S.M. Nirman Infrastructure & Development Pvt. Ltd.

20/3, S.N. Roy Road, Kolkata-700 038


Contractor Name : - Seikh Mainul Haque
Bill Date : - 05.03.2024 Bill No . - 3RD RA Bill Period:- 01.02.2024 to 29.02.2024 PAN NO: AEHPH4323J
PROJECT :- CORE & SHELL WORK FOR TOWER 12, PODIUM, UGR, STP & RAC AT USSHAR, BATANAGAR, KOLKATA
SL UPTO PREVIOUS PRESENT BILL CUMULATIVE Remarks
DESCRIPTION OF WORK Unit RATE
NO. QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
Supply Labour
1 Chipper Nos 500.00 307.000 153500.00 220.000 110000.00 527.000 263500.00

Gross Bill Amount 153500.00 110000.00 263500.00


Less T.D.S. 1.0 % -1535.00 -1100.00 -2635.00
Less if any 0.00 0.00
Less Materials Issued 0.00
Less Advance Paid Including Khoraki 0.00
Hold Amount for any work 0.00
Deducation Amount for Supply 0.00
Round Off
Payble Bill Amount ₹ 151,965.00 ₹ 108,900.00 ₹ 260,865.00
Amount in word : One Lakh Eight Thousand Nine Hundred Rupees Only.

Signature of Contractor with Date Signature of Client with date


SEIKH MAINUL HAQUE
Details of JMR for Unskilled Labour Usshar , Batanagar
Chipper Work

JMR No.
SL. No.

Date Start Time End Time Duration of Nos. of Total Time for Remarks
(Hrs.) (Hrs.) Work (Hrs) Chipper Chipper (Hrs.)

RA-1 (December,23)
RA-2 (January,24)
RA-3 (February,24)
1 1-Feb-24 51 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12: Top Mivan chiping work & 20th Fl.
Planter Chiping Work.

2 2-Feb-24 52 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12: Top Mivan chiping work & 20th Fl.
Planter Chiping Work.
T-12: Top mivan chiping work, 19th &
3 3-Feb-24 53 6:00 AM 7:00 PM 12.00 5.0 60.00 20th Fl. Repairing, chiping work & Floor
chiping work.

4 4-Feb-24 54 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12: Top mivan chiping & 21st Fl.
Balcony, floor Chiping work.
T-12: Top mivan chiping work & 21st Fl.
5 5-Feb-24 55 6:00 AM 7:00 PM 12.00 5.0 60.00 Balcony and Wall (frame side), Sleve
cutting work.

6 6-Feb-24 56 6:00 AM 7:00 PM 12.00 4.0 48.00 T-12: 21st Fl. Sleve cutting & floor
Chiping Work and wall bulge cutting.

7 7-Feb-24 57 6:00 AM 7:00 PM 12.00 7.0 84.00 T-12: 23rd Fl. Floor Chiping work and
22nd Fl. loby chiping work.

8 8-Feb-24 58 6:00 AM 7:00 PM 12.00 7.0 84.00 T12: 22nd Fl. Sleve cutting and top mivan
chiping work.

9 9-Feb-24 59 6:00 AM 7:00 PM 12.00 7.0 84.00 T-12: 21st & 22nd Fl. Chiping work and
fire slab Chiping work.

10 10-Feb-24 60 6:00 AM 7:00 PM 12.00 7.0 84.00 T-12: 22nd Fl. Chiping work and fire slab
chiping work.

11 11-Feb-24 61 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12: 20th Fl. Rectification point work
and 21st Fl. Balcony Chiping work.
T-12: RAC 3rd Fl. Chiping work &
12 12-Feb-24 62 6:00 AM 7:00 PM 12.00 5.0 60.00 shunken Chiping work & 19th Fl.
Rectification work.

13 13-Feb-24 63 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12: Top mivan chiping & RAC _ 3rd Fl.
chiping work.

14 14-Feb-24 64 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_Top mivan chiping & 20th Floor
chiping work.

15 15-Feb-24 65 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_Top mivan chiping, RAC_3rd Fl.
chiping work.

16 16-Feb-24 66 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_Top mivan chiping, & 20th Fl.
chiping work.

17 17-Feb-24 67 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_Top mivan chiping & RAC _ 2nd Fl.
chiping work.

18 18-Feb-24 68 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_Top mivan chiping work & 22nd
Floor sleve cutting work.

19 19-Feb-24 69 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_Top mivan chiping work & RAC_
2nd Fl. chiping work.

20 20-Feb-24 70 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_Top mivan chiping work & 21st Fl.
rectification work.
6:00 AM 7:00 PM 12.00 4.0 48.00 T-12_Top mivan chiping work, 22nd Fl.
21 21-Feb-24 71
6:00 AM 9:00 PM 14.00 1.0 14.00 chiping work.

22 22-Feb-24 72 6:00 AM 7:00 PM 12.00 3.0 36.00 T-12_Top mivan chiping work & 22nd Fl.
Rectification work.

23 23-Feb-24 73 6:00 AM 7:00 PM 12.00 4.0 48.00 T-12_19th Fl. Wall chiping ( Frame side),
floor chiping work.

24 24-Feb-24 74 6:00 AM 7:00 PM 12.00 5.0 60.00 T-12_23rd Fl. Chiping work & RAC_ 2nd
Fl. Chiping work.
25 25-Feb-24 75 6:00 AM 7:00 PM 12.00 4.0 48.00 T-12_23rd Fl. Sleve cutting work.
6:00 AM 11:00 PM 16.00 2.0 32.00 T-12_23rd Fl. Balcony chiping work &
26 26-Feb-24 76
6:00 AM 7:00 PM 12.00 3.0 36.00 RAC_2nd Fl. chiping work.
6:00 AM 11:00 PM 16.00 2.0 32.00 T-12_23rd Fl. Wall chiping, Balcony
27 27-Feb-24 77
6:00 AM 7:00 PM 12.00 2.0 24.00 chiping, & sleve cutting work.

28 28-Feb-24 78 6:00 AM 7:00 PM 12.00 4.0 48.00 T-12_17th Fl. chiping work & RAC _ 4th
Fl. Chiping work.

29 29-Feb-24 79 6:00 AM 7:00 PM 12.00 4.0 48.00 T-12_24th Fl. chiping work & RAC_4th Fl.
Chiping work.
Total Hour of Work: 1758.00
Total no. of Chipper (8hrs/day): 220.00

Cummulative Qty. of Chipper (8hrs/day) : 527.00


Previous Qty. of Labour (8hrs/day): 307.00
This Bill Qty. of Labour (8hrs/day): 220.00