Project Milestones
M 615d 0h 17-Feb-22 01:00 PM 05-Feb-24 01:00 PM 0%
Project Procurement
P Works 334d 3340h 22-Feb-22 01:00 PM 19-Mar-23 01:00 PM 0%
A1070 Sadara Free Issue Filters 30d 300h 22-Feb-22 01:00 PM 29-Mar-22 12:00 PM 0%
A1080 Sadara Free Issue PSV 30d 300h 29-Mar-22 01:00 PM 03-May-22 12:00 PM 0%
A1090 GACC Piping Materials - Pipes and Fittings 55d 550h 03-May-22 01:00 PM 06-Jul-22 01:00 PM 0%
A1100 GACC Piping Materials - Bolts & gaskets 55d 550h 06-Jul-22 01:00 PM 08-Sep-22 01:00 PM 0%
A1110 GACC Piping Materials - Valves MAR Submission 7d 70h 08-Sep-22 01:00 PM 17-Sep-22 01:00 PM 0%
A1110.10 GACC Piping Materials - Valves PO Issue 7d 70h 17-Sep-22 01:00 PM 25-Sep-22 01:00 PM 0%
A1110.20 GACC Piping Materials - Valves Delivery 60d 600h 25-Sep-22 01:00 PM 04-Dec-22 01:00 PM 0%
A1120 GACC Insulation Materials Delivery 90d 900h 04-Dec-22 01:00 PM 19-Mar-23 01:00 PM 0%
Shop Works
W 103d 1030h 19-Mar-23 01:00 PM 17-Jul-23 01:00 PM 0%
Site Works
Wo 170d 1640h 17-Jul-23 01:00 PM 31-Jan-24 01:00 PM 0%
Scaffolding Works
Scaffoldin 1d 10h 17-Jul-23 01:00 PM 18-Jul-23 01:00 PM 0%
A1320 Scaffolding Materials Mobilization works 1d 10h 17-Jul-23 01:00 PM 18-Jul-23 01:00 PM 0%
Train 1 92d 860h 18-Jul-23 01:00 PM 02-Nov-23 01:00 PM 0%
A1330 Scaffolding Installation for Pipelines 25d 250h 30-Jul-23 01:00 PM 28-Aug-23 01:00 PM 0%
A1340 Pipe Spools Mobilization works 2d 20h 18-Jul-23 01:00 PM 20-Jul-23 01:00 PM 0%
A1350 Filter Mobilization to Site 1d 10h 20-Jul-23 01:00 PM 22-Jul-23 01:00 PM 0%
A1360 PSV Mobilization to Site 1d 10h 22-Jul-23 01:00 PM 23-Jul-23 01:00 PM 0%
Filter Works
Wor - FL-1515A 6d 60h 28-Aug-23 01:00 PM 04-Sep-23 01:00 PM 0%
A1370 Location Marking for Filter 1d 10h 28-Aug-23 01:00 PM 29-Aug-23 01:00 PM 0%
A1380 Filter Erection on top of Structure 1d 10h 29-Aug-23 01:00 PM 30-Aug-23 01:00 PM 0%
A1390 Filter Installation works 2d 20h 30-Aug-23 01:00 PM 02-Sep-23 01:00 PM 0%
A1400 Bolting on Structures 2d 20h 02-Sep-23 01:00 PM 04-Sep-23 01:00 PM 0%
MCC Walkdown
Wa and Punch Clearance 4d 40h 31-Jan-24 01:00 PM 05-Feb-24 01:00 PM 0%
Hand Over
Ov Works 17d 170h 05-Feb-24 01:00 PM 25-Feb-24 01:00 PM 0%