EJN-0B207 Installation of Filteration System Downstream P-x515

Activity ID Activity Name Original Budgeted Start Finish Units %


Duration Labor Units Complete

EJN-0B207 Installation of Filteration System


EJN-0B2 633d 6270h 16-Feb-22 01:00 PM 25-Feb-24 01:00 PM 0%

Bidding and Contract Award 5d 50h 16-Feb-22 01:00 PM 22-Feb-22 12:00 PM 0%

A1000 Contract Award Notification 1d 10h 16-Feb-22 01:00 PM 17-Feb-22 12:00 PM 0%


A1010 Receipt of Purchase order 1d 10h 17-Feb-22 01:00 PM 19-Feb-22 12:00 PM 0%
A1020 GIH Training 1d 10h 19-Feb-22 01:00 PM 20-Feb-22 12:00 PM 0%
A1030 Kick off Meeting 1d 10h 20-Feb-22 01:00 PM 21-Feb-22 12:00 PM 0%
A1040 Document Submision 1d 10h 21-Feb-22 01:00 PM 22-Feb-22 12:00 PM 0%

Project Milestones
M 615d 0h 17-Feb-22 01:00 PM 05-Feb-24 01:00 PM 0%

A1050 Project Start 0d 0h 17-Feb-22 01:00 PM 0%


A1060 Project Finish 0d 0h 05-Feb-24 01:00 PM 0%

Project Procurement
P Works 334d 3340h 22-Feb-22 01:00 PM 19-Mar-23 01:00 PM 0%
A1070 Sadara Free Issue Filters 30d 300h 22-Feb-22 01:00 PM 29-Mar-22 12:00 PM 0%
A1080 Sadara Free Issue PSV 30d 300h 29-Mar-22 01:00 PM 03-May-22 12:00 PM 0%
A1090 GACC Piping Materials - Pipes and Fittings 55d 550h 03-May-22 01:00 PM 06-Jul-22 01:00 PM 0%
A1100 GACC Piping Materials - Bolts & gaskets 55d 550h 06-Jul-22 01:00 PM 08-Sep-22 01:00 PM 0%
A1110 GACC Piping Materials - Valves MAR Submission 7d 70h 08-Sep-22 01:00 PM 17-Sep-22 01:00 PM 0%
A1110.10 GACC Piping Materials - Valves PO Issue 7d 70h 17-Sep-22 01:00 PM 25-Sep-22 01:00 PM 0%
A1110.20 GACC Piping Materials - Valves Delivery 60d 600h 25-Sep-22 01:00 PM 04-Dec-22 01:00 PM 0%
A1120 GACC Insulation Materials Delivery 90d 900h 04-Dec-22 01:00 PM 19-Mar-23 01:00 PM 0%

Shop Works
W 103d 1030h 19-Mar-23 01:00 PM 17-Jul-23 01:00 PM 0%

Inspection Works 6d 60h 19-Mar-23 01:00 PM 26-Mar-23 01:00 PM 0%


A1130 Materials Inspection - Piping Materials - Pipes & Fitti 1d 10h 19-Mar-23 01:00 PM 20-Mar-23 01:00 PM 0%
A1140 Materials Inspection - Piping Materials - Bolts & Gas 1d 10h 20-Mar-23 01:00 PM 21-Mar-23 01:00 PM 0%
A1150 Materials Inspection - Piping Materials - Valves 1d 10h 21-Mar-23 01:00 PM 22-Mar-23 01:00 PM 0%
A1160 Materials Inspection - Filters 1d 10h 22-Mar-23 01:00 PM 23-Mar-23 01:00 PM 0%
A1170 Materials Inspection - PSV 1d 10h 23-Mar-23 01:00 PM 25-Mar-23 01:00 PM 0%
A1180 Materials Inspection - Insulation Materials 1d 10h 25-Mar-23 01:00 PM 26-Mar-23 01:00 PM 0%
Piping Works
Wo 59d 590h 26-Mar-23 01:00 PM 03-Jun-23 01:00 PM 0%
A1190 Marking & Cutting of Pipes 15d 150h 26-Mar-23 01:00 PM 12-Apr-23 01:00 PM 0%
A1200 Fitup Works 15d 150h 12-Apr-23 01:00 PM 30-Apr-23 01:00 PM 0%
A1210 Welding Works 20d 200h 30-Apr-23 01:00 PM 23-May-23 01:00 PM 0%
A1220 NDT Works 2d 20h 23-May-23 01:00 PM 25-May-23 01:00 PM 0%
A1230 Hydrotesting Works 2d 20h 25-May-23 01:00 PM 28-May-23 01:00 PM 0%
A1240 Painting Works 4d 40h 28-May-23 01:00 PM 01-Jun-23 01:00 PM 0%
A1250 Final Inspection 1d 10h 01-Jun-23 01:00 PM 03-Jun-23 01:00 PM 0%
Structural Works 38d 380h 03-Jun-23 01:00 PM 17-Jul-23 01:00 PM 0%
A1260 Marking & Cutting of Supports 10d 100h 03-Jun-23 01:00 PM 14-Jun-23 01:00 PM 0%
A1270 Fitup Works 10d 100h 14-Jun-23 01:00 PM 26-Jun-23 01:00 PM 0%
A1280 Welding Works 12d 120h 26-Jun-23 01:00 PM 10-Jul-23 01:00 PM 0%
A1290 Inspection prior to galvanizing 1d 10h 10-Jul-23 01:00 PM 11-Jul-23 01:00 PM 0%
A1300 Galvanizing works 4d 40h 11-Jul-23 01:00 PM 16-Jul-23 01:00 PM 0%
A1310 Final Inspection 1d 10h 16-Jul-23 01:00 PM 17-Jul-23 01:00 PM 0%

Site Works
Wo 170d 1640h 17-Jul-23 01:00 PM 31-Jan-24 01:00 PM 0%

Scaffolding Works
Scaffoldin 1d 10h 17-Jul-23 01:00 PM 18-Jul-23 01:00 PM 0%
A1320 Scaffolding Materials Mobilization works 1d 10h 17-Jul-23 01:00 PM 18-Jul-23 01:00 PM 0%
Train 1 92d 860h 18-Jul-23 01:00 PM 02-Nov-23 01:00 PM 0%
A1330 Scaffolding Installation for Pipelines 25d 250h 30-Jul-23 01:00 PM 28-Aug-23 01:00 PM 0%
A1340 Pipe Spools Mobilization works 2d 20h 18-Jul-23 01:00 PM 20-Jul-23 01:00 PM 0%
A1350 Filter Mobilization to Site 1d 10h 20-Jul-23 01:00 PM 22-Jul-23 01:00 PM 0%
A1360 PSV Mobilization to Site 1d 10h 22-Jul-23 01:00 PM 23-Jul-23 01:00 PM 0%
Filter Works
Wor - FL-1515A 6d 60h 28-Aug-23 01:00 PM 04-Sep-23 01:00 PM 0%
A1370 Location Marking for Filter 1d 10h 28-Aug-23 01:00 PM 29-Aug-23 01:00 PM 0%
A1380 Filter Erection on top of Structure 1d 10h 29-Aug-23 01:00 PM 30-Aug-23 01:00 PM 0%
A1390 Filter Installation works 2d 20h 30-Aug-23 01:00 PM 02-Sep-23 01:00 PM 0%
A1400 Bolting on Structures 2d 20h 02-Sep-23 01:00 PM 04-Sep-23 01:00 PM 0%

Page 1 of 6 © Oracle Corporation


EJN-0B207 Installation of Filteration System Downstream P-x515

Page 2 of 6 © Oracle Corporation


EJN-0B207 Installation of Filteration System Downstream P-x515
Activity ID Activity Name Original Budgeted Start Finish Units %
Duration Labor Units Complete

PH-153602-02 Line Works


PH-153602 18d 120h 04-Sep-23 01:00 PM 25-Sep-23 01:00 PM 0%
A1410 Operations Release and Line Isolation works 1d 10h 04-Sep-23 01:00 PM 05-Sep-23 01:00 PM 0%
Demolition Works
Demolitio 1d 10h 05-Sep-23 01:00 PM 06-Sep-23 01:00 PM 0%
A1420 Existing Line Demolition works 1d 10h 05-Sep-23 01:00 PM 06-Sep-23 01:00 PM 0%
Installation Works
Installatio 16d 100h 06-Sep-23 01:00 PM 25-Sep-23 01:00 PM 0%
A1430 Spool Erection as per the Isometrics 4d 40h 06-Sep-23 01:00 PM 11-Sep-23 01:00 PM 0%
A1440 Bolting to Existing Valves 2d 20h 11-Sep-23 01:00 PM 13-Sep-23 01:00 PM 0%
A1450 Bolting to Filter works 2d 20h 13-Sep-23 01:00 PM 16-Sep-23 01:00 PM 0%
A1500 Bolt Torquing Works 2d 20h 23-Sep-23 01:00 PM 25-Sep-23 01:00 PM 0%
PH-153605-02 Line Works
PH-153605 10d 80h 16-Sep-23 01:00 PM 27-Sep-23 01:00 PM 0%
A1460 Operations Release and Line Isolation works 1d 10h 16-Sep-23 01:00 PM 17-Sep-23 01:00 PM 0%
Demolition Works
Demolitio 1d 10h 17-Sep-23 01:00 PM 18-Sep-23 01:00 PM 0%
A1470 Existing Line Demolition works 1d 10h 17-Sep-23 01:00 PM 18-Sep-23 01:00 PM 0%
Installation Works
Installatio 8d 60h 18-Sep-23 01:00 PM 27-Sep-23 01:00 PM 0%
A1480 Spool Erection as per the Isometrics 2d 20h 18-Sep-23 01:00 PM 20-Sep-23 01:00 PM 0%
A1490 Bolting Works to Existing Lines 2d 20h 20-Sep-23 01:00 PM 23-Sep-23 01:00 PM 0%
A1510 Bolt Torquing Works 2d 20h 25-Sep-23 01:00 PM 27-Sep-23 01:00 PM 0%
PH-153601-01 Line Works
PH-153601 9d 90h 27-Sep-23 01:00 PM 08-Oct-23 01:00 PM 0%
A1510.10 Gratings Works - Modification Works 3d 30h 27-Sep-23 01:00 PM 01-Oct-23 01:00 PM 0%
A1520 Spool Erection as per the Isometrics 2d 20h 01-Oct-23 01:00 PM 03-Oct-23 01:00 PM 0%
A1530 Bolting Works to Existing Lines 2d 20h 03-Oct-23 01:00 PM 05-Oct-23 01:00 PM 0%
A1540 Bolt Torquing Works 2d 20h 05-Oct-23 01:00 PM 08-Oct-23 01:00 PM 0%
PH-153608-01 Line Works
PH-153608 9d 90h 08-Oct-23 01:00 PM 18-Oct-23 01:00 PM 0%
A1550 Spool Erection as per the Isometrics 2d 20h 08-Oct-23 01:00 PM 10-Oct-23 01:00 PM 0%
A1560 Bolting Works to Existing Lines 2d 20h 10-Oct-23 01:00 PM 12-Oct-23 01:00 PM 0%
A1570 Bolt Torquing Works 2d 20h 12-Oct-23 01:00 PM 15-Oct-23 01:00 PM 0%
PSV Valve
Valv Installation 3d 30h 15-Oct-23 01:00 PM 18-Oct-23 01:00 PM 0%
A1580 PSV Installation works 1d 10h 15-Oct-23 01:00 PM 16-Oct-23 01:00 PM 0%
A1590 Bolt Torquing Works 2d 20h 16-Oct-23 01:00 PM 18-Oct-23 01:00 PM 0%
V-153611-01 Line Works
V-153611- 9d 90h 18-Oct-23 01:00 PM 29-Oct-23 01:00 PM 0%
A1590.10 Gratings Works - Modification Works 3d 30h 18-Oct-23 01:00 PM 22-Oct-23 01:00 PM 0%
A1600 Spool Erection as per the Isometrics 2d 20h 22-Oct-23 01:00 PM 24-Oct-23 01:00 PM 0%
A1610 Bolting Works to Existing Lines 2d 20h 24-Oct-23 01:00 PM 26-Oct-23 01:00 PM 0%
A1620 Bolt Torquing Works 2d 20h 26-Oct-23 01:00 PM 29-Oct-23 01:00 PM 0%
V-153614-01 Line Works
V-153614- 4d 40h 29-Oct-23 01:00 PM 02-Nov-23 01:00 PM 0%
A1630 Bolting Works to Existing Lines 2d 20h 29-Oct-23 01:00 PM 31-Oct-23 01:00 PM 0%
A1640 Bolt Torquing Works 2d 20h 31-Oct-23 01:00 PM 02-Nov-23 01:00 PM 0%
Train 2 77d 770h 02-Nov-23 01:00 PM 31-Jan-24 01:00 PM 0%
A1650 Scaffolding Installation for Pipelines 15d 150h 02-Nov-23 01:00 PM 20-Nov-23 01:00 PM 0%
A1660 Pipe Spools Mobilization works 1d 10h 20-Nov-23 01:00 PM 21-Nov-23 01:00 PM 0%
A1670 Filter Mobilization to Site 1d 10h 21-Nov-23 01:00 PM 22-Nov-23 01:00 PM 0%
A1680 PSV Mobilization to Site 1d 10h 22-Nov-23 01:00 PM 23-Nov-23 01:00 PM 0%
Filter Works
Wor - FL-2515A 6d 60h 23-Nov-23 01:00 PM 30-Nov-23 01:00 PM 0%
A1690 Location Marking for Filter 1d 10h 23-Nov-23 01:00 PM 25-Nov-23 01:00 PM 0%
A1700 Filter Erection on top of Structure 1d 10h 25-Nov-23 01:00 PM 26-Nov-23 01:00 PM 0%
A1710 Filter Installation works 2d 20h 26-Nov-23 01:00 PM 28-Nov-23 01:00 PM 0%
A1720 Bolting on Structures 2d 20h 28-Nov-23 01:00 PM 30-Nov-23 01:00 PM 0%
PH-253602-02 Line Works
PH-253602 14d 140h 30-Nov-23 01:00 PM 17-Dec-23 01:00 PM 0%
A1730 Operations Release and Line Isolation works 1d 10h 30-Nov-23 01:00 PM 02-Dec-23 01:00 PM 0%
Demolition Works
Demolitio 1d 10h 02-Dec-23 01:00 PM 03-Dec-23 01:00 PM 0%
A1740 Existing Line Demolition works 1d 10h 02-Dec-23 01:00 PM 03-Dec-23 01:00 PM 0%
Installation Works
Installatio 12d 120h 03-Dec-23 01:00 PM 17-Dec-23 01:00 PM 0%
A1750 Spool Erection as per the Isometrics 4d 40h 03-Dec-23 01:00 PM 07-Dec-23 01:00 PM 0%
A1760 Bolting to Existing Valves 4d 40h 07-Dec-23 01:00 PM 12-Dec-23 01:00 PM 0%
A1770 Bolting to Filter works 2d 20h 12-Dec-23 01:00 PM 14-Dec-23 01:00 PM 0%
A1780 Bolt Torquing Works 2d 20h 14-Dec-23 01:00 PM 17-Dec-23 01:00 PM 0%

Page 3 of 6 © Oracle Corporation


EJN-0B207 Installation of Filteration System Downstream P-x515

Page 4 of 6 © Oracle Corporation


EJN-0B207 Installation of Filteration System Downstream P-x515
Activity ID Activity Name Original Budgeted Start Finish Units %
Duration Labor Units Complete

PH-253605-02 Line Works


PH-253605 14d 80h 17-Dec-23 01:00 PM 02-Jan-24 01:00 PM 0%
A1790 Operations Release and Line Isolation works 1d 10h 17-Dec-23 01:00 PM 18-Dec-23 01:00 PM 0%
Demolition Works
Demolitio 1d 10h 25-Dec-23 01:00 PM 26-Dec-23 01:00 PM 0%
A1800 Existing Line Demolition works 1d 10h 25-Dec-23 01:00 PM 26-Dec-23 01:00 PM 0%
Installation Works
Installatio 6d 60h 26-Dec-23 01:00 PM 02-Jan-24 01:00 PM 0%
A1810 Spool Erection as per the Isometrics 2d 20h 26-Dec-23 01:00 PM 28-Dec-23 01:00 PM 0%
A1820 Bolting Works to Existing Lines 2d 20h 28-Dec-23 01:00 PM 31-Dec-23 01:00 PM 0%
A1830 Bolt Torquing Works 2d 20h 31-Dec-23 01:00 PM 02-Jan-24 01:00 PM 0%
PH-253601-01 Line Works
PH-253601 19d 90h 18-Dec-23 01:00 PM 09-Jan-24 01:00 PM 0%
A1510.20 Gratings Works - Modification Works 3d 30h 18-Dec-23 01:00 PM 21-Dec-23 01:00 PM 0%
A1840 Spool Erection as per the Isometrics 2d 20h 02-Jan-24 01:00 PM 04-Jan-24 01:00 PM 0%
A1850 Bolting Works to Existing Lines 2d 20h 04-Jan-24 01:00 PM 07-Jan-24 01:00 PM 0%
A1860 Bolt Torquing Works 2d 20h 07-Jan-24 01:00 PM 09-Jan-24 01:00 PM 0%
PH-253608-01 Line Works
PH-253608 9d 90h 09-Jan-24 01:00 PM 20-Jan-24 01:00 PM 0%
A1870 Spool Erection as per the Isometrics 2d 20h 09-Jan-24 01:00 PM 11-Jan-24 01:00 PM 0%
A1880 Bolting Works to Existing Lines 2d 20h 11-Jan-24 01:00 PM 14-Jan-24 01:00 PM 0%
A1890 Bolt Torquing Works 2d 20h 14-Jan-24 01:00 PM 16-Jan-24 01:00 PM 0%
PSV Valve
Valv Installation 3d 30h 16-Jan-24 01:00 PM 20-Jan-24 01:00 PM 0%
A1900 PSV Installation works 1d 10h 16-Jan-24 01:00 PM 17-Jan-24 01:00 PM 0%
A1910 Bolt Torquing Works 2d 20h 17-Jan-24 01:00 PM 20-Jan-24 01:00 PM 0%
V-253611-01 Line Works
V-253611- 31d 90h 21-Dec-23 01:00 PM 27-Jan-24 01:00 PM 0%
A1590.20 Gratings Works - Modification Works 3d 30h 21-Dec-23 01:00 PM 25-Dec-23 01:00 PM 0%
A1920 Spool Erection as per the Isometrics 2d 20h 20-Jan-24 01:00 PM 22-Jan-24 01:00 PM 0%
A1930 Bolting Works to Existing Lines 2d 20h 22-Jan-24 01:00 PM 24-Jan-24 01:00 PM 0%
A1940 Bolt Torquing Works 2d 20h 24-Jan-24 01:00 PM 27-Jan-24 01:00 PM 0%
NL-253614-01 Line Works
NL-253614 4d 40h 27-Jan-24 01:00 PM 31-Jan-24 01:00 PM 0%
A1950 Bolting Works to Existing Lines 2d 20h 27-Jan-24 01:00 PM 29-Jan-24 01:00 PM 0%
A1960 Bolt Torquing Works 2d 20h 29-Jan-24 01:00 PM 31-Jan-24 01:00 PM 0%

MCC Walkdown
Wa and Punch Clearance 4d 40h 31-Jan-24 01:00 PM 05-Feb-24 01:00 PM 0%

A1970 MCC Walkdown 1d 10h 31-Jan-24 01:00 PM 01-Feb-24 01:00 PM 0%


A1980 Punch Clearance 1d 10h 01-Feb-24 01:00 PM 03-Feb-24 01:00 PM 0%
A1990 PSSR Walkdown 1d 10h 03-Feb-24 01:00 PM 04-Feb-24 01:00 PM 0%
A2000 Punch Clearance 1d 10h 04-Feb-24 01:00 PM 05-Feb-24 01:00 PM 0%

Hand Over
Ov Works 17d 170h 05-Feb-24 01:00 PM 25-Feb-24 01:00 PM 0%

A2010 Scaffolding Dismantling 5d 50h 05-Feb-24 01:00 PM 11-Feb-24 01:00 PM 0%


A2020 Construction Completion 1d 10h 11-Feb-24 01:00 PM 12-Feb-24 01:00 PM 0%
A2030 Handover 1d 10h 12-Feb-24 01:00 PM 13-Feb-24 01:00 PM 0%
A2040 Document Submission 10d 100h 13-Feb-24 01:00 PM 25-Feb-24 01:00 PM 0%