 - - Capacitor bank RMD Drawing verification with DEWA Completed

17-Feb-22 07. 30 05. 30 10 - - Capacitor bank Torque checks in progress

18-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank RMD Drawing works

19-Feb-22 07. 30 05. 30 10 - - LVAC Outgoing cables witness

20-Feb-22 - - - - - --------HOLIDAY----------

21-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank RMD Drawing works

22-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing works

23-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing works

24-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress

25-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress

26-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress

27-Feb-22 - - - - - --------HOLIDAY----------

28-Feb-22 07. 30 05. 30 10 - - 11KV, LVAC and Capacitor bank AS BUILT Drawing verification with AFRY In Progress

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF APRIL-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Apr-22 07. 30 05. 30 10 - - Final checks witness in progress
2-Apr-22 07. 30 03. 30 8 - - Battery testing
3-Apr-22 - - - - - --------HOLIDAY----------
4-Apr-22 07. 30 03. 30 8 - - CABLE Final checks witness in progress-DEWA
5-Apr-22 07. 30 03. 30 8 - - CABLE Final checks witness in progress-DEWA
6-Apr-22 07. 30 03. 30 8 - - CABLE Final checks witness in progress-DEWA
7-Apr-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
8-Apr-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
9-Apr-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
10-Apr-22 - - - - - --------HOLIDAY----------
11-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress
12-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress
13-Apr-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
14-Apr-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
15-Apr-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
16-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
17-Apr-22 - - - - - --------HOLIDAY----------
18-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
19-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
20-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
21-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
22-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
23-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
24-Apr-22 - - - - - --------HOLIDAY----------
25-Apr-22 07. 30 03. 30 8 - - Level4 Test In progress
26-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
27-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
28-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
29-Apr-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
30-Apr-22 07. 30 03. 30 8 - - Documentation works

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MAY-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-May-22 07. 30 05. 30 10 - - Final checks witness in progress
2-May-22 07. 30 03. 30 8 - - Battery testing
3-May-22 - - - - - --------HOLIDAY----------
4-May-22 07. 30 03. 30 8 - - CABLE Final checks witness in progress-DEWA
5-May-22 07. 30 03. 30 8 - - CABLE Final checks witness in progress-DEWA
6-May-22 07. 30 03. 30 8 - - CABLE Final checks witness in progress-DEWA
7-May-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
8-May-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
9-May-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
10-May-22 - - - - - --------HOLIDAY----------
11-May-22 07. 30 03. 30 8 - - Final checks witness in progress
12-May-22 07. 30 03. 30 8 - - Final checks witness in progress
13-May-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
14-May-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
15-May-22 07. 30 03. 30 8 - - CB Final checks witness in progress-DEWA
16-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
17-May-22 07. 30 03. 30 8 - - --------HOLIDAY----------
18-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
19-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
20-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
21-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
22-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
23-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
24-May-22 07. 30 03. 30 8 - - Level4 Test In progress
25-May-22 07. 30 03. 30 8 - - Level4 Test In progress
26-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
27-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
28-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
29-May-22 07. 30 03. 30 8 - - Final checks witness in progress and documents works
30-May-22
31-May-22 07. 30 03. 30 8 - - Documentation works

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF MAY-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV CIRCLEX S/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-May-22 - - - - - --------HOLIDAY----------
2-May-22 - - - - - --------HOLIDAY----------
3-May-22 - - - - - --------HOLIDAY----------
4-May-22 - - - - - --------HOLIDAY----------
5-May-22 07. 30 05. 30 10 - - LV Comp. Final checks witness in progress-DEWA
6-May-22 07. 30 05. 30 10 - - LV Comp. Final checks witness in progress-DEWA
7-May-22 07. 30 05. 30 10 - - CB Final checks witness in progress-DEWA
8-May-22 - - - - - --------HOLIDAY----------
9-May-22 07. 30 05. 30 10 - - CBANK - FINAL Checks
10-May-22 07. 30 05. 30 10 - - CBANK - FINAL Checks
11-May-22 07. 30 05. 30 10 - - Documentation Verifiaction with DEWA
12-May-22 07. 30 05. 30 10 - - Documentation Verifiaction with DEWA
13-May-22 07. 30 05. 30 10 - - Documentation Verifiaction with DEWA
14-May-22 07. 30 05. 30 10 - - Documentation Verifiaction with DEWA
15-May-22 - - - - - --------HOLIDAY----------
16-May-22 07. 30 05. 30 10 - - DAM Inspection.
17-May-22 07. 30 05. 30 10 - - DAM Inspection.
18-May-22 07. 30 05. 30 10 - - 11kV Cable Final Shealth Test.
19-May-22 07. 30 05. 30 10 - - Cupboard Verification with DEWA
20-May-22 07. 30 05. 30 10 - - Cupboard Verification with DEWA
21-May-22 07. 30 05. 30 10 - - Energization Checklist Verification with DEWA
22-May-22 - - - - - --------HOLIDAY----------
23-May-22 07. 30 05. 30 10 - - Energization Checklist Verification with DEWA
24-May-22 07. 30 05. 30 10 - - Energization Checklist Verification with DEWA
25-May-22 07. 30 05. 30 10 - - Energization - CIRCLEX SS
26-May-22 07. 30 05. 30 10 - - Switching Progress in 11Kv SWGR
27-May-22 07. 30 05. 30 10 - - Switching Progress in 11Kv SWGR
28-May-22 07. 30 05. 30 10 - - Switching Progress in 11Kv SWGR
29-May-22 - - - - - --------HOLIDAY----------
30-May-22 07. 30 05. 30 10 Switching Progress in 11Kv SWGR
31-May-22 07. 30 05. 30 10 - - Switching Progress in 11Kv SWGR

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF JUNE-2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Jun-22 07. 30 05. 30 10 - - Documents Verification
2-Jun-22 07. 30 05. 30 10 - - Documents Verification
3-Jun-22 07. 30 05. 30 10 - - Documents Verification
4-Jun-22 - - - - - --------HOLIDAY----------
5-Jun-22 07. 30 05. 30 10 - - Lvac - O&M manual Preparation
6-Jun-22 07. 30 05. 30 10 - - Lvac - O&M manual Preparation
7-Jun-22 07. 30 05. 30 10 - - CBANK - O&M manual Preparation
8-Jun-22 07. 30 05. 30 10 - - 11Kv SWGR - O&M manual Preparation
9-Jun-22 07. 30 05. 30 10 - - 11Kv SWGR - O&M manual Preparation
10-Jun-22 07. 30 05. 30 10 - - 11Kv SWGR - O&M manual Preparation
11-Jun-22 - - - - - --------HOLIDAY----------
12-Jun-22 07. 30 05. 30 10 - - ET- O&M manual Preparation
13-Jun-22 07. 30 05. 30 10 - - ET- O&M manual Preparation
14-Jun-22 07. 30 05. 30 10 - - GIS- O&M manual Preparation
15-Jun-22 07. 30 05. 30 10 - - GIS- O&M manual Preparation
16-Jun-22 07. 30 05. 30 10 - - GIS- O&M manual Preparation
17-Jun-22 07. 30 05. 30 10 - - GIS- O&M manual Preparation
18-Jun-22 - - - - - --------HOLIDAY----------
19-Jun-22 07. 30 05. 30 10 - - LVAC - FAT Report verification
20-Jun-22 07. 30 05. 30 10 - - LVAC,11kV SWGR - FAT Report verification
21-Jun-22 07. 30 05. 30 10 - - 11kV SWGR - FAT Report verification
22-Jun-22 07. 30 05. 30 10 - - 11kV SWGR - FAT Report verification
23-Jun-22 07. 30 05. 30 10 - - 11kV SWGR, GIS - FAT Report verification
24-Jun-22 07. 30 05. 30 10 - - GIS - FAT Report verification
25-Jun-22 - - - - - --------HOLIDAY----------
26-Jun-22 07. 30 05. 30 10 - - CBANK - FAT Report verification
27-Jun-22 07. 30 05. 30 10 - - CBANK - FAT Report verification

28-Jun-22 07. 30 05. 30 10 - - 11Kv swgr- O&M manual Preparation DEWA VERIFICATION - Inprogress

29-Jun-22 07. 30 05. 30 10 - - 11Kv swgr- O&M manual Preparation DEWA VERIFICATION - Completed.

30-Jun-22 07. 30 05. 30 10 - - GIS- O&M manual Preparation DEWA VERIFICATION - Inprogress

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF JULY 2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Jul-22 07. 30 05. 30 10 - - 1. 132KV Swgr O & M Manual(hard copy) Preparation
2-Jul-22 - - - - - --------HOLIDAY----------
3-Jul-22 07. 30 05. 30 10 - - 1. 132KV Swgr O & M Manual(hard copy) Preparation
4-Jul-22 07. 30 05. 30 10 - - 1. 132KV Swgr SAT Preparation
5-Jul-22 07. 30 05. 30 10 - - 1.IDT O & M Manual preparation
6-Jul-22 07. 30 05. 30 10 - - 11KV Cable Sheath test before termination
7-Jul-22 07. 30 05. 30 10 - - 11KV Cable Sheath test before termination
8-Jul-22 - - - - - --------HOLIDAY----------
9-Jul-22 - - - - - --------HOLIDAY----------
10-Jul-22 - - - - - --------HOLIDAY----------
11-Jul-22 - - - - - --------HOLIDAY----------
12-Jul-22 07. 30 05. 30 10 - - 11KV Swgr RMD Drawing works

13-Jul-22 07. 30 05. 30 10 - - 11KV SWGR L3 Ferrule checks - without metering - Room1 Completed

14-Jul-22 07. 30 05. 30 10 - - 11KV SWGR L3 Ferrule checks - without metering - Room2 Completed

15-Jul-22 07. 30 05. 30 10 - - 11KV SWGR handing over material verification


16-Jul-22 - - - - - --------HOLIDAY----------
17-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Documents works
18-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank panels Interlock and L3 Ferrule checks

- - 11KV SWGR Capacitor bank Installation check list and Capacitor Drawing Verification (in
19-Jul-22 07. 30 05. 30 10 progress)
20-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Installation Drawing Verification
21-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Ferruels checks
22-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Interlock checks
23-Jul-22 - - - - - --------HOLIDAY----------
24-Jul-22 07. 30 05. 30 10 - - 11KV Swgr RMD Drawing works

25-Jul-22 07. 30 05. 30 10 - - 11KV SWGR Capacitor bank Interlock checks - Test report and documents works

26-Jul-22 07. 30 05. 30 10 - - Capacitor bank - 1 To 3 Testing


27-Jul-22 07. 30 05. 30 10 - - Capacitor bank - 4 To 6 Testing

28-Jul-22 07. 30 05. 30 10 - - Capacitor bank SAT Works

29-Jul-22 07. 30 05. 30 10 - - Capacitor bank - 1 To 6 Inductanxce measurement Re-test

30-Jul-22 - - - - - --------HOLIDAY----------

31-Jul-22 07. 30 05. 30 10 Capacitor bank SAT Works

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF AUGUST 2022
CUSTOMER: ETA PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Aug-22 07. 30 05. 30 10 - - RABWAH,GRENHILS NOD Works
2-Aug-22 07. 30 05. 30 10 - - RABWAH,GRENHILS NOD Works
3-Aug-22 07. 30 05. 30 10 - - RABWAH,GRENHILS NOD Works
4-Aug-22 07. 30 05. 30 10 - - Capacitor bank and LVAC Label works
5-Aug-22 07. 30 05. 30 10 - - Capacitor bank and 11kV Label works
6-Aug-22 - - - - - --------HOLIDAY----------
7-Aug-22 07. 30 05. 30 10 - - LVAC Outgoing cables checks
8-Aug-22 07. 30 05. 30 10 - - LVAC and 132KV SWGR O & M Manual verification
9-Aug-22 07. 30 05. 30 10 - - LVAC outgoing cables verification
10-Aug-22 07. 30 05. 30 10 - - LVAC outgoing cables verification
11-Aug-22 07. 30 05. 30 10 - - HLDB outgoing cables verification
12-Aug-22 07. 30 05. 30 10 - - HLDB outgoing cables verification

13-Aug-22 - - - - - --------HOLIDAY----------

14-Aug-22 07. 30 05. 30 10 - - LVAC outgoing cables verification

132kV SWGR O&M Manual verification completed except AS BUILT Drawing and 132kV SWGR FAT
15-Aug-22 07. 30 05. 30 10 - -
Report verification completed and 11kV SWGR FAT Report in progress

16-Aug-22 07. 30 05. 30 10 - - LVAC and HLDB Outgoing cables verification and RMD Drawing Scaning works

17-Aug-22 07. 30 05. 30 10 - - CUC - 5 Drawings Verification


18-Aug-22 07. 30 05. 30 10 - - Pad lock and key list works

19-Aug-22 07. 30 05. 30 10 - - Pad lock and key list works

20-Aug-22 - - - - - --------HOLIDAY----------
21-Aug-22 07. 30 05. 30 10 - - Pad lock works and project meeting
11kV SWGR FAT Report verification completed and LVAC FAT Report verification completed.
22-Aug-22 07. 30 05. 30 10 - - Capacitor bank FAT Report verification in progress
Capacitor bank drawing - 2 Drawings completed
23-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data verification
24-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data preparation and verification with DEWA

25-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data preparation

26-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data preparation


27-Aug-22 - - - - - --------HOLIDAY----------

28-Aug-22 07. 30 05. 30 10 - - CUC - 5 Handing Over

29-Aug-22 07. 30 05. 30 10 - - 132kV SWGR MMS Data preparation and verification with DEWA

30-Aug-22 07. 31 05. 31 11 - - LVAC MMS Data preparation and verification with DEWA

31-Aug-22 07. 32 05. 32 12 - - 132kV SWGR & LVAC MMS MMS Data preparation and verification with DEWA

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF JULY 2022
CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Sijin Diyo
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documents & Works
2-Jul-22 - - - - - --------HOLIDAY----------
3-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
4-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
5-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
6-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
7-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
8-Jul-22 - - - - - --------HOLIDAY----------
9-Jul-22 - - - - - --------HOLIDAY----------
10-Jul-22 - - - - - --------HOLIDAY----------
11-Jul-22 - - - - - --------HOLIDAY----------
12-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

13-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

14-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

15-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works


16-Jul-22 - - - - - --------HOLIDAY----------
17-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
18-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
19-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
20-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
21-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
22-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
23-Jul-22 - - - - - --------HOLIDAY----------
24-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
25-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
26-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
27-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
28-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
29-Jul-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
30-Jul-22 - - - - - --------HOLIDAY----------

31-Jul-22 07. 30 05. 30 10 Supporting Activity for Site Documnets& Works

For

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF AUGUST 2022


CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Sijin Diyo
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documents & Works
2-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
3-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
4-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
5-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
6-Aug-22 - - - - - --------HOLIDAY----------
7-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
8-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
9-Aug-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

For

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF JUNE-2022


CUSTOMER:AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT :132/11kV MRINACMNS/S ENGINEER NAME: SIJIN
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs

1-Jun-22

2-Jun-22

3-Jun-22

4-Jun-22 - - - - - --------HOLIDAY----------

5-Jun-22

6-Jun-22

7-Jun-22

8-Jun-22 07. 30 05. 30 10 - - Site induction

9-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

10-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

11-Jun-22 - - - - - --------HOLIDAY----------

12-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

13-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

14-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

15-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

16-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

17-Jun-22 07. 30 05. 30 10 - - Site Documents verification - internal

18-Jun-22 - - - - - --------HOLIDAY----------

19-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

20-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

21-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

22-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

23-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

24-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

25-Jun-22 - - - - - --------HOLIDAY----------

26-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

27-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

28-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

29-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

30-Jun-22 07. 30 05. 30 10 - - 11kV SWGR testing supporting

for

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF SEPTEMBER 2022


CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Sep-22 07. 30 05. 30 10 - - LVAC Legend works - INTERNAL
2-Sep-22 07. 30 05. 30 10 - - RMD Works - 11kV SWGR and LVAC
3-Sep-22 - - - - - --------HOLIDAY----------
4-Sep-22 07. 30 05. 30 10 - - LVAC level3 works
5-Sep-22 07. 30 05. 30 10 - - 11KV SWGR MMS Data Completed and CTVT In progress
6-Sep-22 07. 30 05. 30 10 - - 11KV CTVT MMS Data and Capacitor bank MMS Data completed
7-Sep-22 07. 30 05. 30 10 - - 11KV SWGR Redmarkup drawing works
8-Sep-22 07. 30 05. 30 10 - - Capacitor bank unbalance internal preparation - INTERNAL
9-Sep-22 07. 30 05. 30 10 - - 11kV Cable Label works - INTERNAL
10-Sep-22 - - - - - --------HOLIDAY----------
11kV Capacitor bank O&M Manual works - Assembly part list and possitioning
11-Sep-22 07. 30 05. 30 10 - -
chart preparation
11kV Capacitor bank 1 To 6 Unbalance current measurement checks
12-Sep-22 07. 30 05. 30 10 - -

SCMS Common Alarm signals - INTERNAL


13-Sep-22 07. 30 05. 30 10 - -

SCMS Common Alarm signals - INTERNAL


14-Sep-22 07. 30 05. 30 10 - -

SCMS Common Alarm signals - INTERNAL


15-Sep-22 07. 30 05. 30 10 - -

SCMS Common Alarm signals - INTERNAL


16-Sep-22 07. 30 05. 30 10 - -

17-Sep-22 - - - - - --------HOLIDAY----------

18-Sep-22 07. 30 05. 30 10 - - SCMS Common Alarm signals - INTERNAL

19-Sep-22 07. 30 05. 30 10 - - SCMS Common Alarm signals - INTERNAL

20-Sep-22 07. 30 05. 30 10 - - SCMS Common Alarm signals - INTERNAL

21-Sep-22 07. 30 05. 30 10 - - SCMS L3 - 11kV SWGR - INTERNAL

22-Sep-22 07. 30 05. 30 10 - - SCMS L3 - 11kV SWGR - INTERNAL

23-Sep-22 07. 30 05. 30 10 - - SCMS L3 - 11kV SWGR - INTERNAL


24-Sep-22 - - - - - --------HOLIDAY----------

25-Sep-22 07. 30 05. 30 10 - - SCMS L3 - 11kV SWGR - INTERNAL

26-Sep-22 07. 30 05. 30 10 - - SCMS L3 - 11kV SWGR - INTERNAL

27-Sep-22 07. 30 05. 30 10 - - SCMS L3 - 11kV SWGR - INTERNAL

28-Sep-22 07. 30 05. 30 10 - - SCMS L3 - 11kV SWGR - INTERNAL

29-Sep-22 07. 30 05. 30 10 - - CUC-5 ENENRGIZATION

30-Sep-22 07. 30 05. 30 10 - - CUC-5 ENENRGIZATION

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF SEPTEMBER 2022


CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: RAJA PALANISAMY
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Sep-22
2-Sep-22
3-Sep-22
4-Sep-22
5-Sep-22
6-Sep-22
7-Sep-22
8-Sep-22
9-Sep-22
10-Sep-22

11-Sep-22

12-Sep-22

13-Sep-22

14-Sep-22

15-Sep-22

16-Sep-22

17-Sep-22

18-Sep-22

19-Sep-22

20-Sep-22 07. 30 05. 30 10 - - 11kV Without Metering Trip Logic test Dewa Witness

21-Sep-22 07. 30 05. 30 10 - - 132kV M2BBP Final Settings Manufacture Coordination

22-Sep-22 07. 30 05. 30 10 - - 132kV M2BBP Final Settings Manufacture Coordination

23-Sep-22 07. 30 05. 30 10 - - 132kV M2BBP Final Settings Manufacture Coordination

24-Sep-22 - - - - - --------HOLIDAY----------

25-Sep-22 07. 30 05. 30 10 - - 11kV Incomer Trip Logic Test Internal Preparation

26-Sep-22 07. 30 05. 30 10 - - 11kV With Metering & Incomer Trip Logic test Dewa Witness

27-Sep-22 07. 30 05. 30 10 - - 11kV Incomer Trip Logic test Dewa Witness

28-Sep-22 07. 30 05. 30 10 - - 11kV BUS SECTION-1 Trip Logic test Dewa Witness

29-Sep-22 07. 30 05. 30 10 - - 11kV BBP Functional checks internal preparation

30-Sep-22 07. 30 05. 30 10 - - 11kV BS-2 Trip Logic test&DMZ Panel Outgoing cable Checks Dewa Witness

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF SEPTEMBER 2022


CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: SIJIN DIYO
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
2-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
3-Sep-22 - - - - - --------HOLIDAY----------
4-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
5-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
6-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
7-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
8-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
9-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works
10-Sep-22 - - - - - --------HOLIDAY----------

11-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

12-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

13-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

14-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

15-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

16-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

17-Sep-22 - - - - - --------HOLIDAY----------

18-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

19-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

20-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

21-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

22-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

23-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

24-Sep-22 - - - - - --------HOLIDAY----------

25-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

26-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

27-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

28-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

29-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

30-Sep-22 07. 30 05. 30 10 - - Supporting Activity for Site Documnets& Works

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com
TIME SHEET FOR THE MONTH OF OCTOBER 2022
CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: RAJA PALANISAMY
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Oct-22 - - - - - --------HOLIDAY----------
2-Oct-22 07. 30 05. 30 10 - - 132kV IDT NCT Primary Injection internal preparation
3-Oct-22
4-Oct-22
5-Oct-22
6-Oct-22
7-Oct-22
8-Oct-22 --------HOLIDAY----------
9-Oct-22
10-Oct-22

11-Oct-22

12-Oct-22

13-Oct-22

14-Oct-22

15-Oct-22 --------HOLIDAY----------

16-Oct-22

17-Oct-22

18-Oct-22

19-Oct-22

20-Oct-22

21-Oct-22

22-Oct-22 --------HOLIDAY----------

23-Oct-22

24-Oct-22

25-Oct-22

26-Oct-22

27-Oct-22

28-Oct-22

29-Oct-22 --------HOLIDAY----------

30-Oct-22

31-Oct-22

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF OCTOBER 2022


CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Oct-22 - - - - - --------HOLIDAY----------
2-Oct-22 07. 30 05. 30 10 - - CUC-5 Reports works
3-Oct-22 07. 30 05. 30 10 - - CUC-5 Reports works
4-Oct-22 07. 30 05. 30 10 - - CUC-5 Documentation works
5-Oct-22 07. 30 05. 30 10 - - CUC-5 Documentation works
6-Oct-22 07. 30 05. 30 10 - - SANAD SS - SRC For LV CABLES,GIS ID - 35,36,37 - Verified
7-Oct-22 07. 30 05. 30 10 - - MRINACMN - L3 Update
8-Oct-22 - - - - - --------HOLIDAY----------

9-Oct-22 07. 30 05. 30 10 - - MRINACMN - L3 Update

10-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing

11-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing

12-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing


11kV SWGR L3 Testing With and Without metering F01 To E31 Interlock
13-Oct-22 07. 30 05. 30 10 - - Completed and Operation checks of F01 To F71 Completed

11kV SWGR L3 Testing


14-Oct-22 07. 30 05. 30 10 - - With and Without metering F32 To E46 Interlock Completed

15-Oct-22 - - - - - --------HOLIDAY----------

16-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing issues rectfication


11kV SWGR L3 Testing With and Without metering Bus1 Interlock
17-Oct-22 07. 30 05. 30 10 - - Completed.Capacitor and BS1,nterlock Completed
11kV SWGR L3 Testing With and Without metering Bus2 Interlock
18-Oct-22 07. 30 05. 30 10 - - Completed.Capacitor and BS2 Interlock Completed

11kV SWGR L3 Testing With and Without metering Bus3 Interlock


19-Oct-22 07. 30 05. 30 10 - - Completed.Capacitor and BS2 Interlock Completed

20-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing completed except Incomers and site note feeders

21-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 documents & report Signing.


22-Oct-22 - - - - - --------HOLIDAY----------

23-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing issues rectfication


24-Oct-22 07. 30 05. 30 10 - - Capacitor bank Damping Reactor HV Test
25-Oct-22 07. 30 05. 30 10 - - Capacitor bank Damping Reactor HV Test

26-Oct-22 07. 30 05. 30 10 - - 132kV SWGR As-built Drawing works

27-Oct-22 07. 30 05. 30 10 - - 132kV SWGR As-built Drawing works

28-Oct-22 07. 30 05. 30 10 - - 132kV SWGR As-built Drawing works

29-Oct-22 - - - - - --------HOLIDAY----------

30-Oct-22 07. 30 05. 30 10 - - 132kV SWGR As-built Drawing works

31-Oct-22 07. 30 05. 30 10 - - 132kV SWGR As-built Drawing works

ENGINEER SIGNATURE CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF OCTOBER 2022


CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: sigin diyo.R
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Oct-22 - - - - - --------HOLIDAY----------
2-Oct-22 07. 30 05. 30 10 - - 132kv triplogic testing
3-Oct-22 07. 30 05. 30 10 - - 132kv triplogic testing
4-Oct-22 07. 30 05. 30 10 - - 132kv primary injection testing
5-Oct-22 07. 30 05. 30 10 - - 132kv primary injection testing
6-Oct-22 07. 30 05. 30 10 - - 132kv primary injection testing
7-Oct-22 07. 30 05. 30 10 - - 132kv primary injection testing
8-Oct-22 - - - - - --------HOLIDAY----------

9-Oct-22 07. 30 05. 30 10 - - 132kv primary injection internal

10-Oct-22 07. 30 05. 30 10 - - 132kv sensitivity internal

11-Oct-22 07. 30 05. 30 10 - - 132kv sensitivity internal

12-Oct-22 07. 30 05. 30 10 - - 132kv sensitivity testing


132kv sensitivity testing
13-Oct-22 07. 30 05. 30 10 - -

132kv sensitivity testing


14-Oct-22 07. 30 05. 30 10 - -

15-Oct-22 - - - - - --------HOLIDAY----------

16-Oct-22 07. 30 05. 30 10 - - 132kv stability internal


132kv stability internal
17-Oct-22 07. 30 05. 30 10 - -

132 kv stability testing


18-Oct-22 07. 30 05. 30 10 - -

132kv stability testing


19-Oct-22 07. 30 05. 30 10 - -

20-Oct-22 07. 30 05. 30 10 - - 132kv stability testing

21-Oct-22 07. 30 05. 30 10 - - ET primary injection drawing checks


22-Oct-22 - - - - - --------HOLIDAY----------

23-Oct-22 07. 30 05. 30 10 - - 11kV SWGR L3 Testing issues rectfication


24-Oct-22 07. 30 05. 30 10 - - Capacitor bank Damping Reactor HV Test
25-Oct-22 07. 30 05. 30 10 - - Capacitor bank Damping Reactor HV Test

26-Oct-22 07. 30 05. 30 10 - - IDT &ET&SHX name plate verification

27-Oct-22 07. 30 05. 30 10 - - SHX-1 OTI/WTI gradiant

28-Oct-22 07. 30 05. 30 10 - - SHX-1 OTI/WTI calibiration

29-Oct-22 - - - - - --------HOLIDAY----------

30-Oct-22 07. 30 05. 30 10 - - SHX-2 OTI/WTI gradiant

31-Oct-22 07. 30 05. 30 10 - - SHX-2 OTI/WTI calibiration

ENGINEER SIGNATURE: SIGINDIYO R CUSTOMER SIGNATURE


ARABIAN GULF POWER GAIN TECHNICAL SERVICES L.L.C
#M-06-22, HHM Business Center , Acico Business Park, Deria, Dubai, U.A.E.
P.O.Box 83639. Contact : Mob.: 050-7559516 & 0553806253
www.agpgain.com, info@agpgain.com

TIME SHEET FOR THE MONTH OF NOVEMBER 2022


CUSTOMER: AG PCS SITE CO-ORDINATOR: Mr.Binu
PROJECT : 132/11kV MRINACMNS/S ENGINEER NAME: Muralidharan.s
Special
Date Time-In Time-Out Normal Hrs O.T Hrs Job Details
O.T Hrs
1-Nov-22 07. 30 05. 30 10 - - Asbuilt drawing works - 132kV SWGR Internal
2-Nov-22 07. 30 05. 30 10 - - Asbuilt drawing works - 132kV SWGR Internal
3-Nov-22 07. 30 05. 30 10 - - Asbuilt drawing works - 132kV SWGR & FAT MOM - 11KV SWGR
4-Nov-22 07. 30 05. 30 10 - - Asbuilt drawing works - 132kV SWGR & FAT MOM - 11KV SWGR
5-Nov-22 - - - - - --------HOLIDAY----------
6-Nov-22 07. 30 05. 30 10 - - SANAD SS - LVAC Installation checks
7-Nov-22 07. 30 05. 30 10 - - SANAD SS - LVAC Installation checks
8-Nov-22 07. 30 05. 30 10 - - SANAD SS - LVAC Installation checks
9-Nov-22 07. 30 05. 30 10 - -
LVAC Energization works Internal
10-Nov-22 07. 30 05. 30 10 - -
LVAC Energization works Internal
11-Nov-22 07. 30 05. 30 10 - -
LVAC Energization works - Witness
12-Nov-22 - - - - -
--------HOLIDAY----------
13-Nov-22 07. 30 05. 30 10 - -
As built drawing works Internal
14-Nov-22 07. 30 05. 30 10 - - SANAD SS - LVAC Installation checks
15-Nov-22 07. 30 05. 30 10 - -
As built drawing works Internal
16-Nov-22 07. 30 05. 30 10 - -
As built drawing works Internal
17-Nov-22 07. 30 05. 30 10 - -
As built drawing works Internal
18-Nov-22 07. 30 05. 30 10 - -
As built drawing works Internal
19-Nov-22 - - - - -
--------HOLIDAY----------

20-Nov-22 07. 30 05. 30 10 - - As built drawing works - 132kV SWGR


And Record Room File works
21-Nov-22 07. 30 05. 30 10 - - As built drawing works - 132kV SWGR
And Record Room File works
22-Nov-22 07. 30 05. 30 10 - - As built drawing works - ET
And 132KV Cable HV Test MOS Preparation
23-Nov-22 07. 30 05. 30 10 - -
LVAC Outgoing Cables Checks Witness
24-Nov-22 07. 30 05. 30 10 - - HLDB Outgoing Cables Checks Witness
25-Nov-22 07. 30 05. 30 10 - -
LVAC Outgoing Cables Checks Witness
26-Nov-22 - - - - -
--------HOLIDAY----------
27-Nov-22 07. 30 05. 30 10 - -
LVAC and HLDB Outgoing Cables Checks
28-Nov-22 07. 30 05. 30 10 - -
LVAC and HLDB Outgoing Cables Checks Witness
29-Nov-22 07. 30 05. 30 10 - -
HLDB Outgoing Cables Checks Witness
30-Nov-22 07. 30 05. 30 10 - -
HLDB Outgoing Cables Checks Witness

ENGINEER SIGNATURE CUSTOMER SIGNATURE

You might also like